Section 24, The India International Arbitration Centre Act, 2019: Grants by Central Government

The India International Arbitration Centre Act, 2019 (17 of 2019) - Section 24

Text of section 24

Grants by Central Government

The Central Government may, after due appropriation made by Parliament by law in this behalf, pay to the Centre in each financial year such sums of money and in such manner as it may think fit for being utilised for the purposes of this Act.

Previous and next

All sections of The India International Arbitration Centre Act, 2019

Questions people ask

Is section 24 of the India International Arbitration Centre Act, 2019 still in force?

No repeal of the India International Arbitration Centre Act, 2019 is recorded.