Guidelines for Building Plan Approval Process
Notification - Capital of Punjab (Development and Regulation) Act, 1952
- Kind: Notification
- Under: Capital of Punjab (Development and Regulation) Act, 1952
Text of this notification
Notifications and/Ordcrs 659
#
35. All the buildings which are or will be located on plot of one kanai and
above shall have rain harvesting system to recharge ground water installed as per
the specifications given by the Administration. All the existing buildings shall install
rain water harvesting system to recharge lhe ground water within Iwo years from
the date of issuance of this notification.
36. The Dwiicr/lessee of any existing building, who may like to avail the
benefits) of additional volumetric control being granted through these orders shall
only be granted the benefit if they upgrade the parking facilities as per norms
given in this order (wherever applicable), set up the solar water heating system,
duel flushing system and rain water harvesting system to recharge ground water
in the respective buildings. -(J ■
37. All the new public buildings which shall be approved after issuance of
these orders shall conform to requirements of Persons with Disabilities Act, 1995
and Rules made thereunder. The owncrs/lcssee/occupier of Existing Public Build
ings shall make their buildingas friendly as possible to persons with disabilities.
38. In case of any contradiction between these order(s) and any order is
sued in past by Chief Administrator, the provisions of these orderfs) shall prevail.
Before these orders are made part of Budding Rules, they shall be reviewed a flor
60 days.
(Published in Chandigarh Administration Gazette (Exira) dated 16-10-2008)
(133) Guidelines for Building Plan Approval Process - With a view to
ensure that the Building/Building Complexes which arc crccted/re-erected in Union
Territory of Chandigarh conform to the overall vision of the Urban Character of
the City, it is mandatory for thcowner/lessee ofthe building/buildingcomplexes to
get the building plans sanctioned.
In lhe process of streamlining the building plan approval process, the follow
ing guidelines are issued by the undersigned:—
A. There shall be two Plan Approval Committees - Upper and Lower.
B. Plan Approval Committee (Lower). - The Plan Approval Committee
(Lower) shall scrutinize and recommend for sanction to the Estate Officer, the
building plans of all residential bu ildings located up to 2 Kanals Area (except group
housing, integrated town ships) al I commercial buildings where architect ura I controls
are applicable such as SCOs, SCFs, booths, bay shops, qu let offices, dhabha sites,
godowns, timber sites and industrial properties up to 2 Kanai. These plans will not
require any concept approvals from Chief Architect, (any clarification if required
may be obtained from the Office of lhe Chief Architect, U. T., Chandigarh). Once
the plan is scrutinized and found in order, the matter will be placed and decided by
the PAC (Lower) within 30 days from the date of submission of plan.
C. Plan Approval Committee (Upper). - The Plan Approval Committee
(Upper) shall scrutinise and i ecommend die building plans for sanction of all projects
except those enlisted under heading PAC (Lower),
D. Procedure for sanctioning of building plaus:
STAGE I ■*. d
(1) Submission of Building Plans:
Al! the plans shall be submitted for approval at Estate'Office. Tito SDO
(Building) of the concerned area shall be the Nodal Officer to receive and take
further action. At the time of submission the owncr/lesseiJ-'shall submit all the
documents enlisted in the building rules to the Estate Office alongwith following:
(i) Soft copy of the drawings prepared on Auto CAD.
LENOVO-3
Text Box
660 Chandigarh Urban Development Laws
(ii) Model of the project if the site is more than 1 acre.
i (a) If the plans are to be cleared by PAC (Lower) then the matter wilt
be placed before PAC (Lower) and a decision on plan shall be
taken by PAC (Lower) within 30 days. Either the plan will be
approved or if there are any observations/objections, they shall be
communicated to the applicant within 30 days. In case of any
observation/obj ection the same have to be conveyed only once and
not in piecemeal pattern time and again if those observations are
met with and no new changes have been made, within next 15
days the plan will be cleared by the PAC (Lower).
