Rule 29, The Rajasthan Boilers Rules,1954: Repairs to boilers
The Rajasthan Boilers Rules,1954 - Rule 29
Text of rule 29
Repairs to boilers
29. Repairs to boilers. - Under Section 12 of the Act the sanction of the
Chief Inspector to all repairs proposed for boilers must be obtained before
hand.
A few water tubes or smoke tubes however, may in an emergency be
renewed pending the sanction of the Chief Inspector but all such cases must
be reported immediately to the Chief Inspector who may, if he deems fit,
notify his sanction to the owner without verification of the renewals by an
inspector.
Generally in repairing boilers the object to be obtained is to make up for
damage or wastage by suitable compensation, either by renewal or repair of
the part affected. Covering patches applied with the object of hiding defects
are a source of danger and must not be passed.
Welding by electric and oxy-acetylene processes may be employed in
the repair of boilers, but as the efficiency of the welding depends largely on
the skill and care of the operator each case will have to be decided on its
merits.
Extensive repairs such as renewal of furnaces, end plates, parts of
shell, fire boxes, girder, etc., should be supervised so far as his other duties
permit, by the inspector, and at such times when fire boxes and smoke tubes
of locomotive type boilers are withdrawn, advantage of the opportunity should
be taken to inspect the internal parts otherwise inaccessible to close
inspection. Repairs to boilers are prescribed in Chapter IX, Regulation 392 of
the Regulations.
Previous and next
Questions people ask
Is rule 29 of the Rajasthan Boilers Rules,1954 still in force?
No repeal of the Rajasthan Boilers Rules,1954 is recorded.