Rule 40, The Maharashtra Boiler Rules, 1962: Fee to cover inspection and tests
The Maharashtra Boiler Rules, 1962 - Rule 40
Text of rule 40
Fee to cover inspection and tests
40. Fee to cover inspection and tests. – A fee paid for the inspection of a
boiler shall cover thorough inspection, hydraulic test and steam test
where such are necessary, subject to the provisions of section 14 (2).
41. Second fee in default – A second fee will be leviable for reinspection in
any case where the inspection of a boiler is begun, but owing to the fault
or neglect of the owner or person-in-charge, is not completed within a
period of six months from the date of commencement of inspection.
42. Sanction of Director to second fee – No extra fee shall be levied except
with the sanction of the Director.
43. Special fee for inspections out of seasons – For any inspection of a
boiler, steam, feed and blow off pipes under fabrication, or boiler
mountings and under manufacture or a boiler or its component under
fabrication, situated at a place beyond the limits of Headquarters which is
visited by an Dy. Director one or more times in a year for the purpose of
inspection, if an owner or person-in-charge fails to avail himself of the
services of the Dy. Director during the usual periods for visiting the
The Maharashtra Boiler Rules, 1962 21
district and applies for inspection at a time which would necessitate a
special journey by the Dy. Director, then before the Inspector undertakes
such a journey, the owner or person-in-charge shall, in addition, to the
usual prescribed fee, pay into the Government treasury additional fee
equivalent to such sum as will cover the rail conveyance and travelling
allowance charges of the Dy. Director from the nearest headquarters and
of any Class IV servant accompanying him as the Director may determine
: Provided that, if two or more owners apply for inspection at a time
which would necessitate a special journey by the Dy. Director then before
the Dy. Director undertakes such a journey, the owners of person-in-
charge shall, in addition to the usual prescribed fees, pay such
proportionate traveling allowance charges as would be determined by
the Director.
44. Fee for copy or registration book – The fee for copy of Registration
Book excluding inspection notes and calculations, shall be one hundred
rupees.
45. Duplicate certificate's fees – Fees for duplicate certificates shall be
charges as under :-
(a) Certificate in Form No. III-A, III-B, III-C and VI of Rs.50 each Regulations
(b) Certificate in Form No., II, III and IV Rs.200 each
(c) Certificate of qualified welders Rs.50 each
(d) Certificate of competency or Proficiency Rs.50 each
45 (A). Fees for endorsement :- Fees for endorsement of welders certificate
shall be charged as Rs.100 per certificate.
46. Refund of Fees – Fees paid in excess and fees paid for an inspection
which for any reason not due to any fault or commission of the owner or person-
in-charge of the boiler has not been made, shall be refunded if a refund is applied
for within one year from the date of payment.
VI. ACCIDENTS
47. Investigation of accidents – On the receipt of a report of an accident to a
boiler or steam-pipe under section 18, the Dy. Director should with the least
possible delay, proceed to the place to investigate the accident. If the report is
received by the Director, he should forward it at once to the Dy. Director within
whose jurisdiction the accident has occurred for necessary action.
48. Procedure during inquiry – The Inspector at his inquiry shall make a
careful examination of the damaged parts and shall take such measurements and
make such sketches for the purpose of his report, as he may deem necessary. He
shall inquire into the circumstances, attending the accident and note the time of
its occurrence, its nature and extent, the injury caused to persons and the
The Maharashtra Boiler Rules, 1962 22
damage done to property. The report should be in the style of the Reports of
Preliminary Enquiries under the British Boiler Explosions Acts, 1882 and 1890.
49. Power to hold inquiry in writing – Jt. Director and Dy. Director are
authorized to take the written statements of witness and all persons
immediately concerned with the accident. In order to comply with the provisions
of section 18 (2) the Jt. Director or the Dy. Director should present to the owner
or person-in-charge of the boiler a series of written questions on all points that
are material to the inquiry.
50. Use of boiler after accident – The Inspector must decide whether the
use of the boiler can be permitted at the same or at a lower pressure without
repairs or pending the completion of any repairs or alterations that he may
order. In no case should he issue a provisional order or renewal certificate until
his orders have been carried out.
51. Procedure in case of serious accidents – The report should be sent
without delay to the Director, if he considers that the investigation has been
sufficient he will record the facts in his Register of Accidents and enter a brief
account of the accident in the Registration Book, a copy being made in the
Memorandum of Inspection Book. If, however, the accident is of a serious nature
and in all cases in which an explosion has occurred, the Director should, after
receipt of the Inspector's report proceed to investigate the accident personally
either alone or with the assistance of a member of the panel of assessors
appointed under Rule 64 who may be appointed for this purpose by the
Commissioner. Report of such inquiries should be recorded as indicated above.
52. Remuneration of Assessor – The Assessor shall be remunerated at such
rate as may be prescribed by the State Government and be allowed the traveling
expenses incurred by him in attending the inquiry.
