Rule 7, The Factory rules 1962: Renewal of licence
The Factory rules 1962 - Rule 7
Text of rule 7
Renewal of licence
7. Renewal of licence. - (1)(a) An application for the renewal of a licence shall be
made to the Chief Inspector in Form No. 4, in duplicate, not less than 30 days before
the date on which the licence expires. The application shall be accompanied by the
treasury chalan as the proof of the payment of the amount of fees as specified in the
Schedule given under Rule 6 :
Provided that the State Government may by general or special order, extend the
period for application for renewal of a licence.
(b) No application for the renewal of licence made after the expiry of the period
specified in sub-rule (a), or if the period is extended, after the expiry of such extended
period, be entertained and the licence renewed unless it is accompanied by a treasury
chalan as the proof of payment of the amount of fees specified in the Schedule
referred to sub-rule (a) and an additional fee equal to 25 per cent fees payable for the
licence which is to be renewed.
[(2)(a) On receipt of the application under sub-rule (1), the Chief Inspector may if he is
satisfied that there is no objection to the renewal of the licence, renew the same for a
period not exceeding one year or may after recording the reasons, refuse the renewal
thereof on any of the grounds specified in the proviso to sub-rule ((2) of the Rule 6.
(b) The Chief Inspector may also refuse the renewal of the licence on the ground that
the applicant has been guilty of repeated contraventions of the provisions of the Act or
these rules or both, or the applicant has obtained the licence by fraud or by
misrepresentation :
Provided that, in any case falling under clause (a) and (b) before refusing any licence,
the applicant shall be given an opportunity to show cause as why licence should not
be refused :
Provided further that, where the Chief Inspector refused to grant or renew a licence,
he shall record in writing the reason for such refusal and communicate the same to
the applicant.]
8. Upon submission of an application in accordance with Rule 6, 7, 9 or 10 the
premises in respect of which such application is made shall be deemed to be duly
licensed, until the Chief Inspector has passed an order either granting or refusing to
grant or renewal or amendment or transfer of the licence.
[Explanation. - For the purpose of this rule, an application for the grant or renewal of a
licence shall be deemed to have been duly made only if it is in the prescribed form
and is filled in with all relevant particulars and is accompanied by a treasury challan as
proof of payment of the fees in accordance with the Schedule annexed to Rule 6.]
Previous and next
Questions people ask
Is rule 7 of the Factory rules 1962 still in force?
No repeal of the Factory rules 1962 is recorded.