(b) In.case the plans so submitted are to be approved by the PAC
(Upper), the following verified documents and site report will be
sent by the Estate Office to the Chief Architect:-—
he Allotment letter
♦Ownership/possession letter
* Size of plot
♦Status of land/site—including if, it is free from encumbrances,
any litigation or stay etc.
♦Financial liabilities
♦Copy ofthe previous sanctioned plan (if applicable)
♦The existing and proposed construction clearly marked on the
layout as well as plans.
♦Whether the proposal involves availing any additional benefit on
payment basis e.g. additional FAR etc.
Once the plans are received which are to be cleared by PAC (Upper), the
Estate Office shall forward two sets of plans alongwith documents attached to
the Chief Architect within a period of 7 days.
E. STAGE 2
Scrutiny and Recommendation by PAC (Upper):
The PAC (Upper) shall scrutinise the building plans received from the Es
tate Office and convey its recommendations on approval or objections/observa-
tions within a period of 60 days of receipt of building plans. The projects which
satisfy the parameters mentioned above shall be recommended for sanctioning to
the Estate Office so that the building plans arc released by the Estate Officer
after completing the due formal itics.
Once the plans have been scrutinised by the PAC (Upper) then observa
tions or objections if any have to be conveyed only once and not in piecemeal
pattern time and again and if those observations are met with and no new changes
have been made from the date of application of revised plan, the same shall be
scrutinispd and cleared within next 30 days.
PAC reserves the right to ovcrrule/rcject any proposal, which is not in con
sonance with the Building Rules, zoning regulations and orders issued under Capi
tal of Punjab (Development and Regulation) Act, 1952.
F. STAGE 3
Sanctioning Stage:
The Building plans are recommended by PAC (Upper) and PAC (Lower)
shall.be sanctioned and released by the Estate Officer after completing due for
malities within 7 days from the date of plans are received.
GL STAGE 4
* Plinth level inspection and Completion Stage:
shall.be
Notifications and Orders 661
Once the building plan has been cleared it shall be mandatory that when the
construction reaches plinth level it shall be got inspected by the Estate Office
before further construction can be taken up to avoid delay, once the application
has been made for inspection, the site has to be inspected within 20 days and if in
any case, the site is not inspected by the officials of Estate Office, within 20 days,
the same shall be deemed to have been inspected and if there fS any violation, not
only the owner/lessee of the plot shall be held responsible for the violation but also
the concerned Architect who made the plan and the concerned official of the
Estate Office who did not inspect the site within stipulated period shall also be
held responsible for the same. '
The respective Committees Which have approved the building [jlans shall
also be the competent authority to recommend completion andoccupation certifi
cate and sewerage connection. * '
II. Procedure for Dcpartnients/Organisations of Chandigarh Admin
istration: ■
Notwithstanding anything contained in these orders,'as regards to the
organisation like Chandigarh Housing Board, Municipal Corporation or any De
partment of Chandigarh Administration they will not be required to submit the plan
to the Estate Office. Instead with relevant details obtained from the Estate Office
as contained in para * D’» they will submittheir plans directly to the office of Chief
Architect for being considered by the PAC (Upper). Once they are approved by
Chief Architect, they will be directly sent to client organisation with a copy to
Estate Officer for records.
1. The composition of the Committees shall be as under
Plan Approval Committee (Upper):
(i) Chief Architect, Department of Urban
Planning, U. T., Chandigarh
(ii) Assistant Estate Officer, U. T.»
Chandigarh
(Iii) Chief Engineer, U. T„ Chandigarh
(iv) Chief Engineer, M. C Chandigarh
Member Secretary, Chandigarh
Pollution Control Committee,
Chandigarh Member
(vi) Senior Architect, Department of Urban
Planning, U.T., Chandigarh
(vii) Senior Town Planner, Department of
Urban Planning, U. T., Chandigarh
(viii) Chief Fire Officer, M. C, Chandigarh ... Member
(ix) S.D.O. (Building), U. T. Chandigarh
(b) Plan Approval Committee (Lower):
(i) Estate Officer, U. T., Chandigarh
(ii) Assistant Estate Officer, U. T-,
Chandigarh
(Hi) Representative, Chandigarh Pollution
Control Committee, Chandigarh .
