Rule 29, the Delhi Contract Labour (Regulation and Abolition) Rules, 1971: Renewal of licence
the Delhi Contract Labour (Regulation and Abolition) Rules, 1971 - Rule 29
Text of rule 29
Renewal of licence
29. Renewal of licence.--(1) Every contractor shall apply
to the licensing officer for renewal of the licence.
(2) Every such application shall be in Form VII in triplicate
and shall be made not less than thirty days before the date on
which the licence expires, and if the application is so made, the
licence shall be deemed to have been renewed until such date
when the renewed licence is issued.
(3) The fees chargeable for renewal of the licence shall be
the same as for the grant thereof:
Provided that if the application for renewal is not received
within the time specified in sub-rule (2), a fee of 25 per cent
in excess of the fee ordinarily payable for the licence shall be
payable for such renewal:
Provided further that in case where the licensing officer is
satisfied that the delay in submission of the application is due
to unavoidable circumstances beyond the control of the contrac-
tor, he may reduce or remit as he thinks fit the payment of such
excess fee.
Previous and next
← Rule 28Amendxnent of the licenceRule 30 →issue of duplicate certificate of registration or licence
All provisions of the Delhi Contract Labour (Regulation and Abolition) Rules, 1971
Questions people ask
Is rule 29 of the Delhi Contract Labour (Regulation and Abolition) Rules, 1971 still in force?
No repeal of the Delhi Contract Labour (Regulation and Abolition) Rules, 1971 is recorded.