Form F, HOUSING BOARD HARYANA (Execution of Agreement) RULES, 1975: Form F
HOUSING BOARD HARYANA (Execution of Agreement) RULES, 1975 - Form F
Text of form F
Form F
Form F
[See rule 4(2)]
Housing Board, Haryana
---------------------------------Division
District
-------------------------------Sub-Division
Percentage Rate Tender and Contract For Works
-------------------------------------------------------------------------
General Rules and Directions for the Guidance of Contractors
1. All work proposed for execution by contract will be notified in a form of invitation to tender
posted on a board hung up in the office of and signed by the Sub-Divisional
Engineer/Executive Engineer.
This form will state the work to be carried out, as well as the date for submitting and opening
tenders and the time allowed for carrying out the work, also the amount of earnest money to be
deposited with tender, and the amount of the security deposit to be deposited by the successful
tenderer and the percentage, if any, to be deducted from bills. Copies of the specification, designs
2 / 16
and drawings Estimated rates/Common Schedule rates and any other documents required in
connection with the work, signed for the purpose of identification by the Sub-Divisional
Engineer/Executive Engineer shall also be open for inspection by the contractors at the office of the
Sub-Divisional Engineer/Executive Engineer during office hours.
2. In the event of the tender being submitted by a firm, it must be signed separately by each
member thereof, or, in the event of the absence of any partner, it must be signed on his
behalf by a person holding a power of attorney authorising him to do so.
3. Any person who submits a tender shall fill up the usual printed form, stating at how much
per cent above or below the rates specified in Rule 1 he is willing to undertake the work.
Only one rate of percentage more or less on all the Estimates rates/Common Schedule rate
shall be named. Tender which proposes any alteration in the work specified in the said form
of invitation to tender, or in time allowed for carrying out the work, or which contain any
other conditions of any sort, will be liable to rejection. No single tender shall include more
than one work, but contractors who wish to tender for two or more works shall submit a
separate tender for each. Tenders shall have the name and number of the work to which
they refer written outside the envelope.
4. The Executive Engineer or his duly authorized assistant will open tender in the presence of
any intending contractors or their authorized Agents who may be present at the time, and
will enter the amount of the several tenders in a Comparative Statement in a suitable form.
In the event of a tender being accepted a receipt for the earnest money forwarded therewith
shall thereupon be given to the contractors who shall thereupon for the purpose of
identification sign copies of the specification and other documents mentioned in Rule 1. In
the event of a tender being rejected, the earnest money forwarded with such unaccepted
tender shall thereupon be returned to the contractor making the same.
5. The Executive Engineer shall have the right of rejecting all or any of the tenders.
6. The Board may refuse or suspend payments on account of a work when executed by a firm
or by contractors described in their tenders as a firm, unless receipts are signed by all the
partners, or one of the partners, or some other person produces written authority enabling
him to give effectual receipts on behalf of the firm.
7. The receipt of an accountant or clerk for any money paid by the contractor will not be
considered as any acknowledgement of payment to the Sub-Divisional Engineer, Executive
Engineer and the contractor shall be responsible for seeing that he procures receipt signed
by the Sub-Divisional Engineer/Executive Engineer.
8. The memorandum of work tendered for and the memorandum of materials to be supplied
by the Housing Board, Haryana and their issue rates shall be filled in and completed in the
office of the Sub-Divisional Engineer/Executive Engineer before the tender form is issued. If
a form is issued to an intending tenderer without having been so filled in and completed, he
shall request the office to have this done before he completes and delivers his tender.
Tender for Works
3 / 16
I/We hereby tender for the execution for the Chairman of the Housing Board, Haryana hereinafter
referred to as Board of the work specified in the underwritten memorandum within the time
specified in such memorandum at_________* per cent below/above the rates entered in the
estimate/Interim common scheduled rates mentioned in Rule 1 and in accordance in all respects
with the specification drawings, and instructions in writing referred to in rule I hereof and in clause 2
of the annexed conditions and with such materials as are provided for and by in all other respects
in accordance with such conditions so far as applicable.
Memorandum
(a) General description ..
(b) Estimated cost .. Rs.
(c) Earnest money .. Rs.
* In figures as well as in words.
(a) If several sub-works are included they should be detailed in a separate list.
(b) This deposit will vary from 1 per cent to 10 per cent of the estimated cost of the work
according to the requirements of the case.
