Rule 7, Water (Prevention and Control of Pollution) (Consent) Madhya Pradesh Rules, 1975: Emergencies
Water (Prevention and Control of Pollution) (Consent) Madhya Pradesh Rules, 1975 - Rule 7
Text of rule 7
Emergencies
7. Emergencies. - In case of emergencies when the water quality of the stream
suddenly deteriorates the applicant shall co-operate with the Board and if necessary
close down certain operations to prevent undue pollution in the streams as a
temporary measure.
1.As substituted vide Notification No F-5-l21132/90 dated 27/12/97
2. As inserted vide Notification No. 13-117/32/90 dated 4-4-91
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
SCHEDULE
[See ruI4(Viii)]
OFFICE OF THE MADHYA PRADESH STATE PREVENTION AND
CONTROL OF WATERPOLLUTION BOARD. 87 MALVIYA NAGAR,
BHOPAL-3
CONSENT FORM
No. /WPCB/ Bhopal, Dated the ................................................
Subject.- Consent to……………………………………………………………….
for the discharge of effluent under section 25/26 of the Water (Prevention and Control
of Pollution) Act 1974.
Reference.-Application No.............................................................................................
......................................................................of…………………………………………
……….……… dated (expiry date...................................................................................
With reference to the above application for Consent to discharge effluent in to
the natural water courses under the Water (Prevention and Control of Pollution) Act;
1974. here in after referred to as the Act is authorised by the State Board to
discharge its industrial and other effluents arising out of their premises into the local
stream/river/well in accordance with the general, and special conditions as
mentioned in the Annexure.
2. This Consent shall be valid for a period of 12 months only commencing
from......................Dated this…………………………..day of………….19
For and on behalf of the Madhya Pradesh State Prevention and Control of Water
Pollution Board:
Seal Member-Secretary
enclosure: Annexure
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
ANNEXERE
ENCLOSURE TO REFERENCE LETTER ISSUED TO
M/s…………………………………………………………………………………
VIDE CONSENT No...................... ................................. /WPCBI7 5, Dated……
A- GENERAL CONDITIONS:
All discharges, authorised shall be consistent with the terms and conditions of
this Consent. Facility expansions, production increases, or process modifications
which result in new or increased discharges of pollutants must be reported by
submission of a new Consent application or if such new or increased discharges does
not violate the effluent limitations specified in this Consent, by submission to the
Board details of such new or increased discharges of pollutants in which case the
Consent may he modified to specify effluent limitations for any pollutants not
identified and limited herein. The discharge of any pollutant more frequently than or
at a level in excess of that identified and authorised by this Consent shall constitute a
violation of the terms and conditions of this Consent.
2. After notice and opportunity for the hearing, this consent may be modified,
suspended or…….)ked by the Board in whole or in part during its term for calise
including, but not limited to, the following
(a) Violation of any terms and conditions of this Consent;
(b) Obtaining this Consent by misrepresentation or failure to disclose fully all relevant
facts;
(c) A change in any condition that requires temporary or permanent reduction or
elimination of the authorised discharge.
3. Notwithstanding para (2) above, if a toxic eft1uent standard or prohibition
(including any schedule of compliance specit1ed in such effluent standard or
prohibition) is established for a toxic pollutant which is present in the discharge
authorised herein and such standard or prohibition is more stringent that any
limitation upon such pollutant in this consent, the Consent shall be revised or
modified in accordance with the toxic effluent standard or prohibition that the Board
may consider and the applicant shall be so notified.
4. The applicant shall allow the staff of the Madhya Pradesh State Prevention
and Control of
Water Pollution Board, and/or their authorised representatives, upon the
representation of credentials;
(a) To enter upon the applicant's premises where an eft1uent source is located
or in which any records are required to be kept under he terms and
conditions of this Consent;
(b) To have access to and copy at reasonable times any records required
to be kept under the terms and conditions of this Consent;
(c) To inspect at reasonable times any monitoring equipment or monitoring
method required in this Consent; or,
(d) To sample at reasonable times any discharge or pollutants.
5. The applicant shall at all times maintain in good working order and operate as
efficiently as possible all treatment or control facilities/or systems installed or used by
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
him to achieve compliance with the terms and conditions of this Consent.
6. The issuance of this Consent does not convey any property rights in either real
or personal property, or any exclusive privileges, nor does it authorise any injury to
private property or any invasion of personal rights, nor any infringement of Central,
State of local laws or regulations.
