Appendix I, THE INDIAN ELECTRICITY RULES, 1956: APPENDIX I
THE INDIAN ELECTRICITY RULES, 1956 - Appendix I
Text of appendix I
APPENDIX I
APPENDIX I
SYLLABUS FOR THE OPERATING AND
SUPERVISORY STAFF ENGAGED IN THE
OPERATION AND MAINTENANCE OF THE
THERMAL POWER STATIONS
(General course for Electrical and Mechanical)
Item No. Particulars Number
of Hours
1 2 3
I Concept of modern Thermal Station: Central Station and utility
systems, base load and peaking stations, concept of unit system,
typical thermal cycles, parameters, heat rates, fuel rates, steam rates,
typical heat balance of boiler, turbine and generator
4
II Choice of location of large thermal station Site availability, water
requirements, fuel, load, centres, transport facilities, air pollution,
topography, choice of size of generating units
3
III Plant lay out in large central station including machine
arrangements, equipment layout and auxiliary arrangements
3
IV Constructional details of large pulverised fuel boilers and
auxiliaries
(i) Water and steam drums, heaters and tubes.
(ii) Types of furnace and firing arrangements, burner details.
(iii) Economisers, primary, secondary, superheaters, re-heaters and
attemperators.
(iv) Forced drough, Induced draught, Primary Air exhauster and gas
recirculation fans, compressors.
(v) Types of coal mills (balls/recess, balltube, bowl roller) stoker,
coal feeders.
(vi) Air preheaters, Lunstorm, tubes, steam.
(vii) Dust extraction plant-electrostatic, mechanical.
(viii) Soot blowers: steam/compressed air operated.
(ix) Station compressed air system-reciprocating and rotary
compressors.
(x) Oil handling and firing equipment.
(xi) Boiler mountings, gauge glasses, safety valves, stop valves,
startup devices, stampling, chemical dosing, continuous blow down.
(xii) Refractories and laggings as used in modern power stations.
16
V Turbine and auxiliaries, constructional details
(i) Principle of operation, heat conversion cycles, types of turbines.
(ii) Casing, steam chests, ‘Wheel blading, nozzles, diaphragms,
glands, flanges and bolt heating, bearings.
(iii) Condenser and vacuum extraction plant, ejectors.
(iv) Lubrication system, pumps, coolers, filters, shaft turbines and
lifting gear
(v) Feed water booster and extraction and colling water pump.
(vi) Low pressure and high pressure feed water heaters, deaerators
and evaporators.
(vii) High and low power by pass systems.
(viii) Oil purifications unit.
9
VI Alternators and excitation systems
(i) Constructional details of alternators, methods of cooling
(Hydrogen/air cooling).
(ii) Main and pilot excitors, voltage regulators, types and
characteristics, amplidyne and magnetic amplifier.
(iii) Methods of grounding.
6
VII Coal handling plant: Tipples, hoppers, vibratory feeders and
conveyors,
crushers, magnetic separators and pulleys
6
VIII Ash and slag handling plant: Electrostatic precipitators,
methods of conveying pneumatic, vacuumatic, hydraulic; bucket
elevators conveyors, screw extractors
2
IX Water sources, treatment: Raw water pumping station,
domestic, circulating and boiler make up water treatment, river salinity,
local water conditions, their variations in different seasons and effects
on power station operation
7
X (i) Fuels: Solid, liquid and gaseous fuels-analysis
(ii) Coal-types and suitability for different kinds of boilers-
alterations in firing methods due to change of coal composition
6
XI Basic flow diagrams in power station practice
(i) Coal and fuel oil cycle
(ii) Air and gas cycle
(iii) Fly ash and slag handling arrangements
(iv) Condensate and feed heating cycle (from condenser hotwell
upto economiser)
(v) Steam and water cycle (from economiser to turbine inlet).
(vi) Circulating water cycle
(vii) Hydrogen filling in generator and hydrogen gland sealing of
generator.
(viii) Bearing cooling system.
8
XII Direct and closed cooling circuits, cooling towers, types and
characteristics
2
XIII D.C. & A.C. power supply for auxiliaries arrangements of units
and station boards, station lighting and automatic changeover
4
XIV Transformers: main transformers, interconnecting transformer,
station/ unit transformers, voltage grounding transformers, types of
connections paralleling, tapchanger gear
5
XV Out-door switchyard single line diagrams, busbars, circuit
breakers, isolators, current transformers, potential transformers,
lightning arrestors, grounding
5
XVI Indoor and outdoor switchgear: types bulk oil, minimum oil, air
blast, air break-constructional details
3
XVII Instrumentation and measurements: constructional details of
measuring instruments for pressure, flow temperature, level, draught,
vibration eccentricity, conductivity, pH value, differential expansion,
oxygen analyser, current, power, reactive power, frequency, energy,
winding temperature.
Auto-controllers, hydrogen purity meter. Axial shift indicator and
recorder, flue gas analysers, Megger-its use for primary
detection of faults
16
XVIII Operation, control and supervision
(i) General boiler start-up procedure.
(ii) Operation of boilers under different loading conditions, soot
blowing.
(iii) Banking and preservation of boilers.
(iv) Demonstration wherever possible through simulators of various
operating conditions.
(v) Handling of boiler under emergency conditions such as tripping
of turbo-alternator set, high/low drum levels, flame failure, failure of
supply to auxiliaries.
(vi) General start-up procedure for high pressure multicy under
reheat type turbines froth cold, warm and hot conditions.
(vii) Handling of turbine, generator and auxiliary plant under
emergency conditions, such as vaccum failure, low feed water,
condenser levels, excitation failure, circulating water failure, feed water
heater high levels, excessive vibration, water or oil ingress in
generator, failure of lubricating, sealing oil circuits.
(viii) Alternator-synchronising, loading, parallel operations, MW &
MVAR sharing.
15
XIX Controls and Protection-sequential operation and interlocks:
(i) Boiler and auxiliaries
(ii) Turbines and auxiliaries.
(iii) Combustion control-pressure, fuel, air and feed heating
cycle
(iv) Analysis of feed and boiler water, fuel gas at station laboratory
(v) Feed water and feed heating cycle controls
(vi) Turbine governing, speed setting, speed drop setting and
control circuits
(vii) Generator protection, under-voltage, over-voltage, differential,
reverse power, under excitation, negative phase sequence, earth fault
with types of the relays used
(viii) Importance of sequential inter-locks
(ix) Transformer protection-differential, overload, earth faults, high
(x) Types of motors and variable speed-drive and speed controls
(xi) Various types of pumps and their starting and control.
(xii) Steam temperature control
(xiii) Furnace purging
2
2
2
4
2
3
4
2
4
4
3
3
3
XX Fire fighting and mulsifier type protection 3
XXI General safety precautions, treatment of electrical or acid alkali
burn, permit to work, first aid
2
XXII Indian Boiler Rules, Factory Act, Indian Electricity Act, 1910,
Electricity (Supply) Act, 1948, Indian Electricity Rules, 1956 and other
statutory regulation concerning Power Stations (General outline)
4
XXIII General plant maintenance procedure, PERT/CPM Methods,
Power Station records and calculation of efficiency
10
XXIV Various type of valves, traps, their constructional details and
application
2
XXV Cranes, hoists, characteristics and control 3
XXVI Personnel management, duties and responsibilities, Labour
Laws and Labour Welfare
6
XXVII Broad principles of material management and inventory control
4
TOTAL 186