Section 5, The West Bengal Slum Areas ( Improvement And Clearance ) Act, 1972
The West Bengal Slum Areas ( Improvement And Clearance ) Act, 1972 (10 of 1972) - Section 5
Text of section 5
5. (1) Where any work in connection with the erection of a new hut Power to
order
or other structure or addition to, or alteration in, an existing hut or other
demolition
structure, has been commenced, is being carried on, or has been completed, in certain
areas.
in contravention of the provisions of section 4, the prescribed authority
may, after giving the owner of the hut or other structure, a reasonable
opportunity of being heard, serve a notice upon such owner requiring him
to demolish so much of the new hut or other structure as has been erected
or so much of the addition or alteration as has been made, as the case may
be, within such time as may be specified in the notice.
(2) On the failure of an owner to comply with the notice referred to
in sub-section (1) within the time specified therein, the prescribed autho-
rity may cause the new hut, other structure, addition or alteration speci-
fied in the said notice to be demolished and recover the expenses of such
demolition from such owner as if such expenses were a public demand.
Previous and next
All sections of The West Bengal Slum Areas ( Improvement And Clearance ) Act, 1972
Questions people ask
Is section 5 of the West Bengal Slum Areas ( Improvement And Clearance ) Act, 1972 still in force?
No repeal of the West Bengal Slum Areas ( Improvement And Clearance ) Act, 1972 is recorded.