Rule 89, Rajasthan Factories Rules,1951: Exemption of certain adult workers
Rajasthan Factories Rules,1951 - Rule 89
Text of rule 89
Exemption of certain adult workers
89. Exemption of certain adult workers. — Adult workers engaged in factories specified
in column 3 of schedule hereto annexed on the work specified in column 4 of the said
schedule shall be exempted from the provisions of the sections specified in column 5 of the
said schedule subject to the conditions, if any specified in column 6 of the said schedule.
Provided that :—
(1) No female adult worker shall be required or allowed to work for more than nine hours
on any day except in the case of urgent repairs covered by item (i) of the said
schedule and no male adult worker shall be required to allowed to work for more than
ten hours on any day.
(2) No male adult worker shall be required or allowed to work in any quarter for more
than fifty hours over time on weekly limits.
(3) Period of work for each male adult worker shall be so arranged that inclusive or his
interval rest they shall not spread over more than twelve hours in any day :
Provided further that the restrictions imposed by sub-clause (2) & (3) shall not apply in the
case of a shift worker engaged in factories specified against serial Nos. 9, 11 to 21, 23 to
34{i), 35(i), 43, 45 and 57(i) of the schedule and allowed to work in the whole or part of the
subsequent shift in place of a worker who has failed to report for duty.
Sl.
No.
Section of the
Act
empowering
grant of
exemption
Class of a
factory
Nature of
exempted work
Extent
Extent of
exemption
conditions
1 2 3 4 5 6
1. 64(2)(a) and
64(3)
All factories Urgent repairs
(Urgent repairs
shall mean
work to be
done to
machinery or
plant but only
so far as may
be necessary to
avoid serious
in-interference
with the
ordinary
working of the
undertaking)
Sections
51, 52,
54, 56,
&61
(a) Unless the Inspector
gives permission in writing
for reporting otherwise than
as herein laid down the
employment of persons on
urgent repairs, the manager
:—
(i) Shall send within twenty
four hours of the
commencement of work on
urgent repairs, written notice
to the Inspector describing
briefly the nature of the
urgent repairs and the
probable period of their
duration, and
(ii) Shall send weekly during
the continuance of the work
on urgent repairs, a
statement giving the names
of all the persons, who have
worked for more than nine
hours in any one day or for
more than forty-eight hours
of the preceding week in a
factory. Such statement shall
also show total number of
hours worked each day of
the week.
(b) If the Inspector is of
opinion that any work being
carried on or likely to be
carried on in factory as
"urgent repairs" is not
"urgent repairs" the
Inspector shall serve the
Manager on order to that
effect and the manager shall
in respect of such work not
allow any worker to work in
contravention of the
provisions of sections 51, 52,
54, 55, 56 and shall comply
with the provision of section
61.
2. 64(2)(b)
64(2)(h) 64(3)
All factories
other than
those on
continuous
process
Works
performed by:
(i) All workers
attending to
engines &
boilers or
generators of
gas preparatory
to the
Sections
51, 52,
55, 56 and
61.
(a) Such workers shall be
allowed not less than two
holidays in each period
covered by four consecutive
statutory factory holidays
and shall not be allowed to
work for more than six hours
on any of the other two
weekly holidays.
commencement
of regular work
(ii) Workers at-
tending to mill
gearings,
starting
stopping and
maintaining
electric motors
& connected
switch gear.
(iii Department
boilers.
(iv) Workers
attending to
mechanical or
electric lifts
(b) The notice required by
section 52 shall be delivered
to the office of the Inspector
showing on which days
holidays will be allowed;
(c) Intervals for food and rest
shall be given to all workers
allowed to work on such
work.
(d) No workers be allowed to
work for more than fifty four
hours in any one week, and
(e) Register or muster roll
required to be maintained
under section 62 shall show
correctly full particulars of
periods within which each
such worker may be
'required to work. The
entries in the register or
muster roll shall be up-to
date.
3. 64(2) and 64(3) All Factories Work
performed by
drivers on
lighting
ventilating and
humidifying
apparatus.
Section
51, 54,
55, 56 and
61
(a) intervals for food and rest
shall be given to all such
workers.
(b) Register or muster roll
required to be maintained
under Section 62 shall show
correctly full Particulars of
periods within which each
such workers may be
required to work. The entries
in the register or muster roll
shall be up-to-date.
4. 64(2)(b) and
64(3)
(i) all factories Work
performed on
the steam of
water pipes or
pumps of a
factory
Section
51, 54,
55, 56 and
61
Register or muster roll
required to be maintained
under section 62 shall show
correctly full particulars of
periods within which each
such worker may be required
to work. The entries in the
register or muster roll shall
be up-to-date.
