Section 78, The Punjab Reorganization Act, 1966
The Punjab Reorganization Act, 1966 (31 of 1966) - Section 78
Text of section 78
78. Rights and liabilities in regard to Bhakra-Nangal and Beas Projects.
(1)Notwithstanding anything contained in this Act but subject to the provisions of sections 79 and
80, all rights and liabilities of the existing State of Punjab in relation to Bhakra-Nangal Project and
Beas Project shall, on the appointed day, be the rights and liabilities of the successor States in such
proportion as may be fixed, and subject to such adjustments as may be made, by agreement entered
into by the said States after consultation with the Central Government or, if no such agreement is
entered into within two years of the appointed day, as the Central Government may be order
determine having regard to the purposes of the Projects :Provided that the order so made by the
Central Government may be varied by any subsequent agreement entered into by the successor
States after consultation with the Central Government.(2)An agreement or order referred to in
sub-section (1) shall, if there has been an extension or further development of either of the projects
referred to in that sub-section after the appointed day, provide also for the rights and liabilities of
the successor States in relation to such extension or further development.(3)The rights and
liabilities referred to in sub-sections (1) and (2) shall include -(a)the rights to receive and to utilise
the water available for distribution as a result of the projects, and(b)the rights to receive and to
utilise the power generated as a result of the projects, but shall not include the rights and liabilities
under any contract entered into before the appointed day by the Government of the existing State of
Punjab with any person or authority other than Government.(4)In this section and in sections 79
and 80, -(A)"Beas Project" means the works which are either under construction or are to be
constructed as components of the Beas-Sutlej Link Project (Unit I) and Pong Dam Project on the
Beas river (Unit II) including -(i)Beas-Sutlej Link Project (Unit I) comprising -(a)Pandoh Dam and
works appurtenant thereto,(b)Pandoh-Baggi Tunnel,(c)Sundernagar Hydel
Channel,(d)Sundernagar-Sutlej Tunnel,(e)By-pass Tunnel,(f)four generating units each of 165 M.W.
capacity at Dehar Power House on the right side of Sutlej river,(g)fifth generating unit of 120 M.W.
capacity at Bhakra Right Bank Power House,(h)transmission lines,(i)Balancing Reservoir;(ii)Pong
Dam Project (Unit II) comprising -(a)Pong Dam and works appurtenant thereto,(b)Outlet
Works,(c)Penstock Tunnels,(d)Power plant with four generating units of 60 M.W. each;(iii)such
other works as are ancillary to the works aforesaid and are of common interest to more than one
State;(B)"Bhakra-Nangal Project" means -(i)Bhakra Dam, Reservoir and works appurtenant
thereto;(ii)Nangal Dam and Nangal-Hydel Channel;(iii)Bhakra Main Line and canal
system;(iv)Bhakra Left Bank Power House, Ganguwal Power House and Kotla Power House,
switchyards, sub-stations and transmission lines;(v)Bhakra Right Bank Power House with four units
of 120 M.W. each.
Indian Kanoon - http://indiankanoon.org/doc/119134230/ 25
The Punjab Reorganisation Act, 1966
Previous and next
Questions people ask
Is section 78 of the Punjab Reorganization Act, 1966 still in force?
No repeal of the Punjab Reorganization Act, 1966 is recorded.