5. Application for registration and grant of licence.- (1) The occupier or
manager of every factory coming within this scope of this Act after its
commencement shall submit to the Chief Inspector an application in triplicate in
2[Form 1] for the registration of the factory 3[and] for the 4[grant of licence therefor
for a period not exceeding 5[ten years];
Provided that the occupier or manager of a place to which the provisions of the
Act are made applicable by a notification under section 85 of the Act shall submit
an application within 30 days of the date of that notification.
(2) Every such application shall be accompanied by a treasury receipt or a
cheque or by an Indian Postal Order or an invoice for book adjustment, as the
case may be, for payment of the fees prescribed for the purpose as specified by
the 6[Schedule below as applicable] 7[with effect from the 1st January 8[2013];-
9[SCHEDULE A]
All factories (except Power Generating Stations and Electrical Sub-Stations)
FOR SCHEDULE A
1 Renumbered by G.N. dt. 8.2.1988 M.G.G. Pt.I-L, Ext. P.57
2 Subs. by G.N. dt. 28.9.2015 MGG Pt.I-l Ext. P.7.
3 The words “accompanied by an application in form 3” subs. by G.N. dated 1.9.2010, MGG Pt. I-L,
Ext. dt. 1.9.2010 p. 18.
4 Subs. by G.N. of 13.10.1981
5 Subs. by G.N. dt. 30.11.2000, M.G.G. Pt.I-L Ext. dt. 30.11.2000 p.243.
6 Subs. by G.N. dt. 22.5.1984.
7 Subs. by G.N. 21st May, 1986
8 Subs. by G.N. dt. 5.6.2012 MGG Pt.I-L Ext. dt. 5.6.2012.
9 Subs. by G.N. dt. 5.6.2012 MGG Pt.I-L Ext. dt. 5.6.2012.
The Maharashtra Factories Rules, 1963 89
1[SCHEDULE “A”
All Factories Maximum Number of persons to be employed on the day during the year
Quantity of H.P. Installed
(Maximum H.P.)
Up to 9 From 10
to 50
From 51 to
150
From
151 to
250
From
251 to
500
From 501 to
1000
From 1001
to 2500
From
2501 to
4000
From
4001 &
above
Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.
Nil 350 750 3500 5250 10500 21000 42000 63000 84000
Upto 10 700 2250 7000 10500 15750 31500 63000 84000 105000
Above 10 but not above 50 1050 3750 10500 15750 21000 42000 78750 96250 115500
Above 50 but not above 100 2800 5250 15750 21000 31500 52500 94500 105000 126000
Above 100 but not above 500 6300 10500 31500 42000 52500 78750 105000 126000 147000
Above 500 but not above 1000 12250 22500 42000 57750 68250 105000 126000 147000 168000
Above 1000 but not above 2000 17500 28500 57750 68250 84000 115500 147000 168000 189000
Above 2000 24500 49500 68250 84000 115500 147000 168000 189000 210000
1 Schedule `A’ subs. by G.N. dt. dt. 5.6.2012 MGG Pt.I-L Ext. dt. 5.6.2012.
90 The Maharashtra Factories Rules, 1963
[SCHEDULE B] 1
(Power Generating Stations)
General Capacity in Mega
Watts
Number of Workers
Upto 100 From 101 to 500 From 501 to 1000 Over 1000
(1) (2) (3) (4) (5)
(Rs.) (Rs.) (Rs.) (Rs.)
Upto 20 M.W. 4200 6300 10500 15750
Over 20 M.W. and upto 50
M.W.
5950 9450 15750 21000
Over 50 M.W. and upto 100
M.W.
8750 12250 21000 26250
Over 100 M.W. and upto 250
M.W.
12250 15750 26250 31500
Over 250 M.W. and upto 500
M.W.
15750 26250 31500 36750
Over 500 M.W. and upto 750
M.W.
24500 24500 36750 42000
Over 750 M.W. and upto
1000 M.W.
24500 28000 42000 52500
Over 1000 M.W. 28000 31500 52500 63000
2[SCHEDULE C]
Provided that -
(i) fees to be charged for the following classes of factories shall, subject to a
minimum of rupees five, be half of those specified above, if they do not
work for more than 180 days in the aggregate in a calendar year:-
(a) Cotton Ginning and Pressing Factories,
(b) Gur Factories,
(c) Jarda Factories (tobacco processing),
(d) Cashewnut Factories,
(e) Groundnut Decorticating Factories,
(f) Rice Mills;
(ii) in the case of other factories working for a part of the year, and
commencing work on or after 1st day of July, the fees to be charged for the
first time shall, subject to a minimum of rupees five, be half of those
specified in the Schedule aforesaid.
3Provided further that, if the period for which the licence is applied for is one
year or more but does not exceed 4[ten years] the fees payable therefor per year,
shall be at the rates specified in this sub-rule.
5[(3) Where the fees for the grant or renewal of a licence for the year 6[2013]
are paid before the 7[1st January 2013] and the fees so paid are less than the fees
1 Subs. by G.N. dt. 4.4.2015, MGG Pt-I-L, Ext. dt. 8.4.2015.
2 Del. by G.N. dt. 4.4.2015, MGG Pt.I-L Ext. dt. 8.4.2015.
3 Added by G.N. of 13.10.1981
4 Subs. by G.N. of 30.11.2000
5 Added by G.N. 31.1.1981
6 Subs. by G.N. dt.5.6.2012, MGG Pt.I-L, Ext. dt. 5.6.2012
7 Subs. by G.N. dt.5.6.2012, MGG Pt.I-L, Ext. dt. 5.6.2012
The Maharashtra Factories Rules, 1963 91
payable in accordance with rates prescribed in the Schedule in sub-rule (2), then
the licensee shall pay the difference on or before the 1[31st day of October, 2013.]
If the licensee fails to pay the difference on or before the 2[31st day of October,
2013], he shall be deemed to have paid the fees after the expiry of the due date
and an additional fee of 25 per cent, of the difference shall be payable by him.]
3[(4) Where the fees for the grant or renewal of a licence for the year (2016)
are paid before the (1st January, 2016) and the fees so paid are less than the fees
payable in accordance with rates prescribed in the “Schedule B” in sub-rule (2),
then the licensee shall pay the difference on or before the (31st day of October,
2016). If the licensee fails to pay the difference on or before the (31st day of
October, 2016), he shall be deemed to have paid the fees after the expiry of the
due date and an additional fee of 25 per cent of the difference shall be payable by
him.
4[5-A. Application for registration and grant of licence.- The occupier or
manager of every factory other than hazardous factories coming within the scope
of this Act shall submit to the Chief Inspector, an application in “Form 1” for the
registration of the factory and for the grant of licence therefor for a period not
exceeding ten year, accompanied by a plan of the factory not necessary to scale
showing clearly all the emergency exits with dimensions and a self declaration
stating that conditions mentioned in the licence will be complied within stipulated
period.]
Previous and next
Questions people ask
Is rule 5 of the Maharashtra Factories Rules, 1963 still in force?
No repeal of the Maharashtra Factories Rules, 1963 is recorded.