Section 9, The West Bengal Building ( Regulation Of Promotion Of Construction And Transfer By Promoters ) Act, 1993: Bar execution of mortgage etc. and refund of money, if such mortgage is executed, or for failure to give possession
The West Bengal Building ( Regulation Of Promotion Of Construction And Transfer By Promoters ) Act, 1993 (20 of 1993) - Section 9
Text of section 9
Bar execution of mortgage etc. and refund of money, if such mortgage is executed, or for failure to give possession.
9. (1) No promoter shall, after he enters into an agreement under
section 7, mortgage or create a charge on the flat or the land on which
such flat is constructed without prior consent of the person or persons
with whom such agreement is entered into.
(2) If any promoter—
(a) executes such mortgage or creates such charge without the
prior consent of the person or persons as aforesaid after the
agreement is registered under section 7, or
196
The West Bengal Building (Regulation of Promotion of Construction
and Transfer by Promoters) Act, 1993.
XX of 19931
(Section 10.)
(b) fails to give possession of a flat, duly completed, by the date
specified in the agreement or by the further date agreed to
by the parties, or
(c) is unable, for reasons beyond his control or beyond the
control of his agent, to give possession of the flat by the
date specified in the agreement under section 7 or by the
further date agreed to by the parties, and a period of three
months thereafter, or a further period of three months if
such reasons still exist, has elapsed,
the promoter shall, without prejudice to any other remedies to which he
may be liable under this Act or any other law for the time being in force,
be liable on demand to refund the amount already received by him in
respect of such flat with simple interest at the current bank rate from the
date of receipt of such amount till the date on which the amount and the
interest thereon is refunded, and the amount and the interest shall, subject
to any prior encumbrance, be a charge on the land and the building
thereon, if any, to the extent of the amount due:
Provided that—
(a) if the promoter wilfully delays the construction of the flat
and does not complete the construction thereof within the
period specified in the agreement under section 7 (hereinafter
referred to as the specified period), and gives possession of
the flat to the party after the expiry of the specified period,
he shall pay compensation at the rate of twelve per cent. of
the advance payment or deposit to the party for the period
commencing from the date following the date of expiry of
the specified period to the date of giving possession of the
flat, and such compensation shall be adjusted against the
price of the flat in such manner as may be prescribed, or
(b) if the promoter delays the construction of the flat beyond
the specified period without any prima facie reason therefor,
and the party expresses its unwillingness to take possession
of the flat as and when completed and claims refund of the
advance payment or deposit, the promoter shall refund the
advance payment or deposit and shall pay compensation at
the rate of twenty-five per cent. of such advance payment or
deposit.
Previous and next
Questions people ask
Is section 9 of the West Bengal Building ( Regulation Of Promotion Of Construction And Transfer By Promoters ) Act, 1993 still in force?
No repeal of the West Bengal Building ( Regulation Of Promotion Of Construction And Transfer By Promoters ) Act, 1993 is recorded.