Form H-6, Mineral conservation and Development Rules, 1988: FORM H-6
Mineral conservation and Development Rules, 1988 - Form H-6
Text of form H-6
FORM H-6
FORM H-6
For the financial year 1st April, 20__ to 31st March, 20____
ANNUAL RETURN
[See rule 45(5) (b)(vi)]
(Read the instructions carefully before filling the particulars)
To
(i) The Regional Controller of Mines
Indian Bureau of Mines
_________Region,
PIN:
(Please address to Regional Controller of Mines in whose territorial jurisdiction the mines falls as notified from time to time by the
Controller General, Indian Bureau of Mines under Rule 62 of the Mineral Conservation and Development rules, 1988)
(ii) The State Government
PART – I (General )
1. Details of Mine:
(a) Registration number allotted by Indian Bureau of Mines (to give registration
number of the mine owner/ agent/ mining engineer/ manager signing the return)
(b) Mine Code
(c) Name of the Mineral Mica
(d) Name of Mine
(e) Name(s) of other mineral(s),
if any, produced from the same mine
2. Location of the Mine :
Village
Post Office
Tahsil/Taluk
District
State and PIN Code
Fax no: E-mail:
Phone no:
3. Name and Address(s) of Lessee/Owner (along with fax no. and e-mail):
Name of Person
Street/Village
Post Office
Tahsil/Taluk
District
State and PIN Code
Fax no: E-mail:
Phone No:
4.Registered Office of the Lessee
5. Director in charge :
6. Agent :
7. Manager :
8.Mining Engineer in charge:
9. Geologist in charge :
10. Transferer (previous owner) if any, and date of transfer:
11. Particulars of area operated/Lease
(Furnish information on items (i) to (v) lease-wise in case mine workings cover more than one lease)
(i) Area under lease (hectares):
Under Forest
Outside Forest
Total
(ii) Date of execution of mining lease deed
(iii) Period of lease
(iv) Area for which surface rights are held (hectares)
(v) Date and period of renewal (if applicable)
(vi) In case there is more than one mine in the same lease area, indicate name of mine and mineral
produced
124
12. Lease area (surface area) utilisation as at the end of year (hectares):
Under
forest
Outside
forest
Total
(i) Already exploited & abandoned by opencast (O/C) mining
(ii) Covered under current (O/C) Workings
(iii) Reclaimed/rehabilitated
(iv) Used for waste disposal
(v) Occupied by plant, buildings, residential, welfare buildings & roads
(vi) Used for any other purpose (specify)
(vii) Work done under progressive mine closure plan during the year
13. Ownership/exploiting Agency of the mine:
(Public Sector/Private Sector/Joint Sector)
PART - II (Employment & Wages)
1.Number of technical and supervisory staff employed at the mine
Description Wholly employed Partly employed
(i) Graduate Mining Engineer
(ii) Diploma Mining Engineer
(iii) Geologist
(iv) Surveyor
(v) Other administrative clerical and technical supervisory staff
Total:-
2.(i) Number of days the mine worked:
(ii) No.of shifts per day:
(iii) Indicate reasons for work stoppage in the mine during the year (due to
strike, lockout, heavy rain, non-availability of labour, transport bottleneck, lack
of demand, uneconomic operations, etc.) and the number of days of work
stoppage for each of the factors separately .
Reasons No of days
3.(i) Employment of Labour and wages paid:-
Maximum number of persons employed on any one day during the year:
(i)In workings below ground on ......................(a).................
(ii)In all in the mine on ..........................(a).................
Classification
Total number of man days
worked during the year
No. of
days
worked
during
the year
Average daily number of
persons employed
Total Wages
/Salary bills for
the year
Direct Contract Total Male Female Total
(1) (2A) 2(B) 2(C) (3) 4(A) 4(B) 4(C) (5)
A. Below Ground
i) Foreman and mining mates
ii) Face workers and Loaders
iii) Others
B. Opencast workings :
i) Foreman and mining mates
ii) Face workers and Loaders
iii) Others
C. Above ground :
(i) Clerical & Supervisory Staff.
(excluding the superior
supervisory staff.)
(ii) Workers in any Attached
factory, Workshop or mineral
dressing plant.
(iii) Others
Total:
125
3. (ii) Total salaries paid to technical and supervisory staff employed in the mine during the year ( in Rs.)________________
PART-II A (Capital Structure)
1.Value of Fixed Assets* (Rs.'000)…………………………………………………………………………………………………………………….
