LawGrids logoLAWGRIDS.ORG

Rule 61, Bangalore Metro Railway (General) Rules, 2011: Objective of single line working

Bangalore Metro Railway (General) Rules, 2011 - Rule 61

Text of rule 61

Objective of single line working

61. Objective of single line working.- In case of an obstruction on a portion of line between any two stations on one of the running lines, train service may be continued in the affected section on the adjacent line in both directions using single line working on the unaffected track and such single line working shall be achieved by 'fleeting' of trains in groups in one direction at intervals decided by the traffic controller followed by an equivalent group of trains in the other direction.

Previous and next

All provisions of Bangalore Metro Railway (General) Rules, 2011

Questions people ask

Is rule 61 of Bangalore Metro Railway (General) Rules, 2011 still in force?

No repeal of Bangalore Metro Railway (General) Rules, 2011 is recorded.