Rule 67, The Rajasthan Boilers Rules,1954: Remuneration of assessor
The Rajasthan Boilers Rules,1954 - Rule 67
Text of rule 67
Remuneration of assessor
67. Remuneration of assessor. - The assessor shall be remunerated at
such rate, as may be prescribed by the State Government and be allowed the
travelling expenses incurred by him in attending the court.
@[68. Penalty. - A person who does or commits to do any act prohibited or
prescribed under the rules shall be punishable with a fine, which may extent
to one hundred rupees.]
Appendix To The Rajasthan Boiler Rules, 1954
Form 'A'
Register of Boiler
(Rule 8 the Rajasthan Boiler Rules, 1954)
Registry
No.
Date of
registration
Boiler
rating
Type
of
boiler
Name and
place of
manufacture
Year of
construction
Maker’s
number
and
mark, if
any
Name
of
owner
Place
where
in use
Remarks
(transfer)
etc.
1 2 3 4 5 6 7 8 9 10
------------------------------------------------------------------------------------------------------
@. Substituted and added vide Notification No. D. 5899/F 3 (22) Lab. 159, dated
1.7.1960 published in Rajasthan gazette part III-B supplement No. 19 dated 11.8.1960
In Part II of the register, column I should contain the registry number and
letters.
Provisions shall be made for the removal of lagging or brick-work or
other concealing part and for the drilling of plates, if required by the inspector,
and for verifying the pressure gauge and safety valve dimensions and
weights. All smoke tubes, smoke-boxes and external flues shall be swept
clean.
Provision shall be made for the effective disconnection of all steam and
hot water communication with any other boiler under steam as prescribed in
Part III of the regulations. This shall be effected by the removal of a length of
pipe from the steam feed and blow down piping or by the insertion of
substantial blank flanges. Where blank flanges are employed they shall be
inserted between the flanges of the chest and the pipe attached to it. No
blank flange shall be inserted between a safety valve chest and the boiler.
Note. - These provisions as to effective disconnection shall extend to every case
wherein a person is sent or with the assent of the owner or person-in-charge
goes into a boiler for any purpose.
Form 'B'
Indian Boilers Act, 1923
(V of 1923)
Notice for Examination of Boiler under Sections 7 and 8
(Rule 33)
No....... of 19 .
Chief Boiler Inspector’s Office.
Dated the...................... 19 .
To
.......................
......................
......................
In reply to your application, dated ..................you are hereby informed that
Boiler Registry No.................. at the above named premises will be
thoroughly examined/hydraulically tested by the Government Inspector on the
............To enable the examination to be made, you are required to-
(a) afford to the inspector all reasonable facilities for the examination and
all such information as may be reasonably be required by him;
(b) have the boiler properly prepared and ready for examination in the
prescribed manner; (See instruction on reverse)
(c) provide in the case of a boiler about to be registered such drawings,
specification and certificates and other particulars as may be
prescribed;
(d) produce to the inspector the last certificate of the boiler at the time of
inspection.
Inspector of Boilers
(Reverse of Form B)
(See reverse for preparation required)
Preparation For Examination
(a) Preparation for inspection
At every inspection of a boiler for the grant or renewal of a certificate, the
boiler shall be empty and thoroughly clean in all its parts. All doors of
manholes, hand holes and sight holes and cleaning plugs and all caps in the
headers and mud drums of water tube boiler, all fire bars bearers front plates,
bridge plates, fire bridges, brick arches, oil fuel burners and mechanical
stoker fittings shall be removed. All valves and cocks comprising the boiler
mountings shall be opened up and taken apart and the valves or cocks
ground, when necessary, before the inspector’s visit.
(b) Preparation for Hydraulic Test
The chests of all mountings subject to steam pressure shall be in place and
shut tight or blank flanged. The safety valves shall either be jammed down or
removed, and the chest-openings blank flanged. The attachment for the
inspectors pressure gauge and the nipple for connecting the inspector’s test
pump hose shall be in order. All doors shall be properly joined and tightened
up. The boiler shall be completely filled with water, care being taken to allow
all air to escape and, if possible, a preliminary test not exceeding the working
pressure of the boiler shall be taken before the inspector’s visit to test the
tightness of the joints.