53. Reference in Annual Report – A brief account of all accidents and their
causes should be included in the Director 's Annual Report.
54. Unreported accidents – If in the course of an inspection or at any other
time the Jt. Director or Dy. Director discover damage which comes within the
definition of and accident but which has not been reported he should report the
facts at once to the Director for action under Section 24(d).
VII. APPEALS
55. Filing of appeal – Every petition of appeal shall be made in writing either
in English or in the vernacular.
56. Presentation of appeal – An appeal may be presented either personally
or registered post to the Director.
The Maharashtra Boiler Rules, 1962 23
57. Form of appeal – The petition of appeal shall be accompanied by the
original order, notice or report appealed against or by a certified copy thereof or
where no such order, notice or report has been made in writing by a clear
statement of the facts appealed against the grounds of appeal and the referring
section of the Act.
58. Fixing date for hearing – On receipt of an appeal, the Director, shall if the
appeal is to be heard by himself, at once fix a date for hearing the appeal, and if it
is to be heard by the Appellant Authority, obtain a date for the hearing of the
appeal from the President of the Appellate Authority. It is important that there
should be no delay in the decision of appeals, as the stoppage of a boiler is likely
to put the owner thereof to great inconvenience. The decision should ordinarily
be given within 10 days from the receipt of the petition of appeal.
59. Procedure before hearing – When the date for hearing has been fixed,
the Director shall at once issue a notice to the appellant stating the date for
hearing and informing him that if he wished to be heard in support of the appeal
or to produce evidence he must be present either in person or by authorized
agent with his evidence on the date fixed. The notice shall be sent by registered
post to such address as shall be entered in the petition of appeal.
60. Presence of Inspector – In all appeals the Director shall decide whether
the presence of the Dy. Director is necessary, and shall issue orders accordingly.
61. Attendance of witnesses – The Appellate Authority shall have power to
secure the attendance of witnesses and to make local inquiries under the
provisions of the Code of Civil Procedure, 1908.
62. Ex-parte decisions – If the appellant is not present on the date fixed, the
appeal may be decided in his absence.
63. Appellate Authority – For the purpose of hearing appeals under section
20, there shall be an Appellate Authority consisting of the President and six
assessors, appointed by the State Government.
64. Qualifications of President and Assessors – (1) A person to be
appointed as the President of the Appellate Authority shall be one –
(i) who is holding or has held any judicial office not lower in rank than that
of 'Civil Judge' or 'First Class Magistrate' or any office which in the
opinion of the State Government is an equivalent office;
(ii) who is an advocate enrolled under the Indian Bar Council Act, 1926;
(iii) an Attorney of a High Court; or
(iv) a Pleader enrolled under the Bombay Pleaders Act, 1920.
The Maharashtra Boiler Rules, 1962 24
(2) A person to be appointed as assessor shall be one who is a Mechanical
Engineer possessing such qualifications as the State Government may determine.
64-A. Fees payable to President and Assessors – The president who is not an
official and Assessors of the appellate authority constituted under section 20,
shall be paid fees in accordance with the following scale, namely:-
President – (i) Rs.250 per day for a meeting lasting for less than 3 hours, (ii)
Rs.500 per day for a meeting lasting for 3 hours or more.
Assessor – (i) Rs.200 (inclusive of traveling and daily allowance) per day for a
meeting lasting for less than 3 hours, (ii) Rs.400 (inclusive of travelling and daily
allowance) per day for a meeting lasting for 3 hours or more.
65. Constitution of Appellate Authority – Whenever the date for an appeal
before the Appellate Authority has been fixed, the Director shall, under the
orders of the President of the Appellate Authority, arrange for the attendance of
3 members of the panel constituted under rule 63 to act as assessors.
66. Cost in appeals – In appeals before the Appellate Authority the President
is authorized to fix the cost and recover them from the appellant in any case in
which the appeal is dismissed; in all case of appeal in which a local inspection is
required by the appellant he shall deposit in advance the full costs of such
inspection.
67. Fees required for certificate granted on appeal – Any order on appeal
authorizing the registering of a boiler or the grant or renewal of a certificate
shall be deemed to be subject to the payment of such fees as are prescribed by
rules or regulations framed under the Act.
NOTE : Rule 68 to 149 deleted; as information in these rules is covered in the
THE BOILERS ACT.1923 (As Amended 2007) / Boiler Attendants Rules,
2011 & Boiler Operation Engineers Rules, 2011.
XXII. INSTRUCTION FOR APPROVAL AND RENEWAL OF FIRMS FOR MANUFACTURE OF
FABRICATION OR REPAIRS OF BOILERS, ETC.
150. Approval of firms for pipe fabrication – (1) Application for pipe
fabrication shall be accompanied by a receipted challan for fee as prescribed in
sub-clause (i) of clause (a) of rule 38-A and shall contain full information of the
supervisory and operational staff employed and also the tools and plant
possessed by the applicant firm as indicated in regulation 392 of the Indian
Boiler Regulations, 1950.