(iv) Architect, Department of Urban
Planning, U. T., Chandigarh
(v) Planning Officer, Department of Urban
Planning, U. T, Chandigarh
... Chairperson
... Member
... Member
... Member
... Member
... Member
... Member
J Convener
... Chairperson
... ' Member
511s
... :i1. Member
eno,
... Member
Member
662 Chandigarh Urbnn Development Laws
(vi) Executive Engineer, Public Health
< Circle, U. T., Chandigarh
(vii) Executive Engineer, Electrical Circle,
U. T., Chandigarh
(viii) Executive Engineer, P.W.D., U. T.,
Chandigarh
(ix) Chief Fire Officer, M. C, Chandigarh
(x) S.D.O, (Building), U. T., Chandigarh
Member
Member
Member
Member
Member
Convener
(Published in Chandigarh Administration Gazette (Extra) dated 4- J2-2008)
A
(134) Rclexatton of built-up apace allotted under different rehabilita
tion Schemes in colonies under theco nt rol/su pervision of Chandigarh
Administration, Municipal Corporation and Chandigarh Housing Board -
Whereas, a large number of slum dwellers have been allotted sites or built up
spaces under the different rehabilitation schemes in different parts of Chandigarh
and have been living in the rehabilitation colonies.
Whereas, they have been pleading that their family size has grown up and
there is a shortage of place and it is difficult for them to purchase any other
residential unit in Chandigarh and demanding that they should be allowed to build
an extra floor.
And whereas, in addition such allottees have been requesting to allow them
commercial activities on the ground floor of their premises to achieve selfemploy
ment opportunities as sufficient commercial places have not been made available
to them in the rehabilitation colonies to cater to thejF needs,
Considering theirdeinands, the Administration, U.T.. Chandigarh is pleased
to accept their demands to the extent as under;.—
(i) Allowing one extra floor on allotted site or built up space al lotted under
different rehabilitation schemes. This will be allowed by PAC (L) on
case to case basis with prior approval after assessing the structural
safety ofthe existing structure. If the existing structure does not permit
additional floor capacity then they will have to revise the building plan
and make the structure with sufficient load bearing capacity for the
structural safety and accordingly any construction can be carried out.
(ii) To al low use of ground floors for small environmental friendly, cottage
activities for self employment purposes such as boutique, beauty parlour,
tailoring shops etc. which wtll supplement the income of the family
while staying at home. However, no sub-division or amalgamation of
the room or space or building shall be allowed. Written permission
shall be obtained from the competent authority under whose control
the concerned rehabilitation colony falls.
(iii) This shall be applicable to all rehabilitation colonics under the control/
supervision of Chandigarh Administration, Municipal Corporation and
Chandigarh Housing Board.
(Published in Chdndigarh Administration Gazette (Extra) dt. 27-2-2009 at
■ nage 141)
j , ' jbib
(135) Provisions u/s. 1(2) shall extend only to the abadi urea of vil
lages Maloya, Pnlsora, Kajberi, Dadumajra and Hallomajra - No. 26/6/39-
U i l'I(3)-2009/3592:—In supersession ofthe Chandigarh Administration, Finance
Department, notification No. 26/6/39-UTFI(3)-2007/6097, dated 25th September,
i-
LENOVO-3
Text Box
NOTIFICATIONS AND ORDERS01 87.pdf
NOTIFICATIONS AND ORDERS01 88
NOTIFICATIONS AND ORDERS01 89
NOTIFICATIONS AND ORDERS01 90
All of Capital of Punjab (Development and Regulation) Act, 1952