7. This Consent does not authorise or approve the construction of any physical
structures or facilities or the undertaking of any work in any natural water course.
8. The specit1c effluent limitations and other pollution controls applicable to the
discharge permitted herein are set forth below in specific conditions. Also set forth
below are self-monitoring and reporting requirements. Unless otherwise specified, the
applicant shall submit duplicate original copies of all reports to the Madhya Pradesh
State Prevention and Control of Water Pollution Board. Except for data determined to
be confidential, all such report shall be available for public inspection at the office of
the Madhya Pradesh State Prevention and Control of Water Pollution Board.
Knowingly making any false statement on any such report may result in the
imposition of criminal penalties as provided for in section 42 of the Act.
B. SPECIAL CONDITIONS:
1. Initial Effluent limitations.- During the period beginning on the effective date
of his consent and lasting until ………………………………..discharge from
outfalls shall be limited and monitored by the applicant as specified below:
(a) The following shall be limited and monitored by the applicant as specified:
_____________________________________________________________________
EFFLUENT DISCHARGE LIMITATION MONITORING
REQUIREMENT
CHARACTERI STI CS
___________________________________________________________
AVERAGE MAXIMUM Frequency Type of
Mg/l kgs/day Mg/l kgs/day *measurement sample
_____________________________________________________________________
*Daily//weekly/Monthly/ Trimonthly
+Grab/24 Hpur. Composite.
In addition to above, discharge shall be limited and monitored as specified below;
_____________________________________________________________________
EFFLUENT DISCHARGE LIMITATION MONITORING
CHARACTERI STI CS REQIOREMEN
AVERAGE MAXIMUM Frequency Type of
Mg/l kgs/day Mg/l Kgs/day
_____________________________________________________________________
*daily/Weekly /Monthly /Trimonthly
+Grabl24 hour. Composite.
_____________________________________________________________________
For the purpose of this sub-section, the daily average discharge is the total
discharge by weight during the calendar month divided by the number of days in a
month the production or commercial facility' was operating.' For the purpose of this
sub-section the daily maximum discharge means the total discharge by. weight during
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
any calendar day.
(b) The pH shall not be less than 5.5 or greater than 9.0
2. Final Eft1uent Limitation.-During the period beginning ................and lasting
until the date of expiration of this Consent ,discharge from the outfalls shall be limited
and monitored by the applicant as specified below:.........................................................……………………..
(a) The following shall be limited' and monitored by the applicant as specified.
____________________________________________________________________
EFFLUEMENT DISCHARGE LIMITATION MONITORING
CHARACTERISTICS REQUIREMENT
AVERAGE MAXIMUM Frequency type of -7
Mg/l Kgs/day Mg/l Kgs/day *Measurement Sample
____________________________________________________________________
____________________________________________________________________
* dailyWeekl¥/Monthy/Trimonthly +Grab/24 Hour. Composite.
____________________________________________________________________
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
Additionally, outfall shall be monitored as follows:
(i) Flow, Temperature and Total solids-one per month;
Grab samples, Maximum discharge Temperature above upsteam receiving water
shall be in accordance with the standard of ISI at 4()0 F.Uniform as per ISI 40° F.The
temperature shall be monitored once per month on each outfall. For the purposes of
this subsection, the daily average discharge is the total discharge by weight during the
calendar month divided by the number of days in the month that the production or
commercial facility was operating. For the purpose of this sub-section, the daily
maximum discharge, means the total discharge by weight during any calendar day.
(b) The pH shall not be less than 5.5 or greater than 9.0 for out falls. The
samples are taken as monthly, grab samples.
3.Schedule of Compliance for Effluent Limitations. The applicant shall achieve
compliance with the effluent limitations specified above for discharge from outfalls in
accordance with the following schedule.- .
(i) Report of Progress;
(ii) Completion of final plans by;
(iii) Award of contract or other commitment of financing;
(iv) Commencement of construction by;
(v) Report of construction progress;
(vi) Completion of construction by;
(vii) Attainment of operational level by;
(b) The applicant shall submit to the Consent Issuing Authority the required
report of progress or where a specified action is required in Ca) above to be taken by a
certain date, a written notice Qf compliance or non-compliance with each of the above
scheduled dates, post marked on later than.14 days following each elapsed date. Each
notice of non-compliance shall include the following information:- .
