Rule 6, The Tamil Nadu Factories Rules,1950: Testing and examination of ventilating systems
The Tamil Nadu Factories Rules,1950 - Rule 6
Text of rule 6
Testing and examination of ventilating systems
6. Testing and examination of ventilating systems.-(1) All ventilating systems used for the purpose of extracting or
suppressing dust as required by this Schedule shall be as per the relevant standard prescribed by the Bureau of Indian
Standards, examined and inspected once every week by a responsible person. It shall be thoroughly examined and tested
by a competent person once in every period of twelve months. Any defects found by such examination or test shall be
rectified forthwith.
(2) A register containing particulars of such examination and tests and the state of the plant and the repairs or
alterations, if any, found to be necessary shall be kept and shall be available for inspection by an inspector.
114 TAMIL NADU GOVERNMENT GAZETTE [Part III-Sec.1(a)