Order of the demolition of building.
40. (1) Where the erection of any building in an industrial estate has
been commenced or is being carried on, or has been completed, or any
existing building is altered, in contravention of the terms and conditions
setteled by the Corporation, any officer of the Corporation empowered
by it in this behalf may, in addition to any prosecution that may be
instituted under this Act, make an order directing the owner to
demolish such erection or to so alter the same as to conform to the said
terms and conditions within a period of three months from the date of
the order:
Provided that no such order shall be made unless the owner has
been given a reasonable opportunity to show cause why the order
should not be made.
(2) Any person aggrieved by an order under sub-section (1)
may appeal against that order, within thirty days from the date thereof,
to a Committee of the Corporation set up for the purpose by regulations
made in this behalf. Such Committee may, following the procedure
provided by regulations made in this behalf, confirm, modify or
set aside the order.
(3) The decision of the Committee on such appeal and, subject
to such decision, the order made by the officer under sub-section (1)
shall be final.
(4) On the failure of the owner—
(a) to comply with the order made under sub-section (1) within
the period specified therein, or
(b) where an appeal has been preferred against such order under
sub-section (2) and the order has not been set aside on
such appeal, to comply with the order of the Committee
on appeal, confirming or modifying the order appealed
against, within such longer period, if any, as may be allowed
by the Committee on appeal,
the officer empowered under sub-section (1) may himself cause the
erection to be demolished and the expenses of such demolition shall be
recoverable by the Corporation from the owner.
Previous and next
← Section 39Powers of the Corporation in case of certain defaults by owner of land in industrialSection 41 →Power to stop building operations
All sections of The West Bengal Industrial Infra-structure Development Corporation Act, 1974
Questions people ask
Is section 40 of the West Bengal Industrial Infra-structure Development Corporation Act, 1974 still in force?
No repeal of the West Bengal Industrial Infra-structure Development Corporation Act, 1974 is recorded.