LawGrids logoLAWGRIDS.ORG

Rule 13, The Punjab Regional and Town Planning and Development (General) Rules, 1995: Time within which building is to be completed

The Punjab Regional and Town Planning and Development (General) Rules, 1995 - Rule 13

Text of rule 13

Time within which building is to be completed

13. Time within which building is to be completed.–(1) The transferee shall complete the building as per the approved building plan within a period of three years from the date of possession of land, failing which he Estate Officer may resume the land or building or both, as the case may be in accordance with the provisions of section 45 of the Act. Providing that the Estate Officer may extent the period of three years, if he is satisfied that the building could not be completed by the transferee due to the reasons beyond the control of transferee on payment of such fee, as is specified in the table given below: Providing further that the period of extension shall not exceed twelve years, which shall be counted after the expiry of the period of three years from the date of possession of land.” Table (Fee for residential, commercial, Industrial land and the land allotted to institutions, housing societies and private builders). Number of years from which fee is to be charged Residential Commercial Land allotted to the institutions, housing societies, private builders and for industrial purposes 4th year 2% of the allotment price, fixed by the Authority at the time of extension. 2% of the auction price or allotment price as the case may be. 2% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 5th year 2% of the allotment price, fixed by the Authority at the time of extension 2% of the auction price or allotment price as the case may be. 2% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 6th year 2.5% of the allotment price, fixed by the Authority at the time of extension 2.5% of the auction price or allotment price as the case may be. 2.5% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 7th year 2.5% of the allotment price, fixed by the Authority at the time of extension 2.5% of the auction price or allotment price as the case may be. 2.5% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 8th year 2.5% of the allotment price, fixed by the Authority at the time of extension 2.5% of the auction price or allotment price as the case may be. 2.5% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 1 Rule 13 substituted by Punjab Govt. Notification No.1/149/1986-4HGI/1759 dated the 9 th June, 2010 4 9th year 3% of the allotment price, fixed by the Authority at the time of extension 3% of the auction price or allotment price as the case may be. 3% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 10th year 3% of the allotment price, fixed by the Authority at the time of extension 3% of the auction price or allotment price as the case may be. 3% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 11th year 3.5% of the allotment price, fixed by the Authority at the time of extension 3.5% of the auction price or allotment price as the case may be. 3.5% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 12th year 3.5% of the allotment price, fixed by the Authority at the time of extension 3.5% of the auction price or allotment price as the case may be. 3.5% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 13th year 4% of the allotment price, fixed by the Authority at the time of extension 4% of the auction price or allotment price as the case may be. 4% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 14th year 4% of the allotment price, fixed by the Authority at the time of extension 4% of the auction price or allotment price as the case may be. 4% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be. 1[15th year and above 4% of the allotment price, fixed by the Authority at the time of extension: Provided that after completion of the 15 th year, additional fee at the rate of 0.25% shall become payable every year at the time of extension over and above the previous year’s fee. 4% of the auction price or allotment price as the case may be: Provided that after completion of the 15 th year, additional fee at the rate of 0.25% shall become payable every year at the time of extension over and above the previous year’s fee. 4% of the allotment price, fixed by the Authority at the time of extension or auction price, as the case may be: Provided that after completion of the 15 th year, additional fee at the rate of 0.25% shall become payable every year at the time of extension over and above the previous year’s fee.] (2) The fee for the period of extension shall be paid by the transferee within a period of thirty days from the date of the order, made with regards thereto by the Estate officer: Provided that the period of thirty days may b extended by the Chief Administrator, if he is satisfied on the request of the transferee up to the period of six months from the date of request, falling which the transferee shall have to pay such penal interest as may be determined by the Authority. (3) The fee, as specified in sub-rule (1) shall be charged half yearly commencing from the 1 st day of January to 30 th June and from the 1 st day of July to 31 st December to the relevant year. (4) [Omitted] (5) [Omitted] (6) The period during which the serving soldiers and officers of the Amend Forces remained posted at 3 [family and non family stations outside the state of Punjab], the fee shall be waived of after due 1. Substituted vide Punjab Govt. Notification No. 1/49/1986-4HGI/1660 dated 31.05.2011. 5 consideration in the case of residential lands by the Chief Administration or any other officer, authorized by him for the purpose of constructing building on those lands. (7) The cases of legal heirs of the deceased, war windows next kin of police and para-military forces killed in action, allotees suffering from disease due to which they were not capable to carry out construction within the stipulated period, and the cases of officers or official of the State Government and Public Sector Undertakings of the State Government, who were required to server outside the State of Punjab in accordance with their service conditions shall be considered for waiving of extension fee only for residential lands by the Chief Administrator or any other officer authorized by him. (8) The case of charitable institutions (except the institutions to whom land has been allotted for educational and hospital purposes), which are exempted from income tax under the Income Tax Act, 1961, may be considered by the Authority or its Committee for waiving of extension fee up to eighty percent of the total extension fee, as specified in the table given below sub-rule (1) for the reasons, to be recorded in writing.]

Previous and next

All provisions of The Punjab Regional and Town Planning and Development (General) Rules, 1995

Questions people ask

Is rule 13 of the Punjab Regional and Town Planning and Development (General) Rules, 1995 still in force?

No repeal of the Punjab Regional and Town Planning and Development (General) Rules, 1995 is recorded.