Rule 12, UP ELECTRICITY DUTY RULES 1952: Provision of installing separate meters
UP ELECTRICITY DUTY RULES 1952 - Rule 12
Text of rule 12
Provision of installing separate meters
12. Provision of installing separate meters.—Where there is a
combined installation in which part of the energy supplied or consumed
is dutiable and part is exempted and where the energy supplied or
consumed is utilized for such categories for which the rates of duty are
different, the licensee, appointed authority and other person shall
provide and maintain separate, suitable and correct meters or sub-
meters to register the quantities of different kinds of consumption
separately : .
meded that if any consumer has already installed suitable and
correct meters for recording the said energy separately the licensee or
appointed ‘authority may not install, separate meter or sub-meter for
the purpose but the responsibility for maintaining in good and
correct condition the meters installed by the consumer shall lie on him
and he shall be entitled to take necessary action in accordancé with sub-
section: {4) of Section 26 of the Indian Electricity Act, 1910, in every
respect : 1
Provided fuirther that it shall also be obligatory on the consumer
at the time of taking connection to apprise the licensee or -the
appointed authority of the purposes for which the energy will be
consum_e'd”by him and that he shall also notify the licensee or the
appointed authority, as the case may be, fifteen days in advance of the
charges, if any, be proposed by him after the commencement of supply, in
the mode- of consumption for which different rates exist for the levy of
duty: fowd ) . :