Rule 8, Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974: To provide sufficient control over these matters and ensure supply in conformity with the samples and specifications the following procedure shall be adopted
Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974 - Rule 8
Text of rule 8
To provide sufficient control over these matters and ensure supply in conformity with the samples and specifications the following procedure shall be adopted
8. To provide sufficient control over these matters and ensure supply in conformity with the
samples and specifications the following procedure shall be adopted:-
(1) Supplies when received shall be subjected to inspection by the purchasing officer or any
responsible officer nominated by him.
(2) The purchasing officer shall be personally responsible for ensuring conformity of the
supply with the samples.
(3) The officer appointed for inspecting the supplies shall pick up a few articles from the
supply and compare these articles with the sample and the specifications, with a critical
eye to ascertain whether the articles supplied, confirm in all respects, with the sample
and specification. Where necessary, prescribed or practicable tests shall be carried out at
random on samples to adjudge the suitability of the supplies.
(4) The numbers of articles picked up for such comparison should be such as would, in the
discretion of the inspecting officer, give him a reasonable basis for concluding that the
supply in general is in conformity with the approved sample and specifications. In any
case the number of article picked for comparison should not be less than 10 per cent of
the article picked for comparison should not be less than 10 per cent of the supplies
unless this impracticable, for which reasons may be recorded.
(5) When the supply is satisfactory, the inspecting officer shall order the taking of the supply
on the register of the Board and give a certificate to the effect that on carefully inspecting
the supply in the prescribed manner, he found it to be conform with
samples/specifications and answering prescribed/practicable tests.
(6) If the supply is not in conformity with the sample, the inspecting officer shall, if he is not
himself the purchasing officer, forthwith draw the attention of the purchasing officer to the
defects found by him.
(7) The purchasing officer shall then either reject the supply and ask the supplier to replace
it at his own cost by goods supplies or if, due to exigencies of the work and the slight
nature of defect, he does not consider it advisable to reject the supply draw the attention
of the Board to this matter recording a note to the effect that such acceptance is
necessary and submit his recommendation about the amount that should be deducted
from the approved rates.
(8) The purchasing officer shall give his decision regarding acceptance or rejection of the
supplies within, at the most, a week of the receipt of supply.
(9) Members of the Finance Committee of the Board and officers authorised under section
283 of the Act may at any time check the stock register and record pertaining to the
purchase and compare the accepted supplies with the approved samples.
(10) They will be entitled to take the approved samples and specification with them under
proper precautions for comparing the sample with the supplies made to the consuming
departments.
Previous and next
← Rule 6The procedure for obtaining tenders shall be as followsRule 9 →The charges of the tender forms against advertised demands shall be according to the following scale
All provisions of Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974
Questions people ask
Is rule 8 of Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974 still in force?
No repeal of Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974 is recorded.