(ii) Cotton
Spinning and
Weaving Mills
Work involved
in cleaning
blow room
flues.
Section
51, 54,
and 56.
(a) No worker shall be
allowed to work for more
than fifty one hours in one
week.
(b) No workers shall be
allowed to worked in such
manner that the spread over
exceeds ten and a half hours
except on one day in a week
previously notified to the
Inspector when it shall not
exceed twelve hours.
5. 64(2)(b) Dying and
bleaching
factories or
departments
Work
performed by
kiermen
Section
51, 54,
and 56
The intervals for food and
rest totaling one hours, if
working hours exceeds eight
and a half in a day or half an
hour, in working hours do
not exceed eight and half
hour shall be given to each
worker every day and the
register of muster roll
maintained in accordance
with Section 62 small show
correctly the period of work
of each worker.
6. 64(2)(b) Cloth printing
factories or
department of
factories
carrying on
printing
sanforizing
and
mercerizing of
cloth.
Work in the
nature of
preparatory or
complementary
to main
operations.
Section
51, 54,
and 56.
-do-
7. 64(2) (b) Cloth printing
factories or
departments of
factories and
bleaching,
raising,
finishing,
mercerizing,
dyeing, sizing
and
sanforizing
deptt, of the
factories.
All work Section
55.
Workers shall be allowed to
work on shift of no longer
than eight hours duration.
8. 64(2)(b) All factories
other cotton—
spinning and
weaving mills
(a) Work-
performed by
oilers and
(b) Work in
mechanic
shops, smithies
or foundries so
far as such
work is
complementary
to the main
operations.
Section
51, 54 and
56
This exemption shall not
apply:-
(I) in the case of work
performed by oilers, where
there workers or the factories
in which the work have been
exempted from the
provisions of section 52 or
55 and
(ii) to the work in the
mechanic shop, smithy or
foundry portion of
Engineering Workshop or to
a smithy or foundry used
solely as such.
9. 64(2)(d) 64(3)
and 64(4)
Oil Tank
Installation
Work
performed by
workers in
connection
with pumping
operations.
Section
51,52, 54,
55, 56 and
61
(a) Intervals for food and rest
shall be given to all workers
allowed to work on such
work .
(b) A compensatory rest
period of at least twenty four
consecutive hours shall be
given to each worker after
the cessation of the pumping
operations continuing after
10. p.m.
(c) Notice of such pumping
operations with the number
of workers allowed to work
shall be sent to the Inspector
as soon as possible after
commencement of such
work.
10. 64(2)(d) and
64(4)
Public
electricity
supply
factories
generating
electricity in
any manner
and those
engine rooms
and boilers
departments
generating
electricity in
any manner for
their own use
employing
worker on
shifts of not
more than
eight hours
each.
Operations and
Maintenance of
-
(i) Prime
movers and
auxiliaries
generators
transformers
and switch
gear;
(ii) Boilers and
auxiliaries
Section
51m 52m
54m 55
and 56
(a) The workers shall be
allowed to work on shift of
no longer than eight hours
duration.
(b) In the absence of a
workers who has failed to
report for duty, a shift
worker many be allowed to
work the whole or part of a
subsequent shift provided
that the next shift of the shift
provided that the next shift
of the workers shall not
commence before a period of
16 hours has elapsed after
the (Specified) stopping time
of the shift to which the
worker belongs.
(c) No worker shall be
allowed to work for more
than fifty six hours in any
week except that when
employed as in condition;
(d) Above, he shall not be
allowed to work for more
than sixty four hours.
(e) such workers shall be
allowed not less than two
holidays in each period
covered by four consecutive
statutory factory holidays
11. 64(2)(d)&64(4) Electrical
receiving
stations and
subsection or
in any factory,
the
departments of
the factory
receiving and
distributing
electrical
energy for the
use of the
factory.
Operations and
maintenance of
transformers
and their
auxiliaries
including
receiving and
distributing
switch gear
lighting,
arresting,
synchronous
and other
condensers and
rotary and
static
condensers.
Section
51, 52,
54, 55 and
56.
As in exemption No. 10
12 -do- Factories or
department of
factories
charging
electrical
accumulators.
Operations in
connection
with charging
electrical
accumulators.
Section
51, 52,
53, 54, 55
and 56.
As in exemption No. 10.
