25. Restrictions on new outlets and new discharges. —
1
[(1) Subject to the provisions of this section,
no person shall, without the previous consent of the State Board, —
(a) establish or take any steps to establish any industry, operation or process, or any
treatment and disposal system or any extension or addition thereto, which is likely to discharge
sewage or trade effluent into a stream or well or sewer or on land (such discharge being hereafter
in this section referred to as discharge of sewage); or
(b) bring into use any new or altered outlets for the discharge of sewage; or
(c) begin to make any new discharge of sewage;
Provided that a person in the process of taking any steps to establish any industry,
operation or process immediately before the commencement of the Water (Prevention and
Control of Pollution) Amendment Act, 1988 (53 of 1988), for which no consent was
necessary prior to such commencement, may continue to do so for a period of three months
from such commencement or, if he has made an application for such consent, within the said
period of three months, till the disposal of such application.
(2) An application for consent of the State Board under sub-section (1) shall be made in such
form, contain such particulars and shall be accompanied by such fees as may be prescribed.]
(3) The State Board may make such inquiry as it may deem fit in respect of the application for
consent referred to in sub-section (1) and in making any such inquiry shall follow such procedure as may
be prescribed.
2
[(4) The State Board may —
(a) grant its consent referred to in sub-section (1), subject to such conditions as it may
impose, being—
(i) in cases referred to in clauses (a) and (b) of sub-section (1) of section 25,
conditions as to the point of discharge of sewage or as to the use of that outlet or any other
outlet for discharge of sewage;
(ii) in the case of a new discharge, conditions as to the nature and composition,
temperature, volume or rate of discharge of the effluent from the land or premises from
which the discharge or new discharge is to be made; and
(iii) that the consent will be valid only for such period as may be specified in the
order, and any such conditions imposed shall be binding on any person establishing or taking
any steps to establish any industry, operation or process, or treatment and disposal system
1
Subs. by s. 12, Act 53 of 1988, for sub-sections (1) and (2) (w.e.f. 29.9.1988)
2
Subs. by s. 12, Act 53 of 1988, for sub-sections (4), (5) and (6) (w.e.f. 29.9.1988)
The Water (Prevention and Control of Pollution) Act, 1974 17
of extension or addition thereto, or using the new or altered outlet, or discharging the effluent
from the land or premises aforesaid; or
(b) refuse such consent for reasons to be recorded in writing.
(5) Where, without the consent of the State Board, any industry operation or process, or any
treatment and disposal system or any extension or addition thereto, is established, or any steps for such
establishment have been taken or a new or altered outlet is brought into use for the discharge of sewage or
a new discharge of sewage is made, the State Board may serve on the person who has established or taken
steps to establish any industry, operation or process, or any treatment and disposal system or any extension
or addition thereto, or using the outlet, or making the discharge, as the case may be, a notice imposing any
such conditions as it might have imposed on an application for its consent in respect of such establishment,
such outlet or discharge.
(6) Every State Board shall maintain a register containing particulars of the conditions imposed
under this section and so much of the register as relates to any outlet, or to any effluent, from any land or
premises shall be open to inspection at all reasonable hours by any person interested in, or affected by such
outlet, land or premises, as the case may be, or by any person authorised by him in this behalf and the
conditions so contained in such register shall be conclusive proof that the consent was granted subject to
such conditions.]
(7) The consent referred to in sub-section (1) shall, unless given or refused earlier, be deemed
to have been given unconditionally on the expiry of a period of four months of the making of an application
in this behalf complete in all respects to the State Board.
(8) For the purposes of this section and sections 27 and 30, —
(a) the expression "new or altered outlet" means any outlet which is wholly or partly
constructed on or after the commencement of this Act or which (whether so constructed or not) is
substantially altered after such commencement;
(b) the expression "new discharge" means a discharge which is not, as respects to nature
and composition, temperature, volume, and rate of discharge of the effluent substantially a
continuation of a discharge made within the preceding twelve months (whether by the same or
different outlet), so however that a discharge which is in other respects a continuation of previous
discharge made as aforesaid shall not be deemed to be a new discharge by reason of any reduction
of the temperature or volume or rate of discharge of the effluent as compared with the previous
discharge.
Previous and next
← Section 24Prohibition on use of stream or well for disposal of polluting matter, etcSection 26 →Provision regarding existing discharge of sewage or trade effluent
All sections of THE WATER (PREVENTION AND CONTROL OF POLLUTION) ACT, 1974
Questions people ask
Is section 25 of THE WATER (PREVENTION AND CONTROL OF POLLUTION) ACT, 1974 still in force?
No repeal of the WATER (PREVENTION AND CONTROL OF POLLUTION) ACT, 1974 is recorded.