(1) A short description of the non-compliance;
(2) A description of any action taken or proposed by the applicant to comply
with the elapsed scheduled requirement without further delay;
(3) A description of any factors which tend to explain or mitigate the non
compliance; and (4) An estimate of the date, the applicant will comply
with the elapsed schedule requirement. and, assessment of the possibility
that the applicant will meet the next scheduled requirement in time.
(4) Compilation of Monitoring Data.-(a) Samples and measurement taken to
meet the monitoring requirements specified above shall be representative
of the volume and nature of monitored discharge.
(b) Following promulgation of guidelines establishing test procedures for the
analysis of pollutants, all sampling and analytical methods used to meet the
monitoring requirements specified above shall conform to such guidelines. Unless
otherwise specified sampling and analytical methods shall conform to the latest
edition of the Indian Standard specifications and where it is not specified the
guidelines as per standard methods for the examination of Water and Waste Waters
18th Edition of the American Public Health Association, New York. U.S.A. shall be
used.
(c) The applicant take samples and measurement to meet the monthly
requirements specified above at the location indicated below;
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
Point of sampling:
(i) Outfalls of waste.
(ii) 100 meters from point of confluence, down stream river or lake.
5. Recording of Monitoring activities and Results.-(a) The applicant shall make and
maintain records of all information resulting from monitoring activities required by
this Consent.
(b) The applicant shall record for each measurement or samples taken pursuant to the
requirements of this consent the following information:
(I) the date, exact place and time of sampling;
(2) the dates on which analysis were performed;
(3) who performed the analysis;
(4) the analytical techniques or methods used ; and
(5) the results of all required analysis.
(c) If the applicant monitors any pollutant more frequently as is required by this
Consent he shall include the results of such monitoring in the calculation and
reporting, of values required in the discharge monitoring reports which may be
prescribed by the Board. Such increased frequency shall be indicated on the discharge
Monitoring Report form.
(d) The applicant shall retain for a minimum of 3 years all records of monitoring
activities and results including all records of calibration and maintenance of
instrumentation and original strip chart regarding from continuous monitoring
instrumentation. This period of retention shall be extended during the course of any
unresolved litigation regarding the discharge of pollutants by the applicant or when
requested by the Central or State Board.
6.Reportion of Monitoring Results.(a) Monitoring information required by this
Consent shall be summerised and reported by submitting a Discharge Monitoring
Report Form duly filled in and signed, to the Board's office at the following address:
"Madhya Pradesh State Prevention and Control of Water Pollution Board,
87, Malviya Nagar, Bhopal-3 (Pin No. 462 003)" (b) Each submitted Discharge
Monitoring Report shall be signed as follows:-.
(i) If submitted by Corporation-by a Principal Executive Officer of at least the
level of VicePresident or his duly authorised representative, if such
representative is responsible for the overall operation of the facility from
which in discharge described in the discharge Monitoring Report originates.
(ii) If submitted by a partnership, by a general partner.
(iii) If submitted by a sole proprietor, by the proprietor,
(iv) If submitted by a Municipal. State or Central Government or other public
enterprise, by a principal Executive officer, ranking elected official,
Commanding officer, or other duly authorised employee.
(c) All information submitted on the Discharge Monitoring Form shall be based upon
measurements and sampling carried out during the three previous calendar months.
The first Discharge Monitoring Report shall be submitted for a period ending 60 days
from issuance. Thereafter, reporting periods shall end on the last date of each month.
The applicant shall submit a discharge Monitoring Report post marked no later than
28th day of the month following each completed reporting period.
7. Limitation of Discharge of Oil and Hazardous Substances in harmful quantities:-
The applicant shall not discharge oil in quantities defined as harmful in regulations. In
addition, the applicant shall not discharge hazardous substances into natural water
Water (Prevention and Control of Pollution)(Consent) Madhya Pradesh, Rules 1975
Madhya Pradesh Pollution Control Board, Bhopal
course in quantities defined as harmful in regulations promulgated by the Board.
Nothing in this Consent shall be deemed to preclude the institution of any legal
action-nor relieve the applicant from any responsibilities, liabilities or penalties to
which the applicant is or may be subject to clauses.
Previous and next
All provisions of Water (Prevention and Control of Pollution) (Consent) Madhya Pradesh Rules, 1975
Questions people ask
Is rule 7 of Water (Prevention and Control of Pollution) (Consent) Madhya Pradesh Rules, 1975 still in force?
No repeal of Water (Prevention and Control of Pollution) (Consent) Madhya Pradesh Rules, 1975 is recorded.