Rule 99, The Factory rules 1962: Exemption of certain adult workers
The Factory rules 1962 - Rule 99
Text of rule 99
Exemption of certain adult workers
99. Exemption of certain adult workers. - Adult workers engaged in factories
specified in column No. 4 (3) of the schedule hereto annexed on the work specified in
column No. (4) of the said schedule shall be exempted from the provisions of the
sections specified in column No. (5) thereof, subject to the conditions if any specified
in column No. (6) of the said schedule and also to the following conditions :-
Conditions
(a) Except in respect of exemption under clause (a) of sub-section (2) the restrictions
imposed under Section 64 (4) shall apply to all exemptions granted under this rule :-
(i) the total number of hours of works in any day shall not exceed 10 (ten) inclusive of
overtime;
(ii) the spreadover, inclusive of intervals for the rest, shall not exceed twelve hours in
any one day :
Provided that the State Government may in respect of any or all of the categories of
workers referred to in clause (d) of sub-section (2) make rules prescribing the
circumstances in which, and the conditions subject to which, the restrictions imposed
by clause (i) and clause (ii) shall apply in order to enable shift worker to work the
whole or part of a subsequent shift in the absence of a worker who has failed to report
for duty;
(iii) the total number of hours of work in a week including overtime shall not exceed
sixty;
(iv) the total number of hours of overtime shall not exceed fifty for any one quarter.
Explanation. - "Quarter" means a period of the conclusive months beginning on the
1st January, the 1st of April, the 1st of July or the 1st of October.
(b) Overtime wages shall be paid in accordance with the provisions of Section 59 and
Rule. 94.
(c) The exemption granted under Section 54 shall not apply in the case of female
workers.
(d) whenever workers are exempted by Section 52 they shall be granted
compensatory holiday in accordance with the provisions of Section 53 and Rule 93.
Schedule Prescribed Under Rule 99
S.
No.
Section of
the Act
empowering
the grant of
exemption
The class of
factories
Nature of
exempted work
Extent of
exemptions
Conditions
subject to
which the
exemption is
granted.
(These
conditions are
in addition to
those specified
under Rule 99)
(1) (2) (3) (4) (5) (6)
1. 64 (2) (a) All Factories Urgent
and 64 (3) Repairs. The
following shall
be considered
to be urgent
repairs :-
(a) Repairs to
any Part of the
machinery,
plant or a
structure of a
Factory which
are of such
nature that
delay in their
execution
would involve
danger to
human life or
safety or
stoppage of the
manufacturing
process.
(a) Within 24
hours of
commencemen
t of work on
urgent repairs
a written notice
shall be sent to
the Inspector
describing
briefly the
nature of the
urgent repairs
and specifying
the estimated
time required to
execute them.
Before any
worker is
employed on
overtime work
entry of the
proposed
overtime shall
be made in the
overtime
register.
(b) Breakdown
repairs to the
motive power
transmission or
other essential
parts of the
factories,
Collieries,
railways, motor
transport, gas
electrical
generating and
Sections
51,
52,54,56,61
.
(b) No worker
shall be
employed for
more than 14
consecutive
days without a
holiday for the
whole day or in
the alternative
a net period of
atleast 36
consecutive
transmission
pumping or
similar
essential or
public utility
services
carried out in
general
engineering
works and
foundries and
which are
necessary to
enable such
concerns to
maintain their
manufacturing
process,
production or
service during
normal working
hours.
hours.
(c) Repairs to
commercial air
craft done in a
factory which
are essential to
enable aircraft
to leave port in
their proper
time or
continue their
normal
operations in
air worthy
conditions as
the case may
be.
(c) The
average
weekly hours of
work of any
such worker in
any month
shall not
exceed 60.
(d) Repairs in
connection with
a change of
motive power
for example
(d) No worker
shall be
employed for
more than 15
hours on any
from a steam to
electricity or
vice versa.
one day.
When such
work cannot
possibly be
done without
stoppage, of
the normal
manufacturing
process.
Note. -
Periodical
cleaning and
lubricating are
not included in
the term
'URGENT
REPAIRS'.
2.
64 (2) (b)
(1)
All factories
(a) work in
connection with
the mill gearing
the electrical
driving or
lighting
apparatus the
mechanical or
electrical lifts or
steam of water
pipes or pumps
of factory.
(a) No worker
shall be
allowed to work
for more than
54 hours in any
week.
(b) Work of
examining or
repairing any
machinery or
other parts of
the plant which
is necessary
for carrying on
work in the
factory.
(b) No worker
shall be
employed for
more than 10
hours in any
one day.
(c) Work in
boiler houses
and engine
room such as
lighting fire in
order to raise
steam or
generating gas
preparatory to
the
commencemen
t of regular
work in the
factory or of
engine drivers
and engine
oilers.