(c) This percentage, where no security deposit is taken will vary from 5 per cent to 10 per cent of
the estimated cost of the work according to the requirements of the case. Where security
deposit is taken, see note to clause 1 of conditions of contract.
(d) Security deposit (including earnest money), ___. Rs
(e) Percentage, if any, to be deduced from bills
Rs. (Rupees per cent) ___.
(f) Time allowed for the work from date of written order to
commence
___. Months
Shall this tender be accepted I/We hereby agree to abide by and fulfil all the terms and provisions
of the said conditions of contract annexed hereto so far as applicable or in default thereof to forfeit
and pay to the Board or its successors in office the sum of money mentioned in the said conditions.
The sum of Rs. _________. [Deposited, - vide Board Receipt number ________ dated
_______________________________ as earnest money the full value of which is to be absolutely
forfeited to the Board or its successors in office, without prejudice to any other rights or remedies of
the said Board or its successor in office, should I/We fail to commence the work specified in the
above memorandum otherwise the said sum of Rs. _______________ shall be retained by Board
on account of the security deposit specified in clause 1(B) of the said conditions of the contract.]
Dated the _________________, day of ____________________ 19 .
4 / 16
Signature of contractor before submission of tender.
Signature of witness to contractor's signature.
Witness :
Address :
Occupation :
The above tender is hereby accepted by me on behalf of Board.
Dated the________________, day of ____________________197 .
Executive Engineer,
_____________Division.
Signature of the officer by whom accepted.
Conditions of Contract
Clause 1. Security Deposit. - The person/persons whose tender may be accepted (hereinafter
called the contractor) shall permit Board at the time of making any payment to him for work done
under the contract to deduct such sum as will (with the earnest money deposited by him) amount
to* 10 per cent of all moneys so payable. Such deductions to be held by Board by way of security
deposit. All compensation or other sums of money payable by the contractor to Board under the
terms of his contract may be deducted from the security deposit or from any sums which may be
due or may become due to the contractor by Board on any account whatsoever, and the event of
his security deposit being reduced by reason of any such deduction the contractor shall within ten
days thereafter make good in cash or Government securities endorsed as aforesaid any sum or
sums which may have been deducted from or raised by sale of his security deposit or any part
thereof.
* This will be the same percentage as that in the tender at (c).
Clause 2. Compensation for delay. - The time for carrying out the work as entered in the tender
shall be strictly observed by the contractor, and shall be reckoned from the date on which the order
to commence work is given to the contractor. The work shall throughout the stipulated period of the
contract be proceeded with all due diligence (time being deemed to be the essence of the contract
on part of the contractor) and the contractor shall pay as compensation an amount equal to one per
cent which the Executive Engineer-in-charge may levy on the amount of the estimated cost of the
5 / 16
whole work as shown by the tender for every day that the work remains uncommenced or
unfinished, after the proper dates. And further, to ensure good progress during the execution of the
work the contractor shall be bound, in all cases in which the time allowed for any work exceeds one
month to complete one-fourth of the whole of the work before one-fourth of the whole time allowed
under the contract has elapsed; one-half of the work before one-half of such time has elapsed and
three-fourth of the work before three-fourth of such time has elapsed. In the event of the contractor
failing to comply with this condition he shall be liable to pay as compensation an amount equal to
one per cent which the Executive Engineer-in-charge may levy on the said estimated cost of the
whole work for every day that the due quantity of work remains incomplete provided always that the
entire amount of compensation to be paid under the provisions of this clause shall not exceed ten
per cent on the estimated cost of work as shown in the tender. The_______may on representation
from the contractor reduce the amount of compensation and his decision in writing shall be final.
Clause 3. Action when whole of security deposit is forfeited. - In any case in which under any
clause or clauses in this contract the contractor shall have rendered himself liable to pay
compensation amounting to the whole of his security deposit (whether paid in one sum or deducted
by instalments), the Executive Engineer on behalf of the Board shall have power to adopt any of
the following courses, as he may deem best suited to the interests of Board :-
(a) To rescind the contract (of which rescission notice in writing to the contractor under the hand of
the Executive Engineer shall be conclusive evidence) and in which case the security deposit of the
contractor shall stand forfeited, and be absolutely at the disposal of the Government.
