Section 246, The New Delhi Municipal Council Act, 1994: Period for completion of building or work

The New Delhi Municipal Council Act, 1994 (44 of 1994) - Section 246

Text of section 246

Period for completion of building or work

246. Period for completion of building or work.—The Chairperson, when sanctioning the erection of a building or execution of a work, shall specify a reasonable period after the commencement of the building or work within which the building or work is to be completed and if the building or work is not completed within the period so specified, it shall not be continued thereafter without fresh sanction obtained in the manner hereinbefore provided, unless the Chairperson on application made therefor has allowed an extension of that period.

Previous and next

All sections of The New Delhi Municipal Council Act, 1994

Questions people ask

Is section 246 of the New Delhi Municipal Council Act, 1994 still in force?

No repeal of the New Delhi Municipal Council Act, 1994 is recorded.