(in respect of the mine, beneficiation plant, mine, work-shop, power and water installation)
Description
As at the
beginning of
the year
Additions
during the
Year
Sold or
discarded
during the
year
Depreciation
during the year
Net
closing
Balance
(2+3)-
(4+5)
Estimated
market
value**
1 2 3 4 5 6 7
(vi) Land***
(ii) Building:
Industrial
Residential
(iii) Plant and Machinery including
transport equipment
iv) Capitalised Expenditure such as pre-
production exploration, development,
major overhaul and repair to machinery
etc.(As prescribed under Income Tax
Act)
Total
* In case the fixed assets are common to more than one mine, furnish combined information for all such mines together in
any one of the mines return and also indicate the names of other mines in which the information relates in the form
provided above. In the returns for other mines, give only a cross reference to the particular mine's return where-in the
information is included.
** Optional and may be furnished in respect of items (i),(ii) and (iii) if the mine owner desires.
*** Including any non recurring expenditure incurred on the acquisition of land.
2. Source of Finance (as at the end of the year) :-
(i) Paid up Share Capital (Rs.'000)
(ii)Own Capital (Rs.’000)
(iii)Reserve & Surplus (All Types)
(iv)Long Term loans outstanding
Indicate the names of the leading institutions such as State Finance Corporation, Industrial Development and other Public
Corporations, Co-operative Banks, Nationalised Banks and other sources along with the amount of loan from each source and the
rate of interest at which loan has been taken.
3.Interest and Rent (in Rs.’000)
(i) Interest paid during the year
(ii) Rents (excluding surface rent) paid during the year
PART - III (Consumption of Materials)
1. Quantity and cost of material consumed during the year
Description Unit Quantity Value (Rs.)
(i) Fuel
(a) Coal Tonnes
(b) Diesel Oil l
(c) Petrol l
(d) Kerosene l
(e) Gas Cu m
(ii) Lubricant
(a) Lubricant oil l
(b) Grease kg
(iii) Electricity
(a) Consumed kWh
(b) Generated kWh
(c) Sold kWh
(iv) Explosives (furnish full details in Part IV)
(v) Tyres Nos.
(vi) Timber & Supports
(vii)Drill roads & kits Nos.
(viii)Other spares & stores
I
I
126
2. Royalty and Rents (in’ 000 Rs.):
X Paid for current year Paid towards past arrears
(a) Royalty
(b) Dead rent
(c) Surface rent
3. Compensation paid for felling trees during the year (in Rs)
4. Depreciation on fixed assets Rs
5. Taxes and cesses
X Amount in Rs. paid during the year to:
X Central Govt. State Govt.
(i) Sales Tax
(ii) Welfare cess
(iii) Other taxes & cesses:-
(a) Mineral cess
(b) Cess on dead rent
(c) Others (please specify)
6. Other expenses:
(i) Overheads
(ii) Maintenance
(iii) Money value of other benefits paid to workmen
(iv) Payment made to professional agencies
Part –IV ( Consumption of Explosives)
1. Licensed capacity of magazine: (specify unit separately in kg/tonne,
numbers, metres )
Item Unit Capacity
2. Total production during the year (Tonne):
3. Overburden removed:
Classification of Explosives Unit Quantity consumed during the year Estimated requirement
during the next year
Small dia.
(upto 32 mm)
Large dia. (above
32 mm)
Small dia.
(upto 32 mm)
Large dia. (above
32 mm)
1.Gun Powder kg
2.Nitrate Mixture kg X X X X
a.Loose ammonium nitrate
b.Ammonium nitrate in
cartridged form
3.Nitro compound kg
4.Liquid Oxygen soaked
cartridges
kg
5.Slurry explosives
(Mention different trade names)
kg
6.Detonators Nos. X X X X
i) Ordinary
ii) Electrical X X X X
(a) Ordinary
(b) Delay
7.Fuse Mts X X X X
(a)Safety Fuse
(b)Detonating Fuse
8.Plastic ignition cord Mts
9.Others (specify) (Mention the
unit)
Different sizes of soaked liquid oxygen cartridges to be equivalent kg. as per manufacturer’s instruction.
