Rule 15, Mineral Concession Rules,1960: Licence to be executed within three months
Mineral Concession Rules,1960 - Rule 15
Text of rule 15
Licence to be executed within three months
15. Licence to be executed within three months : - (1) Where on any
application for a prospecting licence an order has been made for the grant of such
licence, a deed granting such licence shall be executed within ninety days of the
date of the communication of the order or such further period as the State
Government may allow in this behalf, and if no such deed is executed within the
said period due to any default on the part of the applicant, the State Government
may revoke the order granting the licence and in that event the fee paid shall be
forfeited to the State Government.
.
(2) The deed referred to in sub-rule (1) shall be in Form F, or in a form as
near thereto as circumstances of each case may require.
(3) The date of the commencement of the period for which a prospecting
licence is granted shall be the date on which the deed is executed under
sub-rule (1).
2[15A. Where on an application for grant of sanction to transfer the
prospecting licence under clause (vii) of sub-rule (1) of rule 14, the State
Government has granted sanction for transfer of such licence, a transfer deed in
Form P, or a form as near thereto as possible shall be executed within three
months of the date of the consent, or within such further period as the State
Government may allow in this behalf.]