Sections
51, 54, 5
and 56.
(c) Interval of
atleast half an
hour for food
and rest shall
be given on
each working
day to all the
workers
employed on
such work.
(d) Work of
cleaning work
places.
(d) The
spread-over
shall not
exceed 12
hours.
(e) Work of
Departmental
oilers and
beltmen.
(f) work in
connection with
pumping
operations.
(g) Work in
foundries on
the cupola and
casting on the
day the cupola
is worked.
(2) Gur
Factories
The work
performed by
workers in
crushing
sugarcane.
Sections
51, 55 and
56.
(a) No workers
shall be
employed for
more than 54
hrs. in any one
week.
(3) Dyeing and
Bleaching
Factories or
Depth.
Work
performed by
Kierman
(b) The interval
for food and
rest totaling 1
hour if the
working hours
exceed 8 ½
hours in a day
or half an hour
if working
hours, do not
exceed 8 ½
hours shall be
given to each
worker every
day.
3.
64 (2)(c)
and 64 (3)
(1) All Factories
(a) Work
performed by
workers on
lighting
ventilation and
humidifying
apparatus.
Sections
51, 54,55
and 61.
No worker shall
be employed
for more than
54 hours in
only one week.
(b) Work
performed by
fire pumpman.
64 (2)(c)
(2) Cotton
Ginning and
Pressing
Factories.
Work of Fitters
Oilmen Belt
and Ropemen,
Turners and
Blacksmiths.
Section 51
No worker shall
be allowed to
work for more
than 54 hours
in any week.
64 (2)(c)
(3) Cotton,
Spinning and
Weaving Mills.
Work involved
in cleaning
Blow room Flue
Sections
51, 54 and
56
(a) No worker
shall be
allowed to work
for more than
54 hours in any
week.
(b) No worker
shall be
allowed to work
in such a
manner that
the spread over
exceed 10 ½
hours except in
one day in a
week,
previously
notified to the
Inspector when
it shall not
exceed 12
hours.
64 (2)(c) (4) Pottery
Work on kilns
other
continuous fire
kilns.
Sections 51
and 54.
No workers
shall be
employed for
more than 54
hours in any
one week.
64 (2)(d) All Factories
(a) workers
engaged in the
work which for
technical
reasons must
be carried
continuously
and in such,
emergencies
when their
respective
relievers at the
end of their
shifts have
failed to report
for duty.
In the absence
of worker who
has failed to
report for duty
a shift worker
shall be
allowed to
work, the whole
or part of a
subsequent
shift provided
that :-
(a) The next
shift of the shift
worker shall
not commence
before a period
of 8 hours have
elapsed
(b) work in
connection with
generation and
supply of
(b) Within 24
hours of the
commencemen
t of the
steam,
electricity and
water.
subsequent
shift notice
shall be sent to
the Inspector
describing the
circumstances
under which
the worker is
required to
work in the
subsequent
shift.
(c) The
exemption
shall be
restricted to
only male adult
workers.
(d) No workers
shall be
employed for
more than t4
consecutive
days without a
rest period of at
least 24
consecutive
hours.
(2) Cement
Factories and
Asbestos
factories.
(a) No worker
shall be
employed for
more than 56
hours in any
one week.
(3) Oil Mills and
Vegetable
Hydro-geration.
(b) No worker
shall be
employed for
more than 14
consecutive
days without a
rest period of
allowed 24
consecutive
hours.
(4) Ice
Factories.
(5) Distilleries
Workers
engaged on a
manufacturing
process which
is essentially
continuous.
Sections
51,
52,54,55,
and 56
(c) The workers
shall be
employed on
daily 8 hours
shift.
(6) Paper and
Card- Board
Factories.
(7) Chemical
Factories
(8) Carbolic
acid gas
factories.
(d) Interval of
atleast ½ hour
for food and
rest shall be
given on each
working day to
all workers
employed on
such work.
(9) Cold
Storage
(10) Electric
supply power
houses and
Auxiliaries
Operation and
maintenance of
prime movers
and auxiliaries
generators,
transformers
and switch
gear, boilers
and auxiliaries.
(a) No workers
shall be
employed for
more than 56
hrs. in any one
week.
(11) Pottery
work and
Ceramic
Industry
(a) Work or
polisher in all
potteries.
(b) Workers
working in
continuous fire
kilns in
potteries.
(b) No worker
shall be
employed for
more than 14
consecutive
days without
rest period at
least 24
consecutive
hours.
(12) Water
works
Worker
employed in
water works.
Sections
51,52,
54,55 and
56
(13) Glass
Factories
(a) Work in
attending to
furnance and
blowing and
moulding.
(c) The workers
shall be
employed on
daily 8 hours
shift.
(b) Workers
employed in an
healing
section.
