Rule 13, Mineral conservation and Development Rules, 1988: Mining operations to be in accordance with mining plans
Mineral conservation and Development Rules, 1988 - Rule 13
Text of rule 13
Mining operations to be in accordance with mining plans
13. Mining operations to be in accordance with mining plans : -
(1) Every holder of a mining lease shall carry out mining operations in accordance with
the approved mining plan with such conditions as may have been prescribed under sub-rule (2)
of rule 9 or with such modifications, if any, as permitted under rule 10 or the mining plan or
scheme approved under rule 11 or 12 as the case may be.
(2) If the mining operations are not carried out in accordance with the mining plan as
referred to under sub-rule (1), the Regional Controller or the authorised officer may order
suspension of all or any of the mining operations and permit continuance of only such operations
as may be necessary to restore the conditions in the mine as envisaged under the said
mining plan.
Previous and next
All provisions of Mineral conservation and Development Rules, 1988
Questions people ask
Is rule 13 of Mineral conservation and Development Rules, 1988 still in force?
No repeal of Mineral conservation and Development Rules, 1988 is recorded.