13. -do- Distilleries Work on the
extraction of
sugar from
various basis
-do- -do-
fermentation of
sugar juice and
distillation of
fermented
wash
14. 64(2)(d) &
64(4)
Sugar factor. Operations
beginning with
receiving and
weightment of
cane and
ending with
bagging of
sugar
As in
exemption
No. 13
As in exemption No. 13
15. -do- Chemical
factories.
All continuous
process work.
Sections
51, 52,
54, 55 and
56.
-do-
15A. -do- Chemical
factories.
All continuous
process work.
Section
51, 52,
54, 55 and
56.
-do-
16. -do- Rayon and
Synthetic Fibre
factories
The Work viz.
Refining,
bleaching
filtering
generation of
hydrogen,
hydrogenating
and deorishing
proceses also
compression of
oxygen and the
cylinder filling.
-do- -do-
17. 64(2)(d)
&64(4)
Magnesium
chloride
factories.
The work on
cent rating
process
As in
exemption
No. 16.
As in exemption No. 16.
18. -do- Public
pumping and
compressor
stations.
All work. -do- -do-
19. -do- Water supply
pumping
factories of
railway
workshops.
All works.. -do- -do-
20. -do- Ice Factories. Work of the
engine and
compressor
drivers and
assistants and
oilersi
-do- -do-
21. -do- Carbonic acid
gas work.
Work of
firemen, pump
men, plant
drivers, oilers
and the filing
of cylinders.
-do- -do-
22. 64(2)(b) Carbonic acid
gas work.
Work firemen
to light lye
Section
51, 54 and
These exemptions shall be
availed of only one day
boiler 55 when plant is restarted after
closure.
23. 64(2)(d) &
64(4)
Carbonic acid
gas
solidification
works.
All work
except packing
blocks.
Section
51, 52,
54, 55 and
56
As in exemption 10.
24. -do- Oxygen
factories
Engine and
plant drivers,
oilers and
filling of
cylinders.
-do- -do-
25. -do- Coal gas
factories and
departments.
All work in the
retorate house
an on the water
gas plant, work
of the male
yard labour
feeding
hoppers and
removing coke,
work on the
syphnoes,
boilers station
meters and
governors.
Section
51, 52,
54, 55 and
56.
As in examination No. 10.
26. -do- Hydraulic
pumping
stations.
All work. -do- -do-
27. -do- Paper
Cardboard and
straw board
factories
working on
there hours
shift system
Work
performed by
male adults
workers on
choppers,
strainers and
washers,
reaters. Paper
making
machines
pulping plants,
reellers and
cutters,
kheeders and
dig-esters
-do- -do-
28. 64(2) & 64(4) Cement
factories and
asbestos
cement
factories.
All work on
continuous
process units
Section
51, 52,
54, 55 and
56.
As in exemptions No, 10
29 -do- Glycerin
factories.
All continuous
process work.
-do- -do-
30. -do- Dextrine
manufacturing
factories.
All continuous
process work.
-do- -do-
31. -do- Acetylene
factories.
Generation of
gas and filling
of cylinders
-do- -do-
32. -do- Starch
factories
working in 8
All work
except the
engineering
-do- -do-
hours shifts. department and
workshops.
33. -do- Potassium
chloride
factories.
Work in the
cell room.
-do- -do-
34. 64(2)(d) &
64(4)
(I) Ferrous &
non Ferrous
metal factories.
All work in
furnace
Section
51, 52,
54, 55 and
56.
As in exemption No. 10.
(ii) -do- Hot rolling Section
55
Workers small be allowed to
work on shifts not longer
than eight hours duration
35. -do- Sodium
Potassium
bicromate
factories.
Work on
furnace and
crystallisers
Section
51, 52,
54, 55 and
56.
As in exemption No. 10
36. -do- Oil Mills.. All continuous
process work.
-do- -do-
37 -do- Flours Mills. All work. -do- -do-
38. 64(2)(b) (i) Gur
Factories
The work
performed by
workers in
crushing Sugar
cane
Section
51, 52,
54, 55 and
56
As in exemption No. 10
64(2)(b) and
64(3)
(ii) Gur
Factories
All other work
except crushing
sugar cane.
Section
51, 54, 55
and 61.
A notice showing the periods
of work of the crusher shall
be exhibited in the factory
and a copy shall be sent to
the Inspector.
39. 64(2)(d) Cement Tiles
Factories
Work on the
“curing” tiles
Section
51, & 52
(a) No worker shall be
allowed to work for more
than four hours or any of the
weekly holidays.
(b) No worker shall be
allowed to work on
consecutive weekly holidays.
