Rule 15, 1The Haryana Development and Regulation of Urban Area Rules, 1976 Dated 7th March, 1976: Execution of works [Section 24]
1The Haryana Development and Regulation of Urban Area Rules, 1976 Dated 7th March, 1976 - Rule 15
Text of rule 15
Execution of works [Section 24]
15. Execution of works [Section 24]— The colonizer shall 150[start] the
laying out of the colony and development works within a period of three months
of the grant of licence under rule 12 and shall complete the same before the
expiry of the period of licence.
15A. 151[Extension of time for construction of community sites
[Section 3(3)].—(1) In case the licensee, the purchaser or the person
147 In Clause (v), for the words “the licence”, the words “the licence for verification” shall be substituted by
Har. Govt. Gaz. Final Notification No. 5479 dated 9.2.2018
148 Sign {.} substituted by Hr. Govt. Gaz. Noti. No. PF-69/2016/23910 dated 31.10.2016 at page 5924
149 Proviso inserted by Hr. Govt. Gaz. Noti. No. PF-69/2016/23910 dated 31.10.2016 at page 5924
150 Substituted by Haryana Govt. Gaz. Noti. No. 5DP-94/13852 dated 16.12.1994 published on 21.2.1995
151 Inserted by Haryana Govt. Gaz. Notification No. Misc-2218-II/2019/20083 dated 20.08.2019.
[56]
claiming through him fails to construct and use the site for the purpose it
was meant for in the prescribed period, he may apply to the Director or any
other person authorised by him for the purpose for grant of extension in
time for construction of such community site in form LC-VIIA, at least
thirty days before the expiry of such time limit for construction, and the said
application shall be accompanied by:-
(a) proof of ownership of community site in case the extension is
sought by an applicant other than the licencee;
(b) proof of online payment of extension fees;
(c) an explanatory note indicating the details of progress made with
regard to construction of such community site;
(d) any other document which the Director may require for the
purpose of this rule.
(2) On receipt of an application under sub-rule (1), the Director or any other
person authorised by him for the purpose shall, grant an extension in form
LC-VIIB for a period of one year to five years at a time, in the block of one
year. The extension fees shall also be recoverable in a block of one year
period.
(3) In case the Director is not so satisfied, he shall reject the application and
issue rejection orders in form LC-VIIC.”
16. 152
[Completion certificate/Part Completion Certificate [Section
24].— 153[(1) After the colony has been laid out according to approved layout
plans and development works have been executed according to the approved
designs and specifications, the coloniser shall make an application to the
Director in Form LC-VIII alongwith a demand draft on account of Infrastructure
Augmentation Charges as per the rates prescribed in the Schedule-B of these
rules if not paid earlier in accordance with the provision of Section 3(7) of the
Act.]
(2) After such 154[scrutiny], as may be necessary, the Director may issue a
2[completion certificate/part completion certificate] in form LC-IX or refuse to
issue such certificate stating the reasons for such refusal:
Provided that the colonizer shall be afforded an opportunity of being
heard before such refusal.
Previous and next
Questions people ask
Is rule 15 of 1The Haryana Development and Regulation of Urban Area Rules, 1976 Dated 7th March, 1976 still in force?
No repeal of 1The Haryana Development and Regulation of Urban Area Rules, 1976 Dated 7th March, 1976 is recorded.