Preparation now required
(A), (B),
_____________________________________________________________
___________________________________________________________
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
___________________________________________________________
Form 'C'
General working of Boilers-Instructions for boiler attendants
(Rule 7)
General working of boilers-Instructions to boiler attendants. - These
instructions should be frequently and carefully studied, with a view to keeping
in mind the precautions to be observed, and the ordinary procedure to be
followed in the safe working of boilers. '
Precautions before starting the fires. - Before starting the fires in a boiler,
the attendant should-
(1) see that there is sufficient water in the boiler and that gauge cocks are
working freely,
(2) ease safety valves, or open cock on top of boiler to allow air to
escape,
(3) see that the blow-off cock is fully closed and tight,
(4) see that the safety valves and feed check valve are free and workable,
(5) see that water is not leaking from any part of the boiler,
(6) note if the pressure gauge pointer is at zero,
(7) see that the feed pump is in working order.
He must not rely on the supposition that the water he has previously put in is
still in the boiler, as it may have run out without his knowledge through a leak
or open cock, nor can he be sure that the gauge glass shows the true water
level until he has tested it. This is done in the following manner, shut off the
lower gauge cock and empty the glass by the drain cock, then shut the drain
cock and open the gauge cock, if every thing is in order, the water will then
rise in the glass to the same height as before.
Raising steam. - In getting up steam in all types of boilers, the operation
should be as gradual as circumstances will allow. Nothing turns a new boiler
into an old one sooner than getting up steam too quickly. Forcing the fires
when starting work if liable to cause of the steams striving and tubes of the
boiler. In the case of large boilers generally steam should not be got up in
less than six hours. Before getting up steam the water level should be
observed, to ensure that the water is at the proper height in the glass the
pressure gauge noted, and the safety valves tried to see they are free. The
blow-off cock should be examined to see that it is completely shut and tight.
Pressure gauge. - The pressure or steam gauge should be kept in order,
and be in such a position as to be easily seen by the boiler attendant. There
should be a plain mark on it showing the highest pressure allowed for the
boiler, and the dial should be kept clean so that the figures may easily be
read.
Steam pressure. - Ordinarily the safety valve will prevent the steam from
rising much above the working pressure, but if the steam gauge shows so
rapid an increase of pressure as to indicate danger of exceeding the highest
limit, water should be immediately fed into the boiler and the dampers
partially closed in order to diminish the effect of the fire. If however, the water
has fallen so low that there is danger of an accident from this cause, the fires
should be withdrawn before feeding in water, the safety valves eased, and if
the engine is at rest, it should be started so as to reduce the pressure.
The safety valves are provided to guard against over pressure. They
should be moved by hand every day so as to prevent them from sticking. If
moved only occasionally, they are liable to leak.
The valve can be tested by slowly raising it a little, and when let down, it
should close perfectly tight. It should never be opened by a sudden knock or
pull. If it does not close tight turn it on its seat until it fits, or when its
construction does not permit this, raise it slowly a few times and let it down
again, but on no account must the valve be screwed down further or loaded
more than what has been allowed by the inspector.
Safety valves must be over loaded, and spring valves should have ferrules
and other provisions against their being screwed down too far. In case of an
accident resulting from wilful over loading the culprit might be held criminally
responsible at the official enquiry or in quest
.
Low Water Safety Valves. - If there is a low water safety valves test it
occasionally the lowering the water level to see that the valve begins to blow
the right point. It should give warning "before" the water level has sunk too
low, and before damage can be done. When the boiler is opened examined
the floats and lower and see that they are free and that give the valve the full
rise. With the ordinary type of high steam and low water safety valve the float
should be down at its lowest position and are valve full open when the boiler
is empty.