PART – V (General Geology & Mining)
(Details on items 1, 2, 6 & 7(i) may be given once in 5 years)
1. Mineral(s) worked and their characteristics : (In case more than one mineral is worked, the information asked for under (a) to (d)
in respect of the remaining mineral(s) may be furnished in a separate sheet and attached with the return)
(a) Name of mineral :
(b) Type of ore (Tick mark whichever is applicable)
127
(i) Lump
(ii) Fines
(iii) Friable
(iv) Granular
(v) Platy
(vi) Fibrous
(vii) Any other (specify), Powdery etc.
(c) Quality:
Chemical Analysis of Typical Grades Produced
------------------------------------------------------------------------------------------------------------------------------------------------------------------
Constituent Grade
------------------------------------------------------------------------------------------------------------------------------------------------------------------
1 2 3 4
------------------------------------------------------------------------------------------------------------------------------------------------------------------
(i) Size Range
(ii) Principal constituents
(iii) Subsidiary Constituents
------------------------------------------------------------------------------------------------------------------------------------------------------------------
2.(a) Name of rock/mineral excavated and disposed as waste:
(b) Name(s) of the ore/mineral excavated but not sold i.e., mineral reject:
(c) Typical analysis of mineral reject(s)
-----------------------------------------------------------------------------------------------------------------------------------------------------------------
Item 1. 2. 3. 4.
-----------------------------------------------------------------------------------------------------------------------------------------------------------------
Mineral reject
-----------------------------------------------------------------------------------------------------------------------------------------------------------------
3. Reserves and Resources estimated at the end of the year.
Classification Code Quantity Grade (as per NMI grades as
indicated in the mining plan)
(1) (2) (3) (4)
Total Mineral Resources (A + B)
A. Mineral Reserve
1. Proved Mineral Reserve
2. Probable Mineral Reserve
B. Remaining Resources
1. Feasibility Mineral Resource
2. Prefeasibility Mineral Resource
3. Measured Mineral Resource
4. Indicated Mineral Resource
5. Inferred Mineral Resource
6.Reconnaissance Mineral Resource
111
121 and 122
211
221 and 222
331
332
333
334
Note.- For the removal of doubts, the classification terms and codes mentioned in this Form shall have the same meaning as assigned to them
in the Guidelines issued by Indian Bureau of Mines in this regard.
4. Mining Operations during the year:
4.1. Exploration
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
Item Number Meterage Grid/Dimension
(as applicable)
------------------------------------------------------------------------------------------------------------------------------------------------------------------
Drilling
Trenching
Pitting
------------------------------------------------------------------------------------------------------------------------------------------------------------------
4.2 Opencast
(A) Details of Benches (Separately for mechanised and manual sections)
------------------------------------------------------------------------------------------------------------------------------------------------------------------
In ore In OB/Waste
(i) Number of Benches
(ii) Average height (metres)
(iii) Depth of the deepest working from adjacent ground (M):
------------------------------------------------------------------------------------------------------------------------------------------------------------------
(B) (i) Total ROM Ore production (tonnes):
(ii) Mineral Rejects generated with grades (tonnes):
128
(C) Total quantity of Overburden/Waste removed during the year (tonnes)
-----------------------------------------------------------------------------------------------------------------------------------------------------------------
During the year Cumulative so far
-----------------------------------------------------------------------------------------------------------------------------------------------------------------
(i) Quantity back filled
(ii) Quantity disposed of in external dumps
-----------------------------------------------------------------------------------------------------------------------------------------------------------------
4.3 Underground:
(a) Driving (metres) in ore:
(b) Cross Cutting/Footwall Drives (in barren) (Metres) :
(c) Winzing (metres):
(d) Raising (metres):
(e) Shaft sinking (metres):
(f) Stope preparation (metres):
(g) Tonnage of ore blocked for stoping (tonnes):
(h) Quantity of waste removed (tonnes):
(i) Quantity of mineral rejects generated with grade (tonnes):
Within lease area Outside lease area
4.4 i) Number of trees planted during the year
ii) Survival rate in percentage
5. Type and aggregate Horse Power of Machinery: Give the following information for the types of machinery in use such as hoist, fans, drills,
loaders, excavators, dumpers, haulages, conveyors, pumps, etc. Details of any new machinery added during the year may be furnished with cost.
Type of
machinery
Capacity of
each unit
No.of units
H.P. of
each
unit
Electrical/non
electrical
(specify)
Used in
opencast/
underground(specify)
6.(i) Give details of future plans, if any, of exploration and development, production schedule, replacements and expansion of machinery and
equipment etc.
