129. Depth of trenches:-The employer shall ensure at a construction site of
a building or other construction work that—
(a) where the depth of a trench requires two lengths of sheet pilling,
one above the other, the lower piling is set inside the bottom
strings or wales of the upper pilling and such sheet piling is
driven down and braced as the excavation continues;
(b) all metal sheet piles used in excavation or a trench are welded
end to end and secured by other similar means.
Previous and next
Questions people ask
Is section 129 of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 still in force?
No repeal of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 is recorded.