Rule 3B, The Rajasthan Electricity (Duty) Rules, 1970: Time and manner of payment of duty by persons generating energy for their own use or who generate energy and supply the same to others free of charge
The Rajasthan Electricity (Duty) Rules, 1970 - Rule 3B
Text of rule 3B
Time and manner of payment of duty by persons generating energy for their own use or who generate energy and supply the same to others free of charge
1[3B. Time and manner of payment of duty by persons generating energy for their own
use or who generate energy and supply the same to others free of charge.—
(1) Every person (other than a supplier) who intends to generate or intends to
continue generation of energy for his own use or consumption or supplies the
same to others free of charge shall make an application for registration in Form
X to the Commissioner or to an officer authorised by him within thirty days
from date of publication of the Rajasthan Electricity (Duty) (Amendment)
Rules, 1979 in the official Gazette or within 30 days from the date he starts
generation of energy for his own use or consumption, whichever is later. The
Commissioner, or the authorised officer shall assign a registration number to
such applicant within a period of thirty days from the receipt of such
application.
(2) No person to whom a registration number is assigned under sub-rule (1) shall
cause any extension or replacement to be made in his generating set without
making a fresh application under sub-rule (1) and obtaining a fresh registration
number under that sub-rule.
(3) Every person generating energy for his own use or consumption shall install a
suitable meter (duly tested) by an Electrical Inspector or by an officer
authorised by the Commissioner to record the amount of energy used or
consumed by him every month for the purpose of payment of electricity duty.
He shall at his own cost get it tested by the Electrical Inspector or by an officer
authorised by the Commissioner before installation.
(4) The meter installed under sub-rule (3) shall be so maintained as to record the
consumption correctly. The meter shall be deemed to be correct if it conforms
with the requirements of sub-rule (1) and sub-rule (2) of Rules 57 of the Indian
Electricity Rules, 1956.
(5) Where a meter installed at the premises of a person generating energy for his
own use or consumption becomes inaccurate or inoperative the quantity of
energy used or consumed for the period the meter remains inaccurate or
inoperative shall be determined for the purpose of duty by the Commissioner or
by an officer authorised by him after affording a reasonable opportunity of
hearing to the person affected.
"(6) The electricity duty payable under sub-section (5) of section 5 of the Act on the
energy used or consumed shall be deposited by him within fifteen days of the close of
the month to which the duty relates, in the Government treasury, unless otherwise
notified or ordered by the State Government, through e-GRAS."; and
(7) Every person not being a supplier, who generates energy and supplies the same to any
other person free of charge under sub-section (6) of section 5 shall,—
(a) install a suitable meter (duly tested) to record the energy supplied free of
charge, and
"(b) collect and deposit within fifteen days of the close of the month to which the duty
relates in the Government Treasury, unless otherwise notified or ordered by the State
Government, through e-GRAS.".
(8) If duty has been paid in excess of what is payable under the Act, the Commissioner or
any officer authorised by him shall authorise the refund of the excess duty so paid to
the person concerned by adjustment against future dues of duty or by payment in cash
where the person ceases to generate energy for his own use or consumption or to
supply the same to others free of charge.
1. Ins. by GSR 27/F9(1)FDCT/70 dated 4.7.1979.
2. Subs. for “duplicate copy of the treasury challan” by S.O. 476 dt. 26.3.99
Previous and next
← Rule 3ATemporary connection for a certain period, for a certain purpose and consumption exceeding certain units chargeable at a higher rate of dutyRule 3C →Class of consumers for the purpose of clause (c) of proviso (3) to section 3
All provisions of The Rajasthan Electricity (Duty) Rules, 1970
Questions people ask
Is rule 3B of the Rajasthan Electricity (Duty) Rules, 1970 still in force?
No repeal of the Rajasthan Electricity (Duty) Rules, 1970 is recorded.