Text of regulation 85
Additional teats before rejection
85. Additional teats before rejection.- Should cither a tensile or a bend te^t
fail, two fnrtliei tests of the type which failed may be made on tost piectfl cut fiom
the same foiging. If the results obtained Jfiom those retests aro satisfactory, the
forgings shall bo accepted, provided that in other respects they fulfil the conditions
laid down above for steel forgingh. If these letests do not give satisfactory results
the forgings represented may Lc re-heat-treatcd together with the remainder of
the tost blocks and presented for furthei testings.
in all cases whore final retests do not give satisfactory results, the forgings
represented by the test pieces which fail shall be rejected
GRNERAL GREY TRON CASTINGS (GRADtt A)
Previous and next
Questions people ask
Is regulation 85 of Indian Boiler Regulations, 1950 still in force?
No repeal of Indian Boiler Regulations, 1950 is recorded.