Section 74, The Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996
The Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 (27 of 1996) - Section 74
Text of section 74
74. Register of periodical test, examination and certificates thereof:-
The employer shall ensure at a construction site of a building or other
construction work that—
(a) a register in Form XXVI, annexed to these rules is maintained
and particulars of such test and examination of lifting
appliances, lifting gears and heat treatment as required under
rule 56, rule 62 and rule 72, are entered in such register;
(b) certificate in respect of each of the following is obtained from
competent person in the forms as mentioned below, namely:
(i) in case of initial and periodical test and examination
under rule 56 and rule 71, for—
(a) winches, derricks and their accessory gears in
Form V annexed to these rules;
(b) cranes or hoists and their accessory gears in
Form VI annexed to these rules;
Rule 77 The Building and Other Construction Workers‘ 49
(Regulation of Employment and Conditions of Service)
Central Rules, 1998
(ii) in case of test, examination and re-examination of loose
gears under clause (d) of rule 70 in Form VII annexed to
these rules;
(iii) in case of test and examination of wire ropes under rule
62 in form VIII annexed to these rules;
(iv) in case of heat treatment and examination of loose gears
under rule 72 in Form IX annexed to these rules;
(v) in case of annual thorough examination of the loose
gears under clause (b) of rule 70, except where required
particulars of such exemption have been enclosed in the
register referred to in clause (a), in Form XXVI, annexed
to these rules, and such certificates are attached to the
registered referred to in clause (a);
(c) the register referred to in clause (a) and the certificates referred
to in clause (b) attached to such register are—
(i) kept at such construction site in case such register and
certificate relate to lifting appliances, loose gear and wire
ropes;
(ii) produced on demand before an Inspector having
jurisdiction, and
(iii) retained for at least five years after the date of the last
entry made in such register;
(d) no lifting appliance or lifting gear in respect of which an entry is
required to be made in register referred to in clause (a) and
certificate of test and examination are required to be attached in
such register in the manner as specified in clause (a) or clause
(b), as the case may be, is used for building or other construction
work unless the required entries have been made in such
register and certificates.
Previous and next
Questions people ask
Is section 74 of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 still in force?
No repeal of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 is recorded.