(b) To employ labour paid by the State Housing Board and to supply material to carry out the work,
or any part of the work debiting the contractor with the cost of the labour and the price of the
materials of (the amount of which cost and price a certificate of the Executive Engineer shall be
final and conclusive against the contractor) and crediting him with the value of the work done, in all
respects in the same manner and at the same rates as if it had been carried out by the contractor
under terms of his contract; the certificate of the Executive Engineer as to the value of the work
done shall be final and conclusive against the contractor.
(c) To measure up the work of the contractor and to take such part thereof as shall be unexecuted
out of his hands, and to give to another contractor to complete, in which case any expenses which
may be incurred in excess of the sum which would have been paid to the original contractor if the
whole work had been executed by him (for the amount of which excess the certificate in writing of
the Executive Engineer shall be final and conclusive) shall be borne and paid by the original
contractor and may be deducted from any money due to him by Board under the contract or
otherwise or from his security deposit or the proceeds of sale thereof or sufficient part thereof.
In the event of any of the above courses being adopted by the Executive Engineer, the contractor
shall have no claim to compensation for any loss sustained by reason of his having purchased or
procured any material or entered into any engagement or made any advances on account of or
6 / 16
with a view to the execution of the work or the performance of the contract. And in case the
contract shall be rescinded under the provision aforesaid, the contractor shall not be entitled to
recover or be paid any sum for any work theretofore actually performed under this contract, unless
and until the Executive Engineer will have certified in writing the performance of such work and the
value payable in respect thereof, and he shall only be entitled to be paid the value so certified.
Clause 4. Contractor remains liable to pay compensation if action not taken under Clause
3. - In any case in which any of the power, conferred upon the Executive Engineer by clause 3
hereof shall have become exercisable and the same shall not be exercised, the non-exercise
thereof shall not constitute a waiver of any of the conditions hereof and such powers shall
notwithstanding be exercisable in the event of any future case of default by the contractor for which
by any clause or clauses hereof he is declared liable to pay compensation amounting to the whole
of his security deposit, and the liability of the contractor for past and future compensation shall
remain unaffected.
Power to take possession of or require removal of or sell, contractor's plant in the event of
the Executive Engineer putting in force either of the powers (a) or (c) vested in him under the
preceding clause, he may, if he so desires, take possession of all or any tools, materials and stores
in or upon the works, or the site thereof or belonging to the contractor or procured by him and
intended to be used for the execution of the work any part thereof, paying or allowing for the same
in account at the contract rates, or in case of these not being applicable at current market rates to
be certified by the Executive Engineer whose certificate hereof shall be final, otherwise the
Executive Engineer may by notice in writing to the contractor or his clerk of the works, foreman or
other authorized agent require him to remove such tools, plant material or stores from the premises
within a time to be specified in such notice, and in the event of the contractor failing to comply with
any such requisition, the Executive Engineer may remove them at the contractor's expense or sell
them by auction or private sale on account of the contractor and at his risk in all respects and the
certificate of the Executive Engineer as to the expense for any such removal and the amount of the
proceeds and expense of any such sale shall be final and conclusive against the contractor.
Clause 5. Extension of time. - If the contractor shall desire an extension of the time for completion
of the work on the grounds of his having unavoidably hindered in its execution or on and other
ground, he shall apply in writing to the Executive Engineer within 30 days of the date of the
hindrance on account of which he desires such extensions aforesaid and the Executive Engineer
shall, if in his opinion (which shall be final) reasonable grounds be shown therefor authorise such
extension of time, if any, as may, in his opinion be necessary or proper.
Clause 6. Contractor to submit a return every month for any works claimed as extra. - The
contractor shall deliver in the office of the Executive Engineer, on or before the 10th day of every
month during the continuance of the work covered by this contract a return showing details of any
work claimed for as extra, and such return shall also contain the value of such work as claimed by
the contractor, which value shall be based upon the rates and prices mentioned in the contract or in
7 / 16
the Schedule of Rates in force, in the [District for the time being.] The contractor shall include in
such monthly return particulars of all claims of whatever kind and however arising, which at the
date thereof he has or may claim or have against the Executive Engineer return under or in respect
of, or in any manner arising out of the execution of work and the contractor shall be deemed to
have waived all claims not included in such return and will have no right to enforce any such claims
not so included, whatsoever be the circumstances.