(d) Interval of
atleast ½ hour
for food and
rest shall be
given on each
working day to
all workers
employed on
such work.
(14) Spinning
and Weaving
Mills.
Work of
workers
employed in
Dyeing,
Printing and
Bleaching
Departments
and Kiers.
(15) Soap
Factories
(a) Work on
Boilers and
Generators,
Motors, Switch
Boards.
(b) Work on
boiling
scratching and
framing.
(16) Biscuits
Factories and
confectionery.
Work on mixing
of the dough,
backing,
drawing and
packing
Biscuits and
(a) No worker
shall be
employed for
more than 56
hrs. in any one
week.
confectionery
(17) Starch
Factories
Work on
manufacturing
of starch and
its by products
except the
Engineering
and workshop.
(18) Sugar
Factories and
Refineries
working on the
vaccum pan
system.
(a) Workers
attending to
boilers Engines
Motors Switch
Boards and
pumps.
(b) No workers
shall be
employed for
more than 14
consecutive
days without a
rest period of
atleast 24
consecutive
hours.
(b) Workers
handling and
crushing cane
and handling
Gur to melting
bow ups.
(c) Workers
engaged in
filtration
clarification
and
crystilisation of
cane juice and
Gur Liquor.
(d) Workers
engaged in
evaporation
and
concentration
of cane juice
and Gur Liquor.
(e) Workers
(c) The workers
shall be
employed on
daily 8 hours
shift.
engaged in
curing of the
messecuits.
(f) Workers
engaged in
drying,
crushing and
bagging of
sugar.
(g) Engaged in
burning lime
stones sulfur
for the
production of
carbondioxide
and
sulphur-ioxide
and sulfur
dioxide gases
for the
clarification of
cane juice.
(19) Wood
Product (Cutch
and Kattha
Factories)
Work of
Engines,
Boilers,
Motors, Switch,
Board, Pumps,
Mechanical
and sawing
and Clipping,
Autoclaves
evaporation,
refrigeration,
filtration and
drying in wood
products.
Sections
51, 52, 54,
55 and 56.
(20) Iron and
Steel factories
All works on
steel furnaces
(d) Intervals
atleast hour for
food and rest
shall be given
on each
working day to
all workers
employed on
such work.
(21) Rolling
Mills.
Work of ingot
transporters,
furnace-ment
ongmen such
as roughters
and loppers
(workers on the
cooling bed,
waterman,
strengthen
workers
engaged in
stacking of
finished
materials an
attendance of
shears and
other
auxiliaries
machineries).
(22) Lime
Bhattas
Workers
employed on
kilns.
(a) The worker
shall be
employed pn 8
hours shift.
(23) Ferrous
and
non-ferrous
metal factories.
(a) worker
employed on
furnance.
(b) worker
employed in
hetrolling.
Sections 54
and 55(b)
All interval of
atleast ½ hour
shall be given
to each worker
for food and
rest.
(c) worker
employed in
foundries.
(24) Shellic
Factories.
Worker
employed in
Bhattas.
Sections 54
and 55
(25) Oil tank
installation.
Worked
performed by
workers
connected with
pumping
operations.
Sections
51, 52, 54,
55 and 56.
(a) No worker
shall be
allowed to be
employed for
more than 56
hours in any
week.
(b) A
compensatory
rest period of
atleast 24
Consecutive
hours shall be
given to each
worker after the
cessation of
pumping
operation.
(c) Notice of
such operation
with the
number of work
be sent to the
Inspector
immediately
after the
commencemen
t of such work.
(26) Flour mills. All work.
Sections 52
and 55
(a) The
workers shall
ordinarily be
employed on 8
hours shift.
(b) An interval
of atleast ½
hrs. shall
be-given to
each worker,
for food and
rest.
(27) Tanneries
Work on
soaking, liming,
washing
bathing,
tanning, and
drying and
hides, kps. and
skins.
Sections 51
and 52.
(a) The Sunday
work of such
workers shall
not exceed 4
hours.
(b) No worker
shall be
allowed to work
for more than
58 hours in any
one week.
(28) Brick
factories
Work of
firemen on
kilns.
Section 55.
(29) Rubber
Plastic
Factories.
All work on
curing
processes.
[(30) All
factories.
Work
automatic
equipment
engaged in
galvanizing,
anodining
enamelling.
Sections
51, 52, 54,
55, 56 and
58.
(1) The limits of
work inclusive
of overtime
shall not
exceed those
mentioned in
sub-section (4)
of Section 64.
(2) The
exemption
shall be
granted only in
respect of adult
male workers.]
5. 64(2)
(1) Motor
repairs
workshop and
service station.
All work.
No worker shall
be employed
for more than 4
hours on a
weekly holiday
and the holiday
so lost be
compensated
within a period
of 3 months.
(2) Dairies
All work in
dairy factory
other than
printing and
manufacturing
of container for
milk cream,
Ghee and
butter.