The Water Gauges. - These will be kept best in order by frequently blowing
through. The cocks are thus kept in good working condition without leaking.
Blow through the drain cock at the bottom of the gauge, and shut and open
the steam and water cocks every few hours. These cocks should be blown
through more frequently when the water is dirty. Should either of the
Passages become choked, or whenever the water in the gauge glass moves
sluggishly, the passage must be cleaned. This is best done with a wire. The
gauge glass is so arranged that its top cock connects with the steam space
and its bottom cock is below the water line. The water line will ordinarily be
near the centre of the glass tube. Always test the glass water gauges
thoroughly the first thing in the morning and at the commencement of every
shift. This is done by first opening the drain cock, then shutting the upper
cock which should give water, the upper cock should then be opened and the
bottom cock closed which should give steam during this test the drain cock
should be kept open.
If water and steam do not appear in proper order the cocks are choked
and the passages should be cleaned. To lessen the risk of breaking to the
gauge glass the water cock should always be reopened after the steam cock.
Gauge glasses with a narrow white strip running the whole length of the glass
on the side next the boiler are recommended, as they show the water line
more clearly especially when the water is dirty.
The Indian Boiler Regulations require every water gauge glass to be
fitted with a guard to prevent injury to the attendants. See that it is always in
place, and clean, when there is steam in the boiler.
Special note. - It does not follow that there is plenty of water in the boiler
because there is plenty of water in the gauge glass. The passage may be
choked and empty gauge glasses are sometimes mistake for full ones, and
explosions have resulted therefrom. Hence the importance of keeping the
gauge cocks perfectly tight and clean and of blowing through the test cocks
frequently.
A large number of accidents have been due to inoperative water gauge, and
to negligence of the attendant in not carefully reading the water level.
The blow off cock. - The blow-off should be used daily if the water is at all
dirty or sedimentary, especially with Locomotive type and Vertical Boilers’ as
their narrow water spaces are liable to get choked with mud, which so on
hardens into a solid mass. The amount of water to be blown out depends the
size of the boiler and can be determined only from experience. When blowing
out the best result is obtained, if the water has been at rest for sometime to
(say before the engine is started) thus giving the sediment time to settle if the
feed water is clean, merely turn the cock on round.
The scum cock. - When scum cocks are fitted, if the feed water is dirty a little
should be blown-off daily if the water is clean, merely turn the cock round.
Before opening the scum cock see that the water is at the height indicated by
the water level pointer, otherwise the scuming will be ineffective. Water
should be blown from the surface through the scum cock when steam is
being drawn off i.e. when the engine or other machinery is working.
Manhole and other door joints. - When making such joints, the joining
materials should never be of round sectioned packing. Care must be taken
that the spigot of the door is centrally placed in the hole as many accidents
have resulted from packing being blown out between the spigot and side of
hole even when the clearance was only ⅛ inch. The nuts must be carefully
and evenly tightened. Further tightening should be made during the process
of heating up the boiler when raising steam.
Steam pipes. - When properly arranged should give no trouble. Frequently
however, they are so designed as to contain packets in which, while out of
use, condensed steam accumulates. Such water is exceedingly dangerous
and great care should be taken lo see that the pipes are properly drained
before the stop valves opened otherwise 'water hammer' will take place even
with the best designed steam pipes, and disastrous explosion causing loss of
life and property may occur.
Scale and grease. - Roughly speaking, scale offers a hundred times as
much resistance to the passage of heat as does a similar thickness of steel or
iron. A half inch furnace plate covered with 1/10' scale is as efficient a heat
retarder as a steel furnace 10 inches thick grease is about ten times worse
than scale. In a boiler at work the temperature of a clean furnace plate is only
slightly in excess of that of the water in the boiler: but if scale of grease is
interposed between the water and the plate, the latter acquires a temperature
more nearly approximating that of the flame with which it is in contact. If the
fire is fierce (artificial drought) the furnace tube may grow so not that it
elongates considerably. If, in addition, cold air is admitted during each firing a
concertina action of the furnace tubes place, which is one of the worst causes
of boiler wear and tear.
