Text of rule 4
In the said rules, in rule 22A, after sub-rule (1), the following sub-rule shall be inserted, namely
4. In the said rules, in rule 22A, after sub-rule (1), the following sub-rule shall be inserted, namely:-
"(1A) A proposal for modernization-cum-expansion project integrated with cogeneration plant or ethanol plant of any
sugar factory of an undertaking having an installed capacity of less than 2500 tones Crushed Per Day but not less than
1250 tones Crushed Per Day and to which financial assistance has been approved as approved in sub-rule (1), shall
also be eligible to apply for loan under this rule, subject to the following conditions, namely:-
(i) the application for such project is submitted to a bank or financial institution by the sugar factory;
(ii) in every such project, the appraising authority of the bank or financial institution certifies that the project
submitted by the sugar factory is financially viable for such sugar factory of capacity less than 2500 tones crushed Per
Day;
(iii) such project shall be technically appraised by the National Sugar Institute, Kanpur or any other
institute recognised by the Central Government and it has certified that the project is technically viable;
(iv) State Government guarantee is furnished by the sugar factory or sugar undertaking for Sugar Development Fund
loan".
5. In the said rules, in rule 23, after sub-rule (1), the following sub-rule shall be inserted, namely-
"(1A) A proposal for modernization-cum-expansion project integrated with cogeneration plant or ethanol plant of any
sugar factory of an undertaking having an installed capacity of less than 2500 tones Crushed Per Day but notless
than 1250 tones Crushed Per Day and to which financial assistance has been approved as approved in sub-rule (1),
shall also be eligible to apply for loan under this rule, subject to the following conditions, namely:-
(i) the application for such project is submitted to a bank or financial institution by the sugar factory;
(ii) in every such project, the appraising authority of the bank or financial institution certifies
that the project submitted by the sugar factory is financially viable for such sugar factory
of capacity less than 2500 tones crushed Per Day;
(iii) such project shall be technically appraised by the National Sugar Institute, Kanpur or any other institute
recognised by the Central Government and it has certified that the project is technically viable;
(iv) State Government guarantee is furnished by the sugar factory or sugar undertaking for Sugar Development Fund
loan".
6. In the said rules, in rule 25, in sub-rule (3), for the words "rate of six percent", the words "rate of four per cen
shall be substituted.
[F.No-1-1/2020-SDF]
SUBODH KUMAR SINGH, Jt. Secy. [S&A]
Note : The Principal rules were published in the Gazette of India vide notification number G.S.R. 752(E) dated the
27th September, 1983 and was last amended vide notification number G.S.R. 885(E), dated the 17th September, 2018.
Uploaded by Dte.of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
Previous and next
Questions people ask
Is rule 4 of Amendment in rule 6 in s.no.(8) and rule 25 in sub rule (3), Insertion of sub-rule IA in rule 22, 22A & 23 of SDF Rules dated 7th Aug, 2020 still in force?
No repeal of Amendment in rule 6 in s.no.(8) and rule 25 in sub rule (3), Insertion of sub-rule IA in rule 22, 22A & 23 of SDF Rules dated 7th Aug, 2020 is recorded.