Section 53, The Goa,Daman and Diu Town and Country Planning Act 1974: Power to stop unauthorised development
The Goa,Daman and Diu Town and Country Planning Act 1974 (21 of 1975) - Section 53
Text of section 53
Power to stop unauthorised development
53. Power to stop unauthorised development.— (1) Where any development or
change of use of land is being carried out in any manner specified in clauses (a) to (f) of
sub-section (1) of section 51, but has not been completed, the Planning and Development
Authority may serve on the owner and the person carrying out the development or change
a notice requiring such development or change of use of land to be discontinued from the
date of service of such notice.
(2) Where a notice has been served under sub-section (1) the person aggrieved by such
notice may appeal to the Board and the provisions of sub-sections (5) and (6) of section
52 shall apply with such modifications as may be necessary.
(3) Any person, who continues to carry out the development of land, whether for
himself or on behalf of the owner or any other person, even after a notice has been served
under sub-section (1) shall be punishable with fine which may extend to 29[one lakh
rupees] and when the non-compliance is a continuing one, with a further fine which may
extend to five hundred rupees for every day after the date of the service of the notice
during which the non-compliance has continued or continues.
(4) If a notice under sub-section (1) is not complied with forthwith, the Planning and
Development Authority or such officer of the Authority as may be authorised by it in this
behalf may require any police officer to remove such person and all assistants and
workmen from the land and such police officer shall comply with such requisition.
(5) Where action had been taken by a police officer under sub-section (4), the Planning
and Development Authority or the officer referred to in that sub-section shall take
necessary steps to ensure that such development is not continued.
(6) Any expenses incurred by the Planning and Development Authority under sub-
section (4) and sub-section (5) shall be paid by the person at whose instance such
development is being continued or to whom notice under sub-section (1) was given and
shall be recoverable from such person as an arrear of land revenue.
30[(7) An offence under this section shall be cognizable.]
Previous and next
← Section 52Power to require removal of unauthorised developmentSection 54 →Power to require removal of authorised development or use
All sections of The Goa,Daman and Diu Town and Country Planning Act 1974
Questions people ask
Is section 53 of the Goa,Daman and Diu Town and Country Planning Act 1974 still in force?
No repeal of the Goa,Daman and Diu Town and Country Planning Act 1974 is recorded.