Section 29, The West Bengal Premises Rent Control ( Temporary Provisions ) Act, 1950
The West Bengal Premises Rent Control ( Temporary Provisions ) Act, 1950 (17 of 1950) - Section 29
Text of section 29
29. (1) The hearing of every application made to the Final
Controller under this Act shall be completed within a period hearing
of three months, other than an application for obtaining of certain
applica-
permission under sub-section (2) of section 38, which shall
tions.
be completed within a period of one month, unless, in either
case, for reasons to be recorded by the Controllerin writing,
it is not possible for him to complete the hearing within that
period.
(2) The hearing of every application shall, whet it has
begun, be continued from day to day unless, for reasons to
be recorded by the Controller in writing, it is not possible
so to do.
(3) In all proceedings before him the Controller shall
consider the question of costs and may award to and against
any party such costs as would be reasonable.
Previous and next
All sections of The West Bengal Premises Rent Control ( Temporary Provisions ) Act, 1950
Questions people ask
Is section 29 of the West Bengal Premises Rent Control ( Temporary Provisions ) Act, 1950 still in force?
No repeal of the West Bengal Premises Rent Control ( Temporary Provisions ) Act, 1950 is recorded.