Section 210, The Himachal Pradesh Municipal Act, 1994: Completion Certificate and lapse of sanction
The Himachal Pradesh Municipal Act, 1994 (13 of 1994) - Section 210
Text of section 210
Completion Certificate and lapse of sanction
210. Completion Certificate and lapse of sanction.- (1) Every
person shall, within one month after the completion of the erection of the
whole or part of the building, deliver or send or cause to be delivered or sent
to the Executive Officer a notice in writing of such completion or part of
completion accompanied by a certificate in the Form prescribed by bye-laws
made in this behalf and shall give to the Executive Officer all necessary
facilities for the inspection of such building or part of the building.
(2) No person shall occupy or permit to be occupied any such
building or use or permit to be used any building or part thereof until
permission has been granted by the Executive Officer in this behalf in
accordance with the bye-laws made under this Act:
Provided that if the Executive Officer fails within a period of thirty
days after the receipt of the notice of completion to communicate his refusal
to grant such permission such permission shall be deemed to have been
granted.
110
1[XXXXXXXXXXXXXXXXXXXXXXXXXX]
Previous and next
Questions people ask
Is section 210 of the Himachal Pradesh Municipal Act, 1994 still in force?
No repeal of the Himachal Pradesh Municipal Act, 1994 is recorded.