(3) Printing
Press.
Workers
engaged in
daily
newspapers.
6. 64(2)
(1) Cotton
Ginning and
Pressing
Factories.
Work of Fitters,
Oilment Blet
and Ropemen,
Turners and
Blacksmiths.
Section 52
(2) Canning
Industries and
perfumeries.
All work.
(3) Rice Mills.
Work on drying
platforms.
(4) Opium
Factories.
Work on
removing
opium from
railways
wagons to be
import shed.
7. 64(2)(h) (1) All factories.
Workers
engaged in
engine room or
boiler houses
or in attending
to power plant
or transmission
machineries.
Section 52
No worker shall
be employed
for more than
14 consecutive
days without
rest period of
atleast 24
consecutive
hours.
8. 64(2)(f) Printing Press (a) Workers Sections (a) No worker
engaged in
printing of
newspapers.
engaged in
composing,
linotype and
Monotype
machineries
and printing
machines,
folding and
despatching,
who are held
up on account
of the break
down of the
machineries.
51, 54 and
56.
shall be
employed for
more than 56
hours in any
one week.
(b) Workers
employed on
teleprinter
service.
(b) No worker
shall be
employed for
more than 10
hours on any
one day.
(c) The spread
over inclusive
of interval for
food and rest
shall not 12
hours on any
one day.
9. 64(2)(i) (1) All Factories
Workers
engaged in
loading and
unloading of
Railway
wagons, lorries
and trucks.
Sections
51, 52,54
and 56
(a) No worker
shall be
employed for
more than 56
hours in any
one week.
(b) No worker
shall be
employed for
more than 14
consecutive
days without a
rest period to
atleast 24
consecutive
hours.
(c) No worker
shall be
employed for
more than 10
hrs. on any one
day.
(d) The spread
over inclusive
of interval for
food and rest
shall not
exceed 12
hours on any
one day.
10. 64(2)(k)
(1) All
Factories.
Workers
engaged in
work of
National
importance
notified by the
State
Government.
Sections
51, 52, 54,
55 and 56
(a) No worker
shall be
employed for
more than 56
hours in any
one week.
(a) Work in
connection with
printing of
electoral rolls
and Ballot
Papers for
conduct of
elections to
Parliament and
Legislature of
every State.
(b) Work of
manufacture
and testi of
arms,
ammunition,
vehicles and
equipments for
defence
requirements in
defence
factories
owned by the
Government of
India.
(b) No worker
shall be
employed for
more than 14
consecutive
days without a
rest period of
atleast 24
consecutive
hours.
(c) Work of
manufacture of
currency notes,
paper and
printings of
currency notes,
in security
papers mills
and other
factories
owned by the
Government of
India, and
(c) The workers
shall be
employed on
daily 8 hours
shift.
(d) Work in
connection with
the
manufacture of
the articles of
food,
medicines and
clothing used
for relief work
in case of flood
and/or
earthquake.
(d) Interval of
atleast ½ hours
for food and
rest shall be
given on each
working day to
all workers
employed on
such work.
11. ["64(1)(k)"
"Any factory or
class or
description of
"Work of
national
importance as
Sections
51, 52, 54,
55, 56 and
"(1) The limit of
work inclusive
of overtime
factories as
may be notified
by State
Government in
the Official
Gazette."
may be notified
by the State
Government in
the Official
Gazette."
58. shall not
exceed those
mentioned in
sub-section (4)
of Section 64.
(2) The
exemption
shall be limited
to adult-male
worker."]
[Explanation. - (1) The shall be considered to be urgent repairs,-
(a) repairs to any part of the machinery, plant or structure of a factory which are of
such a nature that delay in their execution would involve danger to human life or
safety or the stoppage of manufacturing process;
(b) breakdown repairs to the motive power transmission or other essential plant of
other factories, collieries, railways, dockyards, harbours, transways, motor transport,
gas, electrical generating and transmission, pumping or similar essential or public
utility services carried out in general engineering works and foundries and which are
necessary to enable such concerns to maintain their main manufacturing processes,
production or services during normal working hours;
(c) repairs to deep-sea ships and repairs to commercial air-craft done in a factory
which are essential to enable such ships or air-craft to leave port at proper time or
continue their normal operations in a sea-worthy or air-worthy condition, as the case
may be; and
(d) repairs in connection with a change of motive power, for example, from steam to
electricity or vice versa, when such work cannot possibly be done without stoppage of
the normal manufacturing process.
2. Periodical cleaning is not included in the terms "examining" or repairing".]
Chapter VII
Employment of Young Persons
Notice prescribed under sub-section (3) of Section 72
Previous and next
Questions people ask
Is rule 99 of the Factory rules 1962 still in force?
No repeal of the Factory rules 1962 is recorded.