LawGrids logoLAWGRIDS.ORG

Rule 23, THE UTTAR PRADESH BHOOMI EVAM JAL SANRAKSHAN NIYAMAVALI , 1963: Cost of Works

THE UTTAR PRADESH BHOOMI EVAM JAL SANRAKSHAN NIYAMAVALI , 1963 - Rule 23

Text of rule 23

Cost of Works

23. Cost of Works — Mode of payment— (1) Payment for cost of works carried out by the Bhoomi Sanrakshan Adhikari shall be made by the beneficiary in half yearly instalments and shall start one year after the completion of the work. The rate of interest charged shall be 4 1/2 per cent per annum or such rate as the State Government may from time to time fix. (2) No interest shall be charged if the beneficiary discharges his liability to the full within one year of the completion of the work. (3) Notwithstanding anything contained in sub-rule (1) , no instalment shall connist of less than a rupee. 19 24. Account of beneficiaries and verification of Work-7(1) The Bhoomi Sanrakshan Adhikari shall prepare the account of the beneficiary/beneficiaries in S. C. Form 17 and serve the same on the beneficiary/beneficiaries and forward a copy thereof to the Collector within three months of the completion of the work under a. plan. (2) The Collector shall get the work verified within three months from the receipt of the account in S. C. Form 17.

Previous and next

All provisions of THE UTTAR PRADESH BHOOMI EVAM JAL SANRAKSHAN NIYAMAVALI , 1963

Questions people ask

Is rule 23 of THE UTTAR PRADESH BHOOMI EVAM JAL SANRAKSHAN NIYAMAVALI , 1963 still in force?

No repeal of the UTTAR PRADESH BHOOMI EVAM JAL SANRAKSHAN NIYAMAVALI , 1963 is recorded.