Section 166, The Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996
The Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 (27 of 1996) - Section 166
Text of section 166
166. Man-locks and working in compressed air environment:-The
employer shall ensure at a construction site of a building or other construction
work that—
(a) man-locks used at a tunnelling work are of adequate strength,
made of sound material and designed to withstand any air
pressure, internal or external, to which it may be subject to in
the normal use or in an emergency;
(b) (i) doors of man-locks at an excavation or tunnelling work are made
of steel;
(ii) man-locks used at a tunnelling work are airtight and
devices are provided for sealing the doors when such
locks are under pressure;
(iii) the anchorage of a man-lock used at tunnelling work
have adequate strength to withstand the pressure
exerted by air on the man-lock;
(iv) there is adequate room available for the building worker
for working in the man-lock used at tunnelling work;
(v) where work is carried out in any compressed air tunnel,
a man-lock in accordance with the relevant national
standards is used for such tunnel;
(c) (i) where a man-lock is used at tunnelling work, safety instructions
in Hindi and in local language understood by majority of building
workers employed therein are displaced at conspicuous place at
such tunnelling work;
(ii) except in an emergency, compression and
decompression operation are carried out in a man-lock
used at tunnelling work;
(iii) in a emergency any material lock may be used at
tunnelling work for compression and decompression of
building worker and a record is kept in writing and
produced for inspection on demand to the Inspector
having jurisdiction;
(iv) material-lock is used with the permission of Director
General for compression and decompression of building
workers, where it is impracticable to install both the
man-lock and the material-lock and the material-lock at
a tunnelling work;
(v) decompression of all building workers to atmospheric
condition at tunnelling work is carried out in accordance
Rule 166 The Building and Other Construction Workers‘ 73
(Regulation of Employment and Conditions of Service)
Central Rules, 1998
with a decompression procedure approved by the
Director General;
(vi) the man-lock at tunnelling work is not used for any
purpose other than compression or decompression of
building workers;
(vii) no decanting of building workers at tunnelling work is
carried out without prior approval of Director General,
except in an emergency;
(viii) in case a building worker collapses or is taken ill during
his decompression in a man-lock used at tunnelling
work, the lock attendant of such man-lock raises the
pressure in such man-lock until such pressure is equal
to the maximum pressure which that building worker
was exposed to in the working chamber prior to such
decompression and such lock attendant immediately
reports the matter relating to such collapse to the
medical lock attendant and medical officer on duty at
such tunnelling work;
(ix) a building worker who had previously received training
with a trained building worker to work in a compressed
air environment at tunnelling work is employed to work
independently in such a compressed air environment;
(x) a building worker who had undergone three
decompressions from a pressure exceeding one bar in a
period of eight hours at tunnelling work is not allowed to
enter a compressed air environment except for the
purpose of carrying out rescue work;
(xi) a building worker employed in a compressed air
environment for a period of eight hours in a day at
tunnelling works is not employed again in such
environment unless he has spent not less than twelve
consecutive hours of rest at atmospheric pressure;
(xii) no building worker is engaged in a compressed air
environment at a pressure which exceeds three bars at
tunnelling work unless prior permission, in writing, has
been obtained from the Director General for such
engagement;
(xiii) no building worker is employed in a compressed air
environment for more than fourteen consecutive days in
a month at tunnelling work;
(xiv) a register of employment of all building workers
employed in compressed air environment at tunnelling
work, is maintained;
(xv) an identification badge is supplied to a building worker
employed in compressed air environment at tunnelling
work;
(xvi) the badge of a building worker referred to in sub-clause
(xv) contains particulars of his name, location of the
medical lock allotted to him for work, the telephone
number of the construction Medical Officer concerned
for his treatment and the instructions in case of his
illness of unknown and doubtful causes;
74 The Building and Other Construction Workers‘ Rule 167
(Regulation of Employment and Conditions of Service)
Central Rules, 1998
(xvii) record of all identification badges supplied to building
workers under sub-clause (xvi), is kept in a register;
(xviii) every building worker whose name appears in the
register referred to in sub-cause (xvii) wears the badge
supplied to him under sub-clause (xv) at all times during
his duty hours at tunnelling work;
(xix) suitable warning signs are displayed, in the compressed
air environment at tunnelling work, for the prohibition of
following, namely:-
(a) use of alcoholic drinks;
(b) use and carrying of lighters, matches or other
sources of ignition;
(c) smoking; and
(d) an entry to person who has consumed alcoholic
drinks.
Previous and next
Questions people ask
Is section 166 of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 still in force?
No repeal of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 is recorded.