(ii) If you have laboratory facilities for R & D and if so, give a brief description:
7.(i) Details of mineral Treatment Plant, if any. Give a brief description of the process capacity of the machinery deployed and its availability.
(Enclose Flow Sheet and Material Balance of the Plant).
(ii) Furnish following information every year:
Item Tonnage Average Grade
Feed:
Concentrates :
By-products/Co-products:
Tailings:
8. Furnish surface and/or underground plans and sections as prepared and brought uptodate (as required under rule 28 of MCDR)
9. Please indicate the salient features which affected mining operations during the year.
PART-VI (PRODUCTION, DESPATCHES AND STOCKS)
1[ 1. Production, despatches and stocks of crude and dressed mica ( in kilograms)
Crude (r.o.m) Waste/scrap mica
obtained incidental to
mining
Waste/ mica obtained after
preliminary dressing (at mine site)
1 2 3 4]
A. OPENING STOCKS
(at the Beginning of the month)
i) at Mine
ii) at Dressing unit
iii) at any Other point(Please specify)
Total (Opening Stock)
B. Production
i)From underground mining
1. Substituted by GSR 330(E), dated 10.4.2003
I I
129
ii)From opencast mining
iii) From dump working
Total
(Production)
C. DESPATCHES
i)for dressing
ii)for Sale
Total
(Despatches)
D.CLOSING STOCKS
i)At mine
(ii)At dressing unit
(iii)At any other point
(Please specify)
Total
(Closing Stocks)
E. Ex-mine price(#)
(Rs. Per kg)
(#)This should be estimated for all crude mica/ waste mica produced whether sold or not on the basis of the average sale price obtainable for
crude/ waste mica in the market. To arrive at the ex-mine price from this notional sale price, the cost of transport from the mine head to the
market or factory and any other incidental charges may be deducted .
2. Details of Deductions used for computation of Ex-Mine price (Rs/kg):
Deduction claimed Unit ( in Rs/kg) Remarks
a) Cost of transportation
(indicate Loading station and Distance from
mine in remarks)
b) Loading and Unloading charges
c) Railway freight ,if applicable
(indicate destination and distance)
d) Port Handling charges/export duty(indicate
name of port)
e) Charges for Sampling and Analysis
f) Rent for the plot at Stocking yard
g) Other charges(specify clearly)
Total (a) to (g)
3. Sales/ Despatches effected for Domestic Consumption and for Exports:
Grade
Nature of Despatch
(indicate whether
for Sale or Captive
consumption or
Export)
For Domestic Consumption For export
Consignee name and
Registration number
as allotted by the
Indian Bureau of
Mines to the buyer ##
Quantity Sale value Country Quantity F.O.B
Value(Rs.)
## Consignee name and Registration number as allotted by the Indian Bureau of Mines to the buyer
(to indicate separately if more than one buyer) for the top five despaches in terms of Quantity for the remaining consolidated figure shall be
reported with details of despatches as annexure.
NOTE:- Mine owners are required to substantiate domestic sale value/ FOB value for each grade of ore quoted above with copy of invoices.
5. Give reasons for increase/decrease in production/nil production (of primary or associate mineral), if any, during the month compared
to the previous month.
a)
b)
c)
6. Give reasons for increase/decrease in grade wise ex-mine price (of primary or associate
Mineral),if any, during the month compared to the previous month.
a)
b)
c)
130
PART-VII: COST OF PRODUCTION
Cost of production per kilogram of ore/mineral produced
Item Cost per kilogram
(i) Direct Cost
(a) Exploration
(b) Mining
(c) Beneficiation(Mechanical Only)
(ii) Over-head cost
(iii) Depreciation
(iv) Interest
(v) Royalty
(vi) Taxes
(vii) Dead Rent
(viii) Others (specify)
Total
Note: Information given under Part VI will be kept confidential, if required. The Government, however, will be free to utilize the information for
general studies without revealing the identity or working cost of the firm.
VERIFICATION
I certify that the information furnished above is correct and complete in all respects.
Place: Signature
Date: Name in full:
Designation: Owner/Agent/
Mining Engineer/Manager
131
Previous and next
All provisions of Mineral conservation and Development Rules, 1988
Questions people ask
Is form H-6 of Mineral conservation and Development Rules, 1988 still in force?
No repeal of Mineral conservation and Development Rules, 1988 is recorded.