Clause 7. Final certificate. - Without prejudice to the rights of Board under any clause hereinafter
contained on completion of the work, the contractor shall be furnished with a certificate by the
Executive Engineer (hereinafter called the Engineer-in-charge) of such completion; but no such
certificate shall be given nor shall the work be considered to complete until the contractor shall
have removed from the premises on which the work shall be executed all scaffolding, surplus
materials and rubbish, and cleaned off the dirt from all wood work, walls, floors, or others parts of
any building in upon or about which the work is to be executed, or of which he may have had
possession for the purpose, of the execution thereof, and, the measurements in the said certificate
shall be binding and conclusive against the contractor. If the contractor shall fail to comply with the
requirements of this clause as to removal of scaffolding surplus materials and rubbish and cleaning
off dirt on or before the date fixed for the completion of the work, the Engineer-in-charge may at the
expense of the contractor remove such scaffolding, surplus materials and rubbish and dispose of
the same as he thinks fit and clean off such dirt as aforesaid, and the contractor shall forthwith pay
the amount of all expense so incurred, and shall have no claim in respect of any such scaffolding or
surplus materials as aforesaid except for any sum actually realized by the sale thereof.
Clause 8. Payment on intermediate certificates to be regarded as advances. - No payments
shall be made for works estimated to cost less than rupees one thousand, till after the whole of the
works shall have been completed and a certificate of completion given. But in the case of works
estimated to cost more than rupees one thousand the contractor shall on submitting bill, thereof be
entitled to receive a monthly payment proportionate to the part thereof than approved and passed
by the Engineer-in-charge whose certificate of such approval and passing of the sum so payable
shall be final and conclusive against the contractor. But all such intermediate payments shall be
regarded as payments by way of advance against the final payment only and not as payments for
work actually done and completed and shall not preclude the requiring of bad, unsound, and
imperfect or unskillful work to be removed and taken away and reconstructed or re-erected, or be
considered as an admission of the due performance of the contract or any part thereof in any
respect, or the accruing of any claim nor shall it conclude, determine, or affect in any way the
powers of the Engineer-in-charge under the conditions, or any of them as to the final settlement
and adjustment of the accounts or otherwise, or in any other way vary or affect the contract. The
final bill shall be submitted by the contractor within one month of the date fixed for completion of
the work otherwise the Engineer-in-charge's certificate of the measurement and of the total amount
payable for the work accordingly shall be final and binding on all parties.
Clause 9. Bills to be submitted monthly. - A bill shall be submitted by the contractor each month
8 / 16
on or before the date fixed by the Engineer-in-Charge for all work executed in the previous month,
and the Engineer-in-Charge shall take or cause to be taken the requisite measurement for the
purpose of having the same verified and the claim, as far as admissible, adjusted if possible, before
the expiry of ten days from the presentation of the bill. If the contractor does not submit the bill
within the time fixed as aforesaid, the Engineer-in-Charge may depute a subordinate to measure
up the said work in the presence of the contractor, whose countersignature to the measurement list
will be sufficient warrant; and the Engineer-in-Charge may prepare a bill from such list which shall
be binding on the contractor in all respects.
Clause 10. Bills to be on printed forms. - The contractor shall submit all bills on printed forms to
be had on application at the office of the Engineer-in-charge, and the charge in the bill shall always
be entered at the rates specified in the tender or in the case of any extra work ordered in
pursuance of these conditions, and not mentioned or provided for in the tender at the rates
hereinafter provided for such work.
Clause 11. - If the specification of estimate of the work provides for the use of any special
description of materials to be supplied from the Engineer-in-charge's store or if it is required that
the contractor shall use certain stores to be provided by the Engineer-in-Charge (such materials
and stores, and the prices to be charged therefor as hereinafter mentioned) being so far as
practicable for the convenience of the contractor, but not so in any way to control the meaning or
effect of this control specified in the schedule or memorandum hereto annexed, the contractor shall
be supplied with such materials and stores required from time to time to be used by him for the
purpose of the contract only, and the value of the full quantity of materials and stores so supplied at
the rates specified in the said schedule or memorandum may be set off or deducted from any sums
then due, or thereafter to become due to the contractor under the contract or otherwise, against or
from the security deposit. All materials supplied to the contractor shall remain the property of the
contractor, but shall not on any account be removed from the site of the work without the written
permission of the Engineer-in-Charge, and shall at all times be open to inspection by him. Any such
materials unused and in perfectly good condition at the time of the completion of the contact, shall
be returned to the Engineer-in-Charge store, if by a notice in writing under his hand he shall so
require, but the contractor shall not be entitled to return any such material unless with such
consent, and shall have no claims for compensation on account of any such materials so supplied
to him as aforesaid being unused by him, or for any wastage in or damage to any such materials.
