Rule 5, No. 2/B1-105/60/6126, dated 22nd August, 1960: Production of certificate
No. 2/B1-105/60/6126, dated 22nd August, 1960 - Rule 5
Text of rule 5
Production of certificate
5. Production of certificate. - Boiler Operation Engineer holding a certificate of
proficiency under these Rules shall, at all reasonable times during the period any boiler
is in his charge or attendance, be bound to produce such certificate when called upon to
do so by any of the persons empowered under Section 15 to call for the production of a
certificate or a provisional order granted under the Act.
Previous and next
← Rule 4Competent person shall possess certificate and extent of qualificationRule 6 →Owner to furnish Chief Inspector with particulars of certificates
All provisions of No. 2/B1-105/60/6126, dated 22nd August, 1960
Questions people ask
Is rule 5 of No. 2/B1-105/60/6126, dated 22nd August, 1960 still in force?
No repeal of No. 2/B1-105/60/6126, dated 22nd August, 1960 is recorded.