Rule 21, The Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965: Duration of sanction [Section 8(2)and25(2)(f)]
The Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965 - Rule 21
Text of rule 21
Duration of sanction [Section 8(2)and25(2)(f)]
21. Duration of sanction [Section 8(2)and25(2)(f)]—(1)The permission
granted under rule 20 shall remain valid for a period of three years from the
date of order during which period all works in connection with the laying out
and development of colony shall be completed and a certificate of completion
obtained from the Director as provided in rule 22:
Provided that permission may be renewed upto further period of
two years if the Director is satisfied that the delay in execution of layout and
development works was for reasons beyond the control of the colonizer:
[Provided further that if the permission granted under rule 20 is
based on the colonizer’s furnishing guarantee for one development work, or
more one development work separately, the permission granted for rule work
or works shall remain valid for a period of one year from the date of order,
during which period such work/works shall be completed and a certificate to
that effect obtained from the Director.]
(2) The colonizer shall commence the laying out of the colony and
development works within three months of the issue of order under sub-rule
(1) of rule 20.
***
Previous and next
Questions people ask
Is rule 21 of the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965 still in force?
No repeal of the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Rules, 1965 is recorded.