Clause 12. Works to be executed in accordance with specifications, drawings, orders, etc. -
The contractor shall execute the whole and every part to the work in the most substantial and
workman like manner, and both as regards material and otherwise in every respect in strict
accordance with the specification. The contractor shall also conform exactly, fully and faithfully the
design, drawings, and instructions in writing relating to the work signed by the Engineer-in-Charge
and lodged in the office and to which the contractor, shall be entitled to have access at such office,
or on the site of the work for the purpose of inspection during office hours, and the contractor shall,
if he so require, be entitled at his own expense to make or cause to be made copies of the
9 / 16
specification and of all such designs, drawings and instructions as aforesaid.
Clause 13. Removal of employed workman and foreman. - The Engineer-in-Charge shall have
full powers at all times to object to the employment of any workman, foreman or other employee on
the works by the contractor and if the contractor shall receive notice in writing from the Engineer-in-
Charge requesting the removal of any such man or men from the work the contractor to comply
with the request forthwith.
No such workman, foreman or other employee after his removal from the works by request of the
Engineer-in-Charge shall be re-employed or reinstated on the works by the contractor at any time
except with the previous approval in writing or the Engineer-in-Charge. The contractor shall not be
entitled to demand the reason from the Engineer-in-Charge for requiring the removal of any such
workman, foreman or other employee.
Clause 14. Alterations in specification and designs. Do not invalidate contracts. Extension
of time in consequence of alterations. Rates for works and in estimate or schedule of rates
of the district. - The Engineer-in-Charge shall have power to make any alterations in or omissions
from, additions to or substitutions for the original specifications, drawings, designs and instructions
that may appear to him to be necessary or advisable during the progress of the work and the
contractor shall be bound to carry out the work in accordance with any instructions which may be
given to him in writing, signed by the Engineer-in-Charge and such alterations, additions or
substitutions shall not invalidate the contract; and any altered additional or substituted work which
the contractor may be directed to do in the manner above specified as part of the work shall be
carried out by the contractor on same conditions in all respects on which he agreed to do the main
work and at the same rates as are specified in the tender for main work. The time for the
completion of the work shall be extended in the proportion that the altered additional or substituted
work bears to the original contract work and the certificate of the Engineer-in-Charge shall be
conclusive as to such proportion. And if the altered, additional or substituted work includes any
class or work for which no rate is specified in the contract, then such class of work shall be carried
out at the rates entered in the schedule of rates of the district, subject to the same percentage
above or below as included in the contract and if such class of work is not entered in the schedule
of rates of the district then the contractor shall within seven days of the date of his receipt or the
order to carry out to the work inform the Engineer-in-Charge of the rate which it is his intention to
charge for such class of work and if the Engineer-in-Charge does not agree to this rate he shall, by
notice in writing, be at liberty to cancel his order to carry out such class of work and arrange to
carry it out in such manner as he may consider advisable, provided always that if the contractor
shall commence work or incur any expenditure in regard thereto before the rates shall have been
determined lastly hereinbefore mentioned, then and in such case he shall be entitled to be paid in
respect of the work carried out or expenditure incurred by him prior to the date of the determination
of the rates as aforesaid according to such rate or rates as shall be fixed by the Engineer-in-
Charge. In the event of a dispute the decision of the Executive Engineer shall be final.
10 / 16
Clause 15. No compensation for alteration in or restriction of work to be carried out. - If at
any time after the commencement of the work the Board shall for any reason whatsoever not
require the whole work thereof as specified in the tender to be carried out the Engineer-in-Charge
shall give notice in writing of the fact to the contractor who shall have no claim to any payment or
Compensation whatsoever on account of any profit or advantage which he might have derived from
execution of the work in full that which he did not derive in consequence of the full amount of the
work not having been carried out, neither shall he have any claim for compensation by reason of
any alteration having been made in the original specifications, drawing, designs and instruction
which shall involve any curtailment of the work originally contemplated.
