22.(1) Except with the previous sanction of the Previous
Government, the Board shall not adopt or execute any sanction of
scheme or plan or carry out any works in connection Government
for certain
therewith, if the cost of such schemes, plans or other
schemes,
works exceeds or is likely to exceed-
plans and
works.
(a) Twenty five lakhs of rupees in the case of
replacement, reconstruction, structural, alterations,
adaptations, conversions, improved fixtures, fittings and
machinery and other works of improvement not involving
extensions enlargements or additions to existing works
or works previously in use; or
(b) Twenty five lakhs of rupees in the case of new
works including extensions, enlargements and additions
to existing works or works previously in use.
(2) Notwithstanding anything contained in sub-
section (1), the Board shall not, except with the previous
sanction of the Government, adopt or execute any
scheme or plan, if the cost of such scheme, plan or
other work is met or to be met with from the funds
provided by the Government.
Previous and next
All sections of The Tamilnadu Palm products Development Board Act 1994
Questions people ask
Is section 22 of the Tamilnadu Palm products Development Board Act 1994 still in force?
No repeal of the Tamilnadu Palm products Development Board Act 1994 is recorded.