Rule 11, Mines and Minerals (Development and Regulation) Rules, 1957: Terms and conditions of a prospecting licence and composite licence
Mines and Minerals (Development and Regulation) Rules, 1957 - Rule 11
Text of rule 11
Terms and conditions of a prospecting licence and composite licence
11. Terms and conditions of a prospecting licence and composite licence.- (1) Every
prospecting licence holder or a composite licence holder shall, in addition to the
conditions specified therein, be subject to the following conditions:
(a) the licencee may win and carry for purposes other than commercial purposes:
(i) such quantity of the minerals within the limits specified under column (3)
of Schedule VIII without any payment; or
(ii) such quantity of the minerals not exceeding the limits specified under
column (4) of Schedule VIII, on payment of royalty specified in the
Second Schedule to the Act:
Provided that the licensee may win and carry away for purposes other
than commercial purpose any quantity of limestone not exceeding 500
tonnes for testing its use in any industry specified by the Central
Government in this behalf, on payments of royalty specified in the Second
Schedule to the Act:
Provided further that if any quantity in excess of the quantities specified
in this clause is won and carried away, the State Government may recover
the value of the excess quantity of minerals won and carried away and also
impose penalty under section 21;
(b) the licencee may, with the written permission of the State Government, carry
away quantities of minerals in excess of the limits specified in Schedule VIII, on
payment of royalty specified in the Second Schedule to the Act, for chemical,
metallurgical, ore-dressing and other test purposes;
(c) If the licencee holding a prospecting licence or a composite licence, is convicted
of illegal mining and there are no interim orders of any court of law suspending
the operation of the order of such conviction in appeals pending against such
conviction in any court of law, the State Government may, without prejudice to
any other proceedings that may be taken under the Act or the rules made
thereunder, after giving such licencee an opportunity of being heard and for
reasons to be recorded in writing and communicated to the licencee, cancel such
prospecting licence and forfeit whole or part of the performance security;
(d) the licencee shall, within sixty days from the date of discovery of any mineral
specified in Part B of the First Schedule to the Act, apply to the Secretary,
Department of Atomic Energy, Mumbai, through the State Government, for
grant of a licence to handle such minerals under the provisions of the Atomic
Energy Act, 1962 (33 of 1962) and the Mines and Minerals (Development and
Regulation) Act 1957 (67 of 1957) and the rules made thereunder and the
Department of Atomic Energy shall intimate the State Government regarding the
issue of the licence in this regard;
(e) the licencee shall restore, to the extent possible, the landform affected by
prospecting operations;
(f) the licencee shall comply with the provisions of the Act and the rules made
thereunder including rules made under section 18;
(g) every licencee shall maintain an accurate and faithful account of all expenses
incurred by him on prospecting operations and also the quantity and other
particulars of all minerals obtained during such operations and their despatch;
(h) every licencee shall clear undergrowth, brushwood and trees only with the prior
written approval of the Deputy Commissioner or Collector, as the case may be,
in order to make and use any drains, water courses or water on the said lands for
such purposes as may be necessary for effectually carrying on the prospecting
operations and for the workmen employed thereon. The licencee shall always
ensure that such use shall not diminish or interfere with the supply of water to
which any cultivated land, building or watering place, for livestock has been
accustomed and shall ensure that its prospecting operations do not foul or pollute
streams, springs or wells;
(i) the licencee shall have the right to erect and bring upon the said lands all such
temporary huts, sheds, structures, steam and other engines, machinery,
conveniences, chattels and effects as may be deemed proper and necessary for
effectually carrying on its prospecting operations or for the employment of
workmen thereon;
(j) save in the case of land over which the licencee has been granted a mining lease
on or before the expiry or termination of the licence, as the case may be, the
licencee shall within six months after the expiry or termination of the licence or
date of abandonment, whichever is earlier, securely plug any borehole and fill up
or fence any holes or excavations that may have been made in the lands to the
extent required by the Deputy Commissioner or Collector, as the case may be.