Clause 16. Compensation payable in case of bad work. - If it shall appear to the Engineer-in-
Charge or his subordinate in-charge of the work, that any work has been executed with unsound,
imperfect or unskilful workmanship, or with materials of any inferior description or that any
materials or articles provided by him for the execution of the work are unsound, or of a quality
inferior to that contracted for or otherwise not in accordance with the contract, the contractor shall
on demand in writing from the Engineer-in-Charge specifying the work materials or articles
complained of notwithstanding that the same may have been inadvertently passed, certified and
paid for, forthwith rectify, or remove and reconstruct the work so specified in whole or in part as the
case may require, or as the case may be, remove the materials or articles so specified and provide
other proper and suitable materials or articles at his own proper charge and cost; and in the event
of his failing to do so within a period to be specified by the Engineer-in-Charge in his demand
aforesaid then the contractor shall be liable to pay compensation at the rate of one per cent on the
amount of the estimate for every day not exceeding ten days while his failure to do so shall
continue and in the case of any such failure the Engineer-in-Charge may rectify or remove and re-
execute the work or remove and replace with others materials or articles complained of, as the
case may be, at the risk and expense in all respects of the contractor.
Clause 17. Works to be open to inspection. Contractor or responsible Agent to be present. -
All work under or in course of execution or executed in pursuance of the contract shall at all times
to be open to the inspection and supervision of the Engineer-in-Charge and his subordinates and
the contractor shall at all times, during the usual working hours, and at all other times at which
reasonable notice of the intention of the Engineer-in-Charge or his subordinate to visit the works
shall have been given to the contractor, either himself be present to receive orders and
instructions, or have a responsible agent duly accredited in writing present for that purpose. Orders
given to the contractor's agent shall be considered to have the same force as if they had been
given to the contractor himself.
Clause 18. Notice to be given before work is covered up. - The contractor shall give not less
than five days' notice in writing to the Engineer-in-Charge or his subordinate-in-charge of the work
before covering up or otherwise placing beyond the reach of measurement any work in order that
the same may be measured and correct dimensions thereof be taken before the same is so
covered up or placed beyond the reach of measurement and shall not cover up or place beyond
11 / 16
the reach of measurement, any work without the consent in writing of the Engineer-in-Charge or his
subordinate-in-charge of the work and if any work shall be covered up or placed beyond the reach
of measurement such notice having been given or consent obtained, the same shall be uncovered
at the contractor' expense, or in default thereof no payment or allowance shall be made for such
work or the materials with which the same was executed.
Clause 19. Contractor liable for damage done and for imperfections for months after
certificate. - If the contractor or his work people, or servants shall break, deface, injure or destroy
any part of a building, if they may be working on any building, road, fence, enclosure, or grass land,
cultivated ground contiguous to the premises on which the work or any part of it is being executed,
or if any damage shall happen, to the work, while in progress, from any cause whatever or any
imperfections become apparent in it within three months after a certificate final or the other of its
completion shall have been given by the Engineer-in-Charge as aforesaid, the contractor shall
make the same good at his own expense, or in default the Engineer-in-Charge may cause the
same to be made good by other workman, and deduct the expense (of which the certificate of the
Engineer-in-Charge shall be final) from and sums that may be then, or at any time thereafter may
become due to the contractor, or from his security deposit.
Clause 20. Contractor to supply plant, ladder, scaffolding's, etc. - The contractor shall supply
at his own cost all materials except such special materials, if as may in accordance with the
contract be supplied from the Engineer-in-Charge's stores, plants, tools, appliances implements,
ladders, cordage, tackle, scaffolding, and temporary works requisite or proper for the proper
execution of the work, whether original, altered or substituted, and whether included in the
specification or other documents forming part of the contract or referred to in these conditions or
not, or which may be necessary for the purpose of satisfying or complying with the requirements of
the Engineer-in-Charge as to any matter to which under these conditions he is entitled to be
satisfied or which he is entitled to require together with carriage therefor to and from the work. The
contractors shall also supply without charge the requisite number of persons with means and
materials necessary for the purpose of setting out works and counting, weighing and assisting in
the measurement or examination at any time and from time to time of the work or materials. Failing
his so doing the same may be provided by the Engineer-in-Charge at the expense of the contractor
and the expenses may be deducted from any money due to the contractor under the contract or
from his security deposit. The contractor shall also provide all necessary fencing and lights required
to protect the public from accident and shall be bound to bear the expenses of defence of every
suit, action or other proceedings at law that may be brought by any person for injury sustained
owing to neglect of the above precautions, and to pay any damages and cost which may be
awarded in any such suit, action or proceedings to any such persons or which may with the
consent of the contractor be paid to compromise any claim by any such person.