(2) If the Director is satisfied with the equipment and supervisory personnel
and quality of work done by the Organisation, approval shall be granted subject
to such conditions and limitations as may be prescribed by the Director in his
order. The approval thus granted shall be valid for a period of one year from the
date of order and shall be renewed every year.
The Maharashtra Boiler Rules, 1962 25
(3) Every application for renewal of approval as pipe fabricator shall be
accompanied by a receipted challan for fee as prescribed in sub-clause (ii) of
clause (a) of rule 38-A and shall contain full details in accordance with the
provisions of sub-rule (1) for considering the renewal of approval by the
Director.
(4) Any change in the supervisory and operational staff during the course of
validity of the approval shall be communicated to the Director within seven days
from such change.
151. Approval of firms for Boiler Repairs – (1) An application for approval
as boiler repairer shall be accompanied by a receipted challan for a fee as
prescribed in sub-clause (i) of clause (b) of rule 38-A and shall contain full
information of the supervisory and operational staff employed and also the tools
and the plant possessed by the applicant firm, as indicated in regulation 392 of
the Indian Regulations, 1950.
(2) If the Director is satisfied with the equipment and supervisory personnel
and quality of work done by the Organisation, approval shall be granted subject
to such conditions or limitations as may be prescribed by Director in his order,
The approval thus granted shall be valid for a period of one year from the date of
order and shall be renewed every year.
(3) Every application for renewal of approvals as boiler repairer shall be
accompanied by a receipted challan for fee as prescribed in sub-clause (ii) of
clause (b) of rule 38 A and shall contain full details in accordance with the
provisions of sub-rule (1) for considering the renewal of approval by the
Director.
(4) Any change in the supervisory operational staff during the course of
validity of the approval shall be communicated to the Director within seven days
from such change.
152. Approval of firms for manufacture of Boilers or Economisers – (1) An
application for registration for manufacture of boilers or economisers shall be
accompanied by a receipted challan for fee as prescribed in clause (c) of rule 38-
A and shall contain full information of the supervisory and operational staff
employed and also the tools and plant possessed by the applicant firm and such
other information as may be called for by the Director for considering the
application.
(2) If the Director is satisfied with the equipment and supervisory personnel
and quality of work done by the Organisation, approval shall be granted subject
to such conditions or limitations as may be prescribed by the Director in his
order.
(3) Any change in the supervisory and operational staff during the course of
validity of the approval shall be communicated to the Director within seven days
from such change.
The Maharashtra Boiler Rules, 1962 26
153. Approval of firm for manufacture of valves, forged flanges and such
other fittings – (1) An application for registration for manufacture of valves,
forged flanges and such other fittings shall be accompanied by a receipted
challan for fee as prescribed in clause (d) of rule 38-A and shall contain full
information of the supervisory and operational staff employed and also the tools
and plant possessed by the applicant and such other information as my be called
for by the Director for considering the application.
(2) If the Director is satisfied with the equipment and supervisory personnel
and quality of work done by the Organisation, approval shall be granted subject
to such conditions or limitations as may be prescribed by the Director in his
order.
(3) Any change in the supervisory and operational staff during the course of
validity of the approval shall be communicated to the Director within seven days
from such change.
154. Approval of firm for manufacture of Plate flanges– (1) An application
for manufacture of plate flanges shall be accompanied by a receipted challan for
fee as prescribed in clause (c) of rule 38-A and shall contain full information of
the supervisory and operational staff employed and also the tools and plant
possessed by the applicant and such other information as may be called for by
the Director for considering the application.
(2) If the Director is satisfied with the equipment and supervisory personnel
and quality of work done by the Organisation, approval shall be granted subject
to such conditions or limitations as may be prescribed by the Director in his
order.
(3) Any change in the supervisory and operational staff during the course of
validity of the approval shall be communicated to the Director within seven days
from such change.
155. Withdrawal of Approval – Approval granted under the pregoing rules,
shall be withdrawn if-
(i) the approval was obtained on furnishing incorrect or false information;
or
(ii) no manufacturing activities or fabrication work or repair work was
carried out for a continuous period of six months.
Provided that before any such order for withdrawal of approval is passed,
the owner or person incharge of the organisation shall be given due notice in
writing calling upon the person concerned to show cause why an order for
withdrawal of approval should not be made, the objections, if any, shall be
considered and reasonable opportunity of being heard shall be given to such
person by the Director.
G.C.P.H.4176-5 (2034-1093)
The Maharashtra Boiler Rules, 1962 27
Previous and next
Questions people ask
Is rule 40 of the Maharashtra Boiler Rules, 1962 still in force?
No repeal of the Maharashtra Boiler Rules, 1962 is recorded.