Section 5, The Himachal Pradesh Slum Areas (Improvement and Clearance) Act, 1979
The Himachal Pradesh Slum Areas (Improvement and Clearance) Act, 1979 (19 of 1979) - Section 5
Text of section 5
5. Enforcement of notice requiring execution of works of
improvement.-(1) If a notice under section 4 requiring the owner of
thebuilding to execute works of improvement is not complied with, thenafter
theexpiration of the time specified in the notice the competent authority may
itselfdo the works required to be done by the notice.
(2) All expenses incurred by the competent authority under this
section, together with interest, at such rate as the State Government may by
order fix, from the date when a demand for the expenses is made till payment,
may be recovered by the competent authority from the owner of the building
as arrears ofland revenue:
Provided that if the owner proves that he-
(a)is receiving the rent merely as agent or trustee for someother
person; and
(b)has not in his hands on behalf of that other person sufficient money
to satisfy the whole demand of the authority, his liability shall be
limited to total amount of the money which he has in his hand as
aforesaid.
(3) If the owner of the building is different from the person who owns
the land on which the building stand~ and the expenses incurred by the
competent authority under this section arc recoverable from both these
persons then, expenses shall be recovered from them in such proportion as
may be determined by the competent authority or byan officer empowered by
it in this behalf.
Previous and next
All sections of The Himachal Pradesh Slum Areas (Improvement and Clearance) Act, 1979
Questions people ask
Is section 5 of the Himachal Pradesh Slum Areas (Improvement and Clearance) Act, 1979 still in force?
No repeal of the Himachal Pradesh Slum Areas (Improvement and Clearance) Act, 1979 is recorded.