Rule 26D, The Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965: Conditions required to be fulfilled by the applicant
The Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965 - Rule 26D
Text of rule 26D
Conditions required to be fulfilled by the applicant
26D. Conditions required to be fulfilled by the applicant.-The applicant
shall –
(a) furnish to the Director a bank guarantee in the 79[amount equal to
twenty five percent] of proportionate estimated cost of the
development works as certified by the Director and enter into an
agreement in Form CLU-II for fulfilling the conditions contained
herein in accordance with the permission finally granted.
(b) undertake to pay proportionate development charges which shall be
a first charge of the said land as and when required and as
determined by the Director in respect of external development
works which may be carried out in the area for the benefit of the
said land.
(c) undertake to be responsible for making arrangement for the disposal
of affluent to the satisfaction of the Director.
(d) undertake to get the plan approved from the Director before
commencing any construction on the said land.
(e) undertake not to sell the said land or portion thereof unless the said
land has been put to use permitted by the Director and to use the
said land only for the purposes permitted by the Director; and
(f) undertake to start construction on the said land within a period of six
months and complete the construction within a period of 80[two
years] from the date of issue of order permitting the change of land
use:
81 [Provided that where the existing use of the land in a
Controlled Area is to be changed for the purpose of developing the
said land into buildings for industrial purposes, no bank guarantee
referred to change (a) shall be required to be furnished and in such a
case paragraph 3 of the agreement in Form CLU-II shall not apply.]
82[(g) furnish to the Director a demand draft on account of conversion
charges as per rates prescribed in the 83“Schedule IV/IVB” to these
rules.]
79 Added by Haryana Govt. Notification No. GSR 65/PA-41/63/S.25/69 dated 24.4.1969
80 Substituted by Haryana Govt. Gaz. (Extra.) dated 25.3.1997 published on 26.3.1997
81 Added by Notification No. GSR/59PA-41/63/S.25/70 dated 17.4.1970
82 Inserted by Haryana Govt. Gaz. Notification No. 10DP-99/14217 dated 1.10.1999 at page 2217
[38]
***
Previous and next
Questions people ask
Is rule 26D of the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965 still in force?
No repeal of the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965 is recorded.