Clause 21. Female labour. - No female labourer shall be employed within the limits of a
Cantonment.
12 / 16
Clause 22. - No labourer below the age of twelve years shall be employed on the work.
Clause 23. - The contractor shall pay his labourer not less than the wages paid for similar work in
the neighbourhood.
Clause 24. Work on Sunday. - No work shall be done on Sunday without the sanction in writing of
the Engineer-in-charge.
Clause 25. Contractor liable for payment of compensation to injured workman or in case
death, to his relation. - In every case in which by virtue of the provisions of sub-section (1) of
section 12 of the Workmen's Compensation Act, 1923, Board is obliged to pay compensation to a
workman employed by the contractor in execution of the works, Board will recover from the
contractor the amount of the compensation so paid; and without prejudice to the rights of Board
under sub-section (2) of section 12 of the said Act, Board shall be at liberty to recover such amount
or any part thereof by deducting it from the security deposit or from any sum due by Board to the
contractor whether under this contract or otherwise.
Board shall not be bound to contest any claim made against it under sub-section (1) section 12 of
the said Act except on the written request of the contractor and upon his giving to Board full
security for all costs for which Board might become liable in consequence of contesting the claim.
Clause 26. Work not to be sublet. Contract may be rescinded and security deposit forfeited
for subletting, bribing or contractor becomes insolvent. - The contract shall not be assigned or
sublet without the written approval of the Executive Engineer. And if the contractor shall assign or
sublet his contract; or attempt so to do or become insolvent or commence any insolvency
proceedings or make any composition with his creditors or attempts so to do, or if any bribe,
gratuity, gift, loan, perquisite, reward or advantage, pecuniary or otherwise, shall either directly or
indirectly be given, promised or offered by the contractor, or any of his servants or agents to any
public officer or person in the employ of Board in any way relating to his office or employment, or if
any such officer or person shall become in any way directly or indirectly interested in the contract,
the Executive Engineer may thereupon by notice in writing rescind the contract and the security
deposit of the contract shall thereupon stand forfeited and be absolutely at the disposal of Board
and the same consequence shall ensue as the contract had been rescinded under clause 3 hereof
and in addition the contractor shall not be entitled to recover or be paid for any work therefor
actually performed under the contract.
Clause 27. Sum payable by way of compensation to be considered as responsible
compensation without reference to actual loss. - All sums payable by way of compensation
under any of these conditions shall be considered as reasonable compensation to be applied to the
use of Board without reference to the actual loss or damages sustained and whether or not any
damages shall have been sustained.
13 / 16
Clause 28. Deductions of amounts due to Government on any account whatsoever to be
remissible from sums payable to a contractor. - Any excess payment made so the contractor
inadvertently or otherwise under this contract or any account whatever and any other sum found to
be due to Board by the contractor in respect of his contract or any other contract, or work-order or
on any account whatever, may be deducted from any sum whatsoever payable by Board to the
contractor either in respect of this contract or any work order or contact or on any other account by
any other department of the Government.
Clause 29. Changes in constitution of firm. - In the case of a tender by partners any change in
the constitution of the firm shall be forthwith notified by the contractor to the Engineer-in-Charge for
his information.
Clause 30. Works to be under direction of Executive Engineer. - All works to be executed
under the contract shall be executed under the directions of and subject to the approval in all
respects of the Executive Engineer of the Board for the time being who shall be entitled to direct at
what point or points and in what manner they are to be commenced and from time to time carried
on.
Clause 31. Claim for payment of an extra-ordinary nature to be referred to Board for
decision. - No claims for payment of an extraordinary nature, such as claims for a bonus for an
extra labour, employed in completing the work before the expiry of the contractual period at the
request of the Engineer-in-charge or claims for compensation where work has been temporarily
brought to stand still through no fault of the contractor, shall be allowed unless and to extent that
the same have been expressly sanctioned by the Board.