(c) No workers shall be
allowed to work in excess of
limits of weekly hours of
work as laid down in Section
51 except during the week
when the worker work on a
weekly holidays as in (a)
above and when his total
hours of work may be
allowed to exceed the
weekly limit laid down in
section 51 by the number of
hours not exceeding 4,
worked on the weekly
holidays.
40. 64(2)(c) and
64(3)
Salt factories. Work
performed by
“Baramasees”
on Salt Kyars
Section
51, 54,
55, 56 and
61
(a) Intervals for food and rest
shall be given to all workers
allowed to work on such
work.
(b) Register on muster roll
required to be maintained
under section 62 shall show
correctly full particulars of
period withing which each
such worker may be required
to work; entries in register or
muster roll shall be up to
date.
41. 64(2)(g) and
64(3)
Salt factories All workers Section
52 and 55
No worker shall be allowed
to work on consecutive
weekly holidays.
42. 64(2) (g) and
64(3)
Rice Mills All persons
employed in
drying, lifting
and storing of
paddy.
Section
52 and 55
No worker shall be allowed
to work on consecutive
weekly holidays
43. 64(2)(d) and
64(4)
Glass Factories All work
except packing
work in
Engineering
Department
Section
51, 52,
54, 55 and
56.
As in Exemption No. 10
44. 64(2) (g) and
64(4)
Smelting &
Refining
factories
(I) Work on the
reducing
furnace
Section
55
(a) the workers shall be
allowed to work on shift of
not longer than eight hours
duration.
(ii) All
continuous
process work in
Electrolytic
refining
factories.
(b) Intervals for food and
rest shall be given to all
workers allowed to work on
such work
45. 64(2) (d) and
64(4)
Rubber Tyre
factories
All work on
curing process
Section
51, 54, 55
and 56
(a) The workers shall be
allowed to work on shift of
not longer than eight hours
duration.
(b) in the absence of a
worker who has failed to
report for duty, a shift
worker may be allowed to
work the whole or part of a
subsequent shift worker shall
not commence before period
of 16 hours has elapsed after
the (specified) stopping time
of the shift to which the
worker belongs.
46. 64(2)(d) Soap factories Work on soap
boiling pans
and soap dying
pans
Section
55
Workers shall be allowed to
work on shift of not longer
than eight hours duration.
47. 64(2)(d) Pottery work (I) Work of
fireman on
Kilns
Section
55
(a) Workers shall be allowed
to work on shift of not
longer than eight hours
duration.
(ii) Work on
tunnel Kilns
Section
52 & 55
(b) No worker shall be
allowed to work on
consecutive weekly holidays.
48. 64(2)(d) Brick Factories Work of
fireman Kilns.
Section
55
As in exemptions No. 46
49. 64(2)(d) Plastic
Factories
Work of Plastic
injection
machines &
Plastic
extruding
machines
Section
55
-do-
50. 64(2)(d) Pharmaceutical
Factories
All
continuance
process work.
Section
55
-do-
51. -do- All factories Telephone
operators.
Section
55
The intervals for food and
rest totaling one hour if
working hours exceed eight
and a half in a day or half an
hour if working hours does
not exceed eight and half
hours shall be given to each
worker every day and the
same noted in the register or
muster roll maintained in
accordance with section 62.
52. 64(2)(c) News paper
printing press
(a) All work on
daily news
paper.
Section
51, 54, 55
& 56
(a) No worker shall be
allowed to work from more
than 56 hours in any week.
(b) All work on
weekly news
paper
(b) No overtimes shall be
carries on except for two
days prior to the
53. 64(2)(I)&64(3) All factories. Loading and
unloading of
Railway
Wagons
Lorries and
Trucks.
Section
51, 52,
54, 55 ,
56 & 61.
Exemption from section 61
may be availed of provided
that every worker at the end
of the day's work is supplied
with a note showing the total
No. of hours of work put in
by such worker.
55. 64(2)(d) Cycle
manufacturing
factories
Work in
coloring and
enamelings
section and
Semi automatic
plating plant
Section
55
As in exemptions No. 46
56. 64(2)(d) Chemical
product
factories
Process of
manufacturing
activated
carbon.
Section
51, 52,
54, 55 and
56.
(a) the Workers shall be
allowed to work on Shift of
not longer than eight hours
duration.
(b) No worker shall be
allowed to work in such a
manner that the spread over
exceeds twelve hours in any
day and this shall be
permissible only in cases
when a shift reliever
working on continuous
process does not attend at the
correct time and alternative
relief can not be arranged.
(c) No worker shall be
allowed to work more than
fifty six hours in any week
except that when employed
as in condition (b) above he
shall mot b e allowed to
work for more than sixty
four hours in any week.
