Rule 10, The Indian Telegraph Right of Way Rules, 2016: Grant of permission by appropriate authority
The Indian Telegraph Right of Way Rules, 2016 - Rule 10
Text of rule 10
Grant of permission by appropriate authority
10. Grant of permission by appropriate authority.-(1) The appropriate authority shall examine the application
with respect to the following parameters, namely:-
(a) the extent of land required for the overground telegraph infrastructure;
(b) the location proposed;
(c) the approval issued by the duly authorised officer of the Central Government for location of the above
ground contrivances proposed to be used for transmission of Radio waves or Hertzian waves;
(d) the mode of and time duration for execution of the work;
(e) the estimation of expenses that the appropriate authority shall necessarily be put in consequence of the work
proposed to be undertaken;
(f) assessment of the inconvenience that the public is likely to be put to in consequence of the establishment or
maintenance of the overground telegraph infrastructure, and the measures to mitigate such inconvenience
indicated by the licensee;
(g) certification of the technical design by a structural engineer attesting to the structural safety of the
overground telegraph infrastructure;
(h) certification, by a structural engineer, of the structural safety of the building on which the post or other
above ground contrivances is proposed to be established;
(i) any other matter, consistent with the provision of the Act and these rules, connected with or related to
the laying of overground telegraph infrastructure, through a general or special order or guidelines by the Central
Government, appropriate State Government or the appropriate local authority:
(2) Where the establishment of the overground telegraph infrastructure renders the immoveable property, vested in
the control or management of any appropriate authority over which such overground telegraph infrastructure is
established, unlikely to be used for any other purpose, the appropriate authority shall be entitled to compensation for the
value of the immoveable property, either once or annually, assessed on such rates as that appropriate authority may, by
general order, specify.
(3) The appropriate authority shall, within a period not exceeding sixty days from the date of application made
under rule 9 -
(a) grant permission on such conditions including, but not limited to, the time, mode of execution,
measures to mitigate public inconvenience or enhance public safety or structural safety and payment of restoration charge
or compensation , subject to the provisions of the Act and these rules; or
(b) reject the application for reasons to be recorded in writing:
Provided that no application shall be rejected unless the applicant licensee has been given an opportunity of
being heard on the reasons for such rejection:
12 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
Provided further that the permission shall be deemed to have been granted if the appropriate authority fails to
either grant permission under clause (a) or reject the application under clause (b) and the same shall be communicated in
writing to the applicant not later than five working days after permission is deemed to have been granted.
(4) The appropriate authority shall not charge any fee other than those mentioned under sub-rule (3) of rule 9 and
clause (a) of sub-rule (3) from the licensee for establishing overground telegraph infrastructure.
Previous and next
All provisions of The Indian Telegraph Right of Way Rules, 2016
Questions people ask
Is rule 10 of the Indian Telegraph Right of Way Rules, 2016 still in force?
No repeal of the Indian Telegraph Right of Way Rules, 2016 is recorded.