Regulation 10, Central Electricity Authority (Technical Standards for Communication System in Power System Operation) Regulations, 2020: Outage planning
Central Electricity Authority (Technical Standards for Communication System in Power System Operation) Regulations, 2020 - Regulation 10
Text of regulation 10
Outage planning
10. Outage planning. - Monthly outage shall be planned and got approved by the owner of communication
equipment in the concerned regional power committee, as per detailed procedure finalised by the
respective regional power committee.
Previous and next
Questions people ask
Is regulation 10 of Central Electricity Authority (Technical Standards for Communication System in Power System Operation) Regulations, 2020 still in force?
No repeal of Central Electricity Authority (Technical Standards for Communication System in Power System Operation) Regulations, 2020 is recorded.