Rule 11, Mineral conservation and Development Rules, 1988: Mining plan to be submitted by the existing lessee
Mineral conservation and Development Rules, 1988 - Rule 11
Text of rule 11
Mining plan to be submitted by the existing lessee
11. Mining plan to be submitted by the existing lessee :-
(1) Where mining operations have been undertaken before the commencement of these
rules without an approved mining plan, the holder of such mining lease shall submit a mining
plan within a period of one year from the date of commencement of these rules,
5
[ to the
Regional Controller or the authorised officer or the officer authorised in this behalf by the State
Government, as the case may be, for approval.]
(2) If a holder of a mining lease has not been able to submit the mining plan within the
specified time for reasons beyond his control, he may apply for extension of time giving reasons
to the following authorities :
______________________________________________________________________________
1. Inserted by G.S.R. 55 (E), dated 17.1.2000. 2. Ibid. 3. Ibid.
4. Substituted by G.S.R. 22 (E), dated 11.1.2002. 5. Substituted by G.S.R. 55 (E), dated 17.1.2000.
9
(a) to the Regional Controller for extension of time up to six months;
(b) to the Controller of Mines for extension of time exceeding six months but not
exceeding one year;
(c) to the Chief Controller of Mines for extension of time beyond one year;
1
[(d) to the officer authorised in this behalf by the State Government in respect of
mining plan approved by the State Government.]
2
[(3) The Regional Controller, Controller of Mines, the Chief Controller of Mines or the
authorised officer or the officer authorised in this behalf by the State Government, as the case
may be, on receiving an application made under sub-rule (2) may, on being satisfied, extend the
period for submission of the mining plan for the period mentioned in clause (a), (b), (c) or (d) of
the said sub-rule.]
(4) The Regional Controller
3
[or the officer authorised in this behalf by the State
Government, as the case may be,] may approve the plan as submitted by the lessee under sub-
rule (1) or may require modifications to be carried out in the plan and the lessee shall carry out
such modifications and resubmit the modified plan for
4
[omitted.] approval.
5
[(5) The Regional Controller or the officer authorised in this behalf by the State
Government, as the case may be, shall, within a period of 90 days from the date of receipt of the
mining plan or the modified mining plan, convey approval or disapproval to the applicant and in
case of disapproval shall also convey the reasons for disapproving the said mining plan or the
modified mining plan.]
(6) If no decision is conveyed within the period stipulated under sub-rule (5), the mining
plan or the modified mining plan, as the case may be, shall be deemed to have been provisionally
approved and such approval shall be subject to the final decision whenever communicated.
(7) The mining plan submitted under sub-rule (1) shall be prepared by a recognised
person.
Previous and next
All provisions of Mineral conservation and Development Rules, 1988
Questions people ask
Is rule 11 of Mineral conservation and Development Rules, 1988 still in force?
No repeal of Mineral conservation and Development Rules, 1988 is recorded.