Section 25, Water (Prevention and Control of Pollution) Act, 1974
Water (Prevention and Control of Pollution) Act, 1974 (6 of 1974) - Section 25
Text of section 25
25. RESTRICTIONS ON NEW OUTLETS AND NEW DISCHARGES.
1[(1) Subject to the provisions of this section, no person shall, without the
previous consent of the State Board,--
(a) establish or take any steps to establish any industry, operation or
process, or any treatment and disposal system or an extension or addition thereto,
which is likely to discharge sewage or trade effluent into a stream or well or
sewer or on land (such discharge being hereafter in this section referred to as
discharge of sewage); or
(b) bring into use any new or altered outlets for the discharge of sewage; or
(c) begin to make any new discharge of sewage;
Provided that a person in the process of taking any steps to establish any
industry, operation or process immediately before the commencement of the
Water (Prevention and Control of Pollution) Amendment Act, 1988, for which no
consent was necessary prior to such commencement, may continue to do so for a
period of there months from such commencement or, if he has made an
application for such consent, within the said period of three months, till the
disposal of such application.
(2) An applications for consent of the State Board under sub-section (1) shall be
made in such form, contain such particulars and shall be accompanied by such fees as
may be prescribed.]
(3) The State Board may make such inquiry as it may deem fit in respect of the
application for consent referred to in sub-section (1) and in making any such inquiry shall
follow such procedure as may be prescribed.
2[(4) The State Board may --
(a) grant its consent referred to in sub-section (1), subject to such
conditions as it may impose, being--
(i) in cases referred to in clauses (a) and (b) of sub-section (1) of section
25, conditions as to the point of discharge of sewage or as to the use of that outlet
or any other outlet for discharge of sewage;
(ii) in the case of a new discharge, conditions as to the nature and
composition, temperature, volume or rate of discharge of the effluent from the
land or premises from which the discharge or new discharge is to be made; and
1
Subs. by s. 12, Act 53 of 1988, for sub-sections (1) and (2).
2
Subs. by s. 12, Act 53 of 1988,for sub-sections (4), (5) and (6).
24 The Water (Prevention and Control of Pollution) Act, 1974 [Act 6 of 1974]
(iii) that the consent will be valid only for such period as may be
specified in the order, and any such conditions imposed shall be binding on any
person establishing or taking any steps to establish any industry, operation or
process, or treatment and disposal system or extension or addition thereto, or
using the new or altered outlet, or discharging the effluent from the land or
premises aforesaid; or
(b) refuse such consent for reasons to be recorded in writing.
(5) Where, without the consent of the State Board, any industry operation or
process, or any treatment and disposal system or any extension or addition thereto, is
established, or any steps for such establishment have been taken or a new or altered outlet
is brought into use for the discharge of sewage or a new discharge of sewage is made, the
State Board may serve on the person who has established or taken steps to establish any
industry, operation or process, or any treatment and disposal system or any extension or
addition thereto, or using the outlet, or making the discharge, as the case may be, a notice
imposing any such conditions as it might have imposed on an application for its consent
in respect of such establishment, such outlet or discharge.
(6) Every State Board shall maintain a register containing particulars or
conditions imposed under this section and so much of the register as relates to any outlet,
or to any effluent, from any land or premises shall be open to inspection at all reasonable
hours by any person interested in, or affected by such outlet, land or premises, as the case
may be, or by any person authorised by him in this behalf and the conditions so contained
in such register shall be conclusive proof that the consent was granted subject to such
conditions.]
(7) The consent referred to in sub-section (1) shall, unless given or refused
earlier, be deemed to have been given unconditionally on the expiry of a period of four
months of the making of an application in this behalf complete in all respects to the State
Board.
(8) For the purposes of this section and sections 27 and 30,-
(a) the expression "new or altered outlet" means any outlet which is
wholly or partly constructed on or after the commencement of this Act or which
(whether so constructed or not) is substantially altered after such commencement;
(b) the expression "new discharge" means a discharge which is not, as
respects the nature and composition, temperature, volume, and rate of discharge
of the effluent substantially a continuation of a discharge made within the
preceding twelve months (whether by the same or different outlet), so however
that a discharge which is in other respects a continuation of previous discharge
made as aforesaid shall not be deemed to be a new discharge by reason of any
reduction of the temperature or volume or rate of discharge of the effluent as
compared with the previous discharge.
[Act 6 of 1974] The Water (Prevention and Control of Pollution) Act, 1974 25
Previous and next
All sections of Water (Prevention and Control of Pollution) Act, 1974
Questions people ask
Is section 25 of Water (Prevention and Control of Pollution) Act, 1974 still in force?
No repeal of Water (Prevention and Control of Pollution) Act, 1974 is recorded.