Wear and tear can be reduced and the life of a boiler prolonged if scale
and grease are prevented from accumulating in a boiler. The combined effect
of scale of grease and artificial drought are disastrous, scale also causes
waste of fuel.
Grease. - A mixture of sedimentary water, soda and grease produces an
adhesive scum. Where this suspected the water level should never be
lowered below the furnace top unless the boiler is afterwards entered in this
scum cleaned off the furnace plate before jiring again.
Scale removal. - The customary method is not a satisfactory one. The boiler
is emptied and then cooled down by opening all the manholes and the result
is that the scale, which would otherwise be soft, hardens through contact with
the air, and requires laborious chipping off.
A very effective, but slower method, is to retain the water in the boiler
until cool, and not to run it out until the mean are ready to enter the boiler with
water hose, brushes and scrapers. The scale will then be soft and easily
removable.
If time is a consideration, the cooling be accelerated by adding cold feed
to the hot water in, the boiler and slowly running off the cooled water. Another
method is to blow-off the boiler with the lowest possible pressure (not more
than 20 lb.) and to keep it closed until cold. The scale will then be easily
removed.
Treatment of feed water. - Many feed water require soda or other chemical
to arrest corrosion or to change the nature of the scale.
There is no harmless chemical which will remove scale or sediment
when it has once got into the boiler, and the only effective process is to purify
the feed water before it enters the boiler. By this means the sediment, and
generally too the added chemicals, can be deposited in tanks or in filters, and
therefore, never goes into the boiler, Excepting when the water obtainable is
very good, water purifying apparatus ought to pay any boiler owner,
particularly at those works where three or more boilers are in constant work,
boiler owners wishing to have definite advice as to the best treatment of their
feed water should have it analysed at some chemical laboratory and
ascertain the best treatment of their feed water should have it analysed at
some chemical laboratory and ascertain the best treatment in the particular
circumstances.
Special attention is drawn to the not infrequent very bad practice of
allowing the waste steam from the engine cylinders or pumps to be drained
into the boiler feed water tanks. The waste steam from cylinders is always run
with a certain amount of oil matter which will be deposited in the feed water
tanks and ultimately be pumped into the boiler with possible disastrous
results as it will be obvious to every careful boiler attendant that should the oil
be deposited on the furnace crowns. They may become overheated and
collapse.
It should be the first care of the boiler owner and the boiler attendant to
see that the feed water is kept as pure as possible. Impure feed water means
additional expense on the up keep of the boiler.
Preservation of boilers when not in use. - Steam boilers when not in use
are liable to deterioration from corrosion and unless well cared for, and made
rust-proof they may depreciate more rapidly than when in use. They should
be thoroughly drained and thoroughly dried and all valves, cock and openings
closed so as to exclude moisture. Another plan is to fill the boiler with water to
which about 1/10 per cent caustic soda has been added.
Special instruction for Boiler No..........
The boiler should be opened up and thoroughly cleaned after a period of work
which should not exceed....................A record of such cleanings should be
maintained and produced, when required by the inspector.
Dated.............
Inspector of Boilers
Form 'D'
Accident Report under Section 18(1) of the Indian Boilers Act, 1923
To
The Chief Inspector of Boilers,
Rajasthan, Jaipur
The undersigned begs to report that an accident occurred in
the.................... Factory at ................... on dated ...................
hour.............. causing slight/serious injury as detailed below:-
1. Nature of accident..........................................................
2. Cause of accident...........................................................
3. Full details of damage to Boiler No.........................................
4. Full details of damage to steam pipe........................................
5. Full details of injury caused to any person.................................
Date.........
Signature of the owner or agent of the boiler
Previous and next
Questions people ask
Is rule 67 of the Rajasthan Boilers Rules,1954 still in force?
No repeal of the Rajasthan Boilers Rules,1954 is recorded.