Clause 32. Arbitration Clause. - If any question, difference or objection whatsoever shall arise in
any way connected with or arising out of this instrument or the meaning or operation of any part
thereof or the rights, duties or liabilities of either party, then same in so far as the decision of and
such matter is herein before provided for and has been so decided, every such matter including
whether its decision has been otherwise provided and or whether it has been finally decided
accordingly or whether the contract should be terminated or has been rightly terminated and as
regards the rights and obligations of the parties as the results of such termination shall be referred
for arbitration to the authority nominated by the Chairman within one hundred and eighty days or
six months from the payment of final bill to the contractor or from the date registered notice is sent
to the contractor and his decision shall be final and binding and where the matter involves a claim
for or the payment or recovery or deduction of money only the amount, if any awarded in such
arbitration shall be recoverable in respect of the matter so referred.
"If the matter is not referred to arbitrator within the specified period, all the rights and claims under
the contract shall be deemed to have been forfeited and absolutely time barred."
Clause 33. Fluctuation in Railway freight. - Any fluctuations in Railway rates which may occur
14 / 16
during the subsistence of, and affecting freights of any material to be supplied under this contract
shall be brought to the notice of the Engineer-in-Charge by the contractor within_________days
from_________________without prejudice to the rights of Board should the contractor had to
comply with the above requirement any excess or charge on account of such increase or decrease
shall be credited to or recoverable from the contractor. No alteration in contract rate shall be
admissible in consequence of fluctuation in railway freight when such railway freight is on account
of material which is required by a contractor in the manufacture of an article to be supplied under
this contract, that is, fluctuation of railway freight on coal required for burning bricks will not be
taken into consideration, or for an article which form part of a finished work, for purposes of this
clause. Similarly, no alteration in rates will be allowed when a manufactured article is transported
by rail from place A to place B to form part of a finished work.
Clause 34. Lump sum in Estimate. - When the estimate on which a tender is made includes lump
sums in respect of parts of the work the contractor shall be entitled to payment in respect of the
items of work involved or the part of the work in question at the same rates as are payable under
this contract for such items, or if the part of the work in question is not, in the opinion of the
Engineer-in-charge capable of measurement, the Engineer-in-charge may at his discretion or pay
the lump sum amount entered in the estimate, and the certificate in writing of the Engineer-in-
charge shall be final and conclusive against the contractor with regard to any sum or sums payable
to him under the provisions of this clause.
Clause 35. Action where no specification. - In the case of any class of works for which there is
no such specification as is mentioned in Rule 1; such work shall be carried out in accordance with
the district specification and in the event of there being no district specification, then in such case
the work shall be carried out in all respects in accordance with the instructions and requirements of
the Incharge.
Clause 36. Definition of works. - The expression "works" or "work" where used in these
conditions shall unless there be something either in the subject or context repugnant to such
construction be construed and taken to mean the works by or by virtue of the contract contracted to
be executed whether temporary or permanent and whether original, altered, substituted or
additional.
Clause 37. The percentage referred to in the tender will be calculated on the gross amount (value
of finished work including cost of materials whether purchased from the Board or direct) of (1) the
items of work to which the rates in the tender apply and also (2) the items of work for which rates
exist in the Schedule of the district.
Clause 38. The terms and conditions of the agreement have been explained to me/us and I/we
clearly understand them.
* Here insert the official designation of the officer to the appointed as arbitrator.
15 / 16
Schedules showing approximately material to be supplied from the Board's
Store for works contracted to be executed and the rates at which they are to be
charged for :-
Particulars Rates at which the material will be charged
to the Contractor
Place of delivery
Unit Rs P.
Note. - The person or firm submitting the tender should see that the rates in the above schedule
are filled up by the Engineer-in-charge on the issue of the form prior to submission of the tender.
(Signature of Contractor) Signature of
Powered by TCPDF (www.tcpdf.org)
16 / 16
http://www.tcpdf.org
Previous and next
All provisions of HOUSING BOARD HARYANA (Execution of Agreement) RULES, 1975
Questions people ask
Is form F of HOUSING BOARD HARYANA (Execution of Agreement) RULES, 1975 still in force?
No repeal of HOUSING BOARD HARYANA (Execution of Agreement) RULES, 1975 is recorded.