Section 15, THE JAMMU AND KASHMIR CONTROL OF BUILDING OPERATIONS ACT, 1988: Finality of orders
THE JAMMU AND KASHMIR CONTROL OF BUILDING OPERATIONS ACT, 1988 (15 of 1988) - Section 15
Text of section 15
Finality of orders
15. Finality of orders.––Save as otherwise provided in this Act every
order made by an Authority or the appellate officer shall be final and shall not
be called in question in any suit, application or execution proceeding.
Previous and next
All sections of THE JAMMU AND KASHMIR CONTROL OF BUILDING OPERATIONS ACT, 1988
Questions people ask
Is section 15 of THE JAMMU AND KASHMIR CONTROL OF BUILDING OPERATIONS ACT, 1988 still in force?
No repeal of the JAMMU AND KASHMIR CONTROL OF BUILDING OPERATIONS ACT, 1988 is recorded.