Rule 5, The Mahatma Gandhi National Rural Employment Guarantee Audit of Schemes Rules, 2011: Social audit pre-requisites
The Mahatma Gandhi National Rural Employment Guarantee Audit of Schemes Rules, 2011 - Rule 5
Text of rule 5
Social audit pre-requisites
5. Social audit pre-requisites.—(1) The social Audit shall be a process
independent of any process undertaken by the implementing
agency of the scheme.
(2) The implementing agency shall at no time interfere with the
conduct of social audit.
(3) Notwithstanding anything contained in sub-rule (2), the
implementing agency of the Scheme shall provide requisite
information to the Programme Officer for making it available to
Social Audit Unit at least fifteen days prior to the date of
commencement of the social audit.
(4) The resource persons deployed for facilitating social audit in
Panchayat shall not be residents of the same Panchayat.
Previous and next
Questions people ask
Is rule 5 of the Mahatma Gandhi National Rural Employment Guarantee Audit of Schemes Rules, 2011 still in force?
No repeal of the Mahatma Gandhi National Rural Employment Guarantee Audit of Schemes Rules, 2011 is recorded.