(d) Such worker shall be
allowed not less than two
holidays in each period
covered by four consecutive
statutory holidays.
57. 64(2)(d) &
64(4)
Power Cables
factories
Work on
impregnation
of paper
insulated laid
up cables
Section
51, 52,
54, 55 &
56.
As in exemption No. 10.
-do- Work on wire
annealing
furnace, lead
sheating and
armoring.
Workers shall be allowed to
work one shift not longer
than eight hours duration.
58. 64(2)(d) Cotton
spinning &
Weaving Mills
Work n hot air
sizing
machines.
Section
55
(i) Workers Shall be allowed
to work one shift of not
longer than eight hours
duration.
(ii) Workers shall be given
specified rest intervals for
food and rest.
59. 64(2)(d)&64(3) All factories Work of
automatic
equipment
engaged in
galvanizing
anodizing and
enameling wire
platening
packing, hot
drop
galvanizing
and stores
relating.
Section
51, 52,
54, 55,
56, 56,
58, & 61
The limits of work inclusive
of overtime shall not exceed
those mentioned in
subsection (4) of section 64.
60. 64(2)(k) Any factory,
class or
description of
factories as
may be
notified by the
State
Government in
the
Government in
the official
Gazette.
Work of
national
importance as
may be notified
by the State
Government in
the official
Gazette.
Section
51, 52,
54, 55 &
56.
The limits of work inclusive
of overtime shall not exceed
those mentioned in
subsection (4) of section 64.
61. 64(2)(d) Enameling
wire
manufacturing
factory.
Work
Enameling
wires.
Section
51, 54, 55
& 56
(a) The workers shall be
allowed to work one shift of
not longer than eight hours
duration.
(b) In the absence of a
worker who has failed to
report for duty, a shift
worker may be allowed to
work the whole or part of a
subsequent shift provided
that the next shift of the shift
worker shall not be
commence before a period of
16 hours has elapsed after
the (specified) stopping time
of the shift to which the
worker belongs.
(c) No worker shall be
allowed to work for more
than fifty six hours in any
one week except that when
employed in condition (b)
above he shall not be
allowed to work for more
than sixty four hours in any
one week.
62. 64(2)(d) Dairy Plants
manufacturing
Dairy products
like skimmed
milk powder,
whole milk
Powder, baby
food, Ghee &
butter etc.
The work of
adult male
workers
employed in
dairy factories
other than
those engaged
in printing and
in the
manufacturing
of containers
for milk, cream
Ghee's and
butter should
be deemed to
be the nature of
referred to in
clause (e) of
sub-section (2)
of section 65 of
the Act.
Section
51, 52,
54, 55 &
56.
1. No such workers shall be
allowed for more than 8
hours on Sunday .
2. No such worker shall be
employed for more than 14
consecutive days without
holidays of 24 days of 24
consecutive hours.
3. Every such worker shall
be given a compensatory
holiday in accordance with
section 53 of the Act.
4. No exemptions shall be
given from the provisions of
se3ction 59 to the workers
who are exempted from the
provisions of section 51, 54,
55 & 56.
63. 64(2) & 64(4) Aluminium
and Copper
foil
manufacturing
factories.
All continuous
process.
Section
55
As in exemptions No. 10.
The following shall be considered to be urgent repairs:—
(a) Repairs to any part of the machinery, plant or structure or a factory which are of such
a nature that delay in their execution would involve danger to human life or safety or
the stoppage of manufacturing processes.
(b) Break down repairs to the motive power, transmission or other essential plant of
other factories, collieries, railways, dockyards, harbours, tramways, transport, gas,
electrical generating and transmission pumping or similar essential or public utility
services carried out in general engineering works and foundries and which are
necessary to enable such concerns to maintain their main manufacturing processes
production or services during normal working hours.
(c) Repairs to deep sea ships and repairs to commercial air crafts done in a factory
which are essential to enable such ships, air crafts to leave post at proper time or
continue their normal operations in a sea or air worthy condition as the case may be.
(d) Repairs in connection with a change of active power from steam to electricity or vice
versa, when such work cannot possibly be done without stoppage of the normal
manufacturing process.
2. Periodical cleaning not included in the terms "examining" or "repairing".]
CHAPTER VII
Employment of Young Persons
Notice prescribed under sub-section (3) of section 72
Previous and next
Questions people ask
Is rule 89 of Rajasthan Factories Rules,1951 still in force?
No repeal of Rajasthan Factories Rules,1951 is recorded.