The licencee shall also restore the surface of the land and all buildings thereon
which may have been damaged or destroyed in the course of its prospecting
operations, provided that it shall not be required to restore the surface of the land
or any building in respect of which full and proper compensation has already
been paid by it;
(k) failure on the part of the licencee to fulfil any of the terms and conditions
hereunder or under the prospecting licence shall not give the Central
Government or State Government any claim against the licencee or be deemed a
breach of the licence, in so far as such failure is considered by the relevant
Government to arise from force majeure. In the event of any delay by the
licencee to fulfill any of the terms and conditions hereunder or under the
prospecting licence on account of a force majeure event, the period of such
delay shall be added to the period fixed by these rules or the prospecting licence.
In this clause the expression “force majeure” means act of God, war,
insurrection, riot, civil commotion, strike, earth quake, tide, storm, tidal wave,
flood, lightning, explosion, fire, earthquake and any other happening which the
licencee could not reasonably prevent or control; and
(l) the licencee shall, on the expiry or termination of the licence or the abandonment
of the prospecting operations, whichever is earlier, remove expeditiously at his
own cost, all buildings, structures, plant, engines machinery, implements,
utensils and other property and effects erected or brought by the licencee and
standing or situated on the said lands together with all minerals won by the
licencee and situated on the said land, provided that it shall not be required to
remove any of the above from any part of the said lands which may be comprised
in any mining lease granted to the licencee during the subsistence of the
prospecting licence.
(2) The licencee shall report to the State Government the discovery of any mineral not
specified in the licence within a period of sixty days from the date of such discovery,
and consequent upon such reporting the newly discovered mineral except those
minerals specified in Part A and Part B of the First Schedule to the Act shall be
deemed to have been included in the composite licence:
Provided that the holder of a prospecting licence granted otherwise than through
auction, shall have no right over the discovered mineral and such mineral shall not be
included in the licence.
(3) A prospecting licence or a composite licence may contain such other conditions as
the State Government may deem fit to impose, namely:-
(a) compensation for damage to land in respect of which the licence has been
granted;
(b) indemnity to Government against the claim of a third party for any damage,
injury or disturbance caused to him by the licencee;
(c) restrictions regarding felling of trees on unoccupied and unreserved Government
land;
(d) restrictions on prospecting operations in any area prohibited by any competent
authority;
(e) operations in forest land;
(f) conditions regarding entry on occupied land;
(g) facilities to be given by the licencee for working other minerals in the licenced
area or adjacent areas;
(h) filing of civil suits or petitions relating to disputes arising out of the area under
prospecting licence:
Provided that in case of a composite licence, the State Government shall
specify such conditions in the tender document for auction for grant of composite
licence.
(4) The State Government may, either with the previous approval of the Central
Government or at the instance of the Central Government, impose such further
conditions as may be necessary in the interest of conservation and development of
minerals.
(5) In the case of breach of any condition imposed on any holder of prospecting
licence or composite licence under the Act and the rules made thereunder, the State
Government may, by order in writing, cancel the licence and/or forfeit in whole or
part, the amount of performance security deposited by the holder of prospecting
licence or composite licence, as applicable, under the Act and the rules made
thereunder:
Provided that no such order shall be made without giving the licencee a
reasonable opportunity of representing his case.
(6) The minimum area for grant of a prospecting licence or composite licence shall not
be less than the minimum area for which a mining lease may be granted in accordance
with the sub-rule (5) of rule 12 and the maximum area shall be in accordance with
section 6 as applicable to a prospecting licence.
Previous and next
← Rule 9Composite licence and mining lease granted through auctionRule 12 →Terms and conditions of a mining lease
All provisions of Mines and Minerals (Development and Regulation) Rules, 1957
Questions people ask
Is rule 11 of Mines and Minerals (Development and Regulation) Rules, 1957 still in force?
No repeal of Mines and Minerals (Development and